Closing Flashcards

1
Q

Which procurement document can be used to close a project if all deliverables have been completed?

A

Procurement agreement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When is the project finally completed?

A

all actions and all activities listed in the project closure phase are completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the closure activities? (9)

A
  1. Obtaining Final acceptance of deliverables
  2. Obtaining financial, legal and administrative closure
  3. Providing a final report to the stakeholders
  4. Collect all lessons learned
  5. Archive project documents
  6. Transfer the ownership to the client
  7. Ensure all cost is transferred to the project
  8. Reassigning personnel
  9. Update OPAs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the inputs for the closure project PROCESS

A
  • Business Documents
  • Agreements
  • Project Charter
  • Accepted Deliverables

and more like stakeholders and comm plan, SCOPE BASELINE, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Documents the project success criteria, the approval requirements

A

Project charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Does collecting stakeholder satisfaction is part of the closure activities?

A

YES.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Does obtain final acceptance of deliverables is part of the closing activities?

A

YES. as OVERALL not as individual deliverables

Did we meet the project objective?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What document includes

Summary of final performance of the project

A

Final report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What document contains

  • Scope objectives,
  • the criteria used to evaluate the scope, and
  • evidence that the completion criteria were met.
A

Final Report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

In which process should I close the contract with a vendor

A

Control procurements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What tools can be used here… Where would you use it?

A

NOT LIMITED TO BUT…..

  1. Document analysis = Id lessons learned with the documents
  2. Technical performance analysis = Not likely, but if it is related to something technical (MIGHT…)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Are these process relevant here?

  1. Reserve analysis
  2. Stakeholder analysis…
  3. Document Analysis
A

one and two NOT.

Tree is

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

If projects are divided in phases…. Can you start the second phase without finishing the first…

A

YES…. There is a chance that there might not be sequential…

READ THE QUESTION!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When closing the project. When can you release the project team?

A

When ALL OF THE CLOSING ACTIVITIES are completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

True or false

The final report helps to ensure a good transition

A

FALSE!!