Control flashcard
Can lessons learn to be updated with thoughts?
No. Only with materialized content. Things that actually happens.
What is the difference between lessons learn register vs lessons learned repository?
Project vs PMO
- The register is within the project while
- The repository is for PMO
What is the key the outputs of monitor risk process?
- Work performance information
In which process is the change request executed
Direct and manage process work– not on monitor…
What tools can I use in manage quality
- Data gathering (checklist)
- Data analysis (multiple)
- Data representation( Multiple Decision Making (multicriteria) Audits–
- Design for X and problem solving
Can the assumption log be updated with thoughts?
Yes. It is an assumption. Not materialized
In which process can I use Technical performance analysis
Monitor Risk
What is control quality? And MAIN characteristics
- Monitor and record results of executing the quality management activities
- Ensure project outputs meet CU expectations
- Ensure outcomes are complete and correct 3. verifies deliverables to meet stakeholders requirements 4. Verify if project outputs do what they were intended to do
What is retrospective?
Lessons learned equivalent
What is time boxing?
Tool Used for agile When requirement changes frequent
If you have to do a survey, what would you choose between sending a survey with questions and making telemarketing calls?
** There are no other variables
Send a survey,
because telemarketing calls are not EFFECTIVE
In which process do I measure the effectiveness or risk responses?
Monitor Risk
Yes or No As you monitor the project you realize you need more budget Do you use management reserves?
No They are for unforseen risks.
After your CR gets approved– what does the PM need to do
Update the change log with the status of the CR
Yes or No DOES Cost budget include management reserves?
YES.
Can a team member submit a CR?
YES.
What document displays gaps between current and desired engagement levels of project stakeholders?
Stakeholder engagement assessment matrix
What tools can I use in control procurements? (3)
UN CHINGO…. HAY MAS!!!!
- Inspections
- Audits
- Claims administration
como note imaginabas
PERFORMANCE REVIEWS!!
Can CPI have control limits?
Can it modify cost baseline?
Yes, but rarely used as cause to modify Cost baseline
_____ is Data analysis technique that id opportunities for process improvements by examining problems, constraints and non-value-added activities that occur during a process
Process analysis
If you discover a lack of resources during control or monitor process. what is the first document that you will use to document this situation?
Issue log.
Because
- it is an issue!!!
- IT IS in control process
Resource optimization technique that typically increases the critical path
Resource leveling
______ IS degree to which product or service fulfills the requirement
______ Is the classification of products that have a common function but offer different technical specification
- Quality
- Grade
Also known as Tally Sheet
Check sheet