Contract Practice Flashcards
What are the various forms of JCT contract you are aware of?
JCT Standard Building Contract
JCT Design and Build Contract
JCT Intermediate contract
JCT Minor Works Contract
What are the forms of executing a contract
- Under Hand (Simple contracts)
- Under Seal (Formal contracts or Deeds)
What are the provisions in a JCT Standard Building contact?
- Requires a contract administrator.
- Quantity Surveyor required
- Collateral warranties
- Retention on payments
- Retention bond
- Insurance for new building insured by the contractor.
- Insurance for new building insured by the contractor.
- Insurance for existing buildings/works insured by Employer or in the case of existing buildings by other means
What are the differences of a contract under seal and under hand?
Under Hand
No formalities for execution
Made verbally or in writing.
Legally binding as long as it satisfies all the requirements for a valid contract.
No seal signature required.
Under seal
Formalities required for execution.
Executed with seals, signature and witness
Legally binding and enforceable in court
Seal is typically affixed to the document
Commonly used in formal legal documents such as deeds, mortgages and agreements for the transfer of property or land
What is a collateral warranty?
A document which provides rights to a party (usually a developer/funder or owner) against a party with whom they have no privity of contract.
What is assignment of a contract?
Transferring an agreement’s rights, obligations, and property to another party.
What is novation?
When a contract is novated, both parties agree that the responsibilities and obligations of one party are transferred from the original signee to a third party
What is privity of contracts
A contract cannot confer rights or impose obligations upon anyone who is not a party to that contract
What are the components of a contract?
Offer, Acceptance, Awareness, Consideration, Capacity, Legality.
Can you tell what information you would include a part of a construction contract?
- The main contract
- Any schedule of amendments
- Employers’ requirements and appendices
- Contract drawings and specifications
- Surveys and reports
- Contractors proposals
- Contractor pricing schedule
- H&S information
If want to transfer the design risk to the contractor , what contract would you advise on?
JCT Design and Build
On your HRA Project what notice did you have to serve after being informed the contractor had gone into administration.
Pay less notice
What are extensions of time?
Extensions of time adjust the completion date and relieves the contractor’s liability to pay liquidated damages for the period of the extension
What are liquidated damages?
A genuine pre-estimate of the likely loss incurred by the employer should the completion date not be met.
What must be in place before LDs can be deducted?
- A non-completion certificate.
- A withholding notice.
What if the employer actually suffered no loss or damage?
- It doesn’t matter.
- The damages can still be deducted at the value stated in the contract
What are the benefits of being able to grant an extension of time?
- It relieves the contractor’s liability for liquidated damages for a delay that they did not cause.
- It enables another completion date to be set, which maintains the employer’s ability to deduct liquidated damages if another delay occurs
What happens when ‘time is at large’?
- There is no set completion date.
- The contractor only has the obligation to complete the works in a ‘reasonable time’.
- Liquidated damages cannot be claimed as there is no date to take them from.
- The employer would have to try and prove that the contractor had not completed in a reasonable time.
What are Relevant Events in a JCT form of Contract?
They are events that entitle the contractor to an extension of time.
What are the relevant events?
- Variations.
- Instructions.
- Deferment of possession of the site.
- Exceptionally adverse weather conditions.
- Strike or lock out.
- Force majeure
What are the main elements you would include within an interim
valuation?
- Preliminaries.
- Measured work
- Variations.
- Materials on site.
- Materials off site.
- Loss and expense.
- Retention.
What needs to be in place for you to include payments for materials on
site?
- The materials should be for the works.
- They should be adequately protected.
- Delivered to programme.
- In a reasonable quantity.
What needs to be in place for you to include payments for materials
off site?
- Proof that ownership will transfer to the employer upon payment (vesting certificate).
- Insurance until materials arrive at site.
- Materials are clearly labelled as for the site and set apart from other materials.
- A materials off site bond has been provided if required.
What is a vesting certificate?
Proof that ownership will transfer to the employer upon payment