Contract Administration Flashcards

1
Q

What are the contractual mechanisms under JCT?

A

EOT
Loss and Expense
Payment Certificate
Section completion
Partial possession
Practical Completion
Non completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What timescales for issuing a payment certificate under JCT?

A

Due date - 7 day from the valuation date
Timescales for issuing certificate – 5 days.
Payment terms – 14 day as standard.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the definition of completion?

A

When all the work required by the ‘works information’ is completed by the specified completion date, and all notified defects that would prevent the client from using the works are corrected.

End of contractor liability (termination of any liquidated damages)
Insurance handover
Handover of the premises
Beginning of the defects liability period
Retention releases (generally from 5% to 2.5%)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the difference between section completion and partial possession.

A

Sectional Completion -Defined date in the contract. Liquidated damages can apply

Partial possession LD cannot apply.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the various forms of JCT contract?

A

JCT SBC, IC, MW, D&B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the role of a contract administrator?

A

Management or administration of the building contract between the employer and the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the difference between a contract instruction and a variation?

A

All variation are contract instructions but not all contract instructions are variations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

On Jodrell – What is the importance of a vesting certificate?

A

A vesting certificate or agreement for construction goods, plant or materials, in letter form, used to confirm that ownership of the goods, plant or materials will transfer from one party to another on payment.

This is particularly important if the contractor become insolvent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What details must be including in a vesting certificate?

A

The certificate will have to detail the location where the material is being stored, the client and contractors’ details, and photographic evidence of the material with clear, marked identification of the item being in the client’s entity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the type of certificates issued in a project?

A

Practical completion
Section Completion
Non completion
Certificate of making good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

If there are problems with the design, after Novation of the architect,
who would be responsible?

A
  • At the point of novation, the client would agree the level of design was satisfactory & would be signed off by all parties.
  • The contractor would then become responsible for the Architect & his design should any problems arise during construction.
  • Disputes may arise where it becomes unclear when problems have arisen, either prior to the transfer of services or afterwards.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the difference between Novation and Assignment?

A

Novation -Transfer of obligations and benefits
Assignment - Transfer of contractual benefits

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Describe differences between Statutory Provisions and Contract
Provisions?

A
  • Statutory provisions are set out by law & must be complied with.
  • Contract provisions relate to the contract in question & therefore only apply to a specific project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

After valuation and certificate are issued, the client advised that they
don’t have sufficient funding to make the payment. What would you
do?

A
  • Once the certificate has been issued to the contractor, the client is contractually obliged to honour payment of the certificate and cannot withhold money without a valid reason.
  • If this were the case, I would contact the client and contractor ASAP to arrange some form of payment. It may be the case that the client has insufficient funds available in time for the final date for payment and it may be possible to defer payment by 1-2 days.
  • Failing this or if the contractor is unwilling to delay the payment, the client would need to find finance the payment through other funds to honour the certificate.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What items do you include for on a valuation?

A

Items would include:
* 1) Prelims.
* 2) Measured Works.
* 3) Materials on / off site.
* 4) Variations.
* 5) Claims.
* 6) Retention.
* 7) Previous payments.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

If an instruction was issued during the contract which involved the
fabrication of a substantial amount of materials off site would you pay
for them as off site materials within the valuation?

A
  • There is no obligation on the client to pay for materials off site if this is not identified in the contract.
  • However in the scenario where the client wishes to pay for them, I would ultimately check with the client before paying or rejecting them
  • Request vesting certificate
17
Q

How would you deal with the urgent Verbal Instructions?

A
  • If the instruction affects the critical path or programme in general I would review the instruction with the contractor administrator, client & contractor.
  • If the instruction is valid under the contract I would ensure this is converted into a formal written instruction as soon as possible.
18
Q

What is the difference between NEC and JCT?

A

The main difference between the 2 forms is its usage.
* NEC can be used within the building & civil engineering projects whereas JCT is specifically for building projects.
* NEC can be adopted to a number of bespoke contract strategies due to the various options available whereas JCT has a standard set of clauses.

19
Q

How is a contract under hand different from a deed?

A

A Deed is signed by a witness & traditionally authenticated by a seal.
The limitation period of under hand is 6 years whereas a deed is 12 years

20
Q

What is your understanding of latent defects and what contractual
issues are associated with them?

A
  • Latent defects are defects which are not readily identifiable upon inspection & only come to fruition some time after building completion and may take many years to become identifiable.
  • A claim in contract can only be brought about within the limitation period of the contract, 6 or 12 years depending on whether the contract was executed as a deed or underhand.
21
Q

What should the architect do if they are discovered?

A
  • The CA should issue an instruction as necessary to instruct the contractor what to do if they are identified.
  • This can include telling them to comply with a third party who is examining or opening up the works to identify the defect
22
Q

What are the main parts of the JCT contracts?

A
  • Recitals.
  • Articles.
  • Contract Particulars.
  • Attestation.
  • Conditions divided into 9 sections (7 for minor works).
  • Schedules.
23
Q

Name the main types of JCT contract

A
  • Minor works.
  • Intermediate.
  • Standard building contract.
  • Design and Build.
24
Q

When would you use JCT Intermediate Contract?

A

The project should be simple in content and require only basic skills and trades where services are not complex and where the works are already designed

25
When would you use a JCT Standard contract with quantities?
- A JCT Standard Building Contract would be used where the work has already been designed at execution. - It is suitable for use with a bill of quantities and is a lump sum form. - The contractor’s risk is limited to price only. - The employer takes the risk of errors in the bill
26
When would you use JCT Standard without quantities?
- This is suitable where work has been designed prior to contract however there is no bill of quantities. - The contract documents will include drawings, specification and a schedule of rates. - It is a lump sum form of contract. - The contractor’s risk includes both price and quantity.
27
When would you use JCT Standard with approximate quantities?
- This is a remeasurement form of contract. - There is no fixed contract sum. - It is used where the design is not completed at the time of execution. - An approximate bill of quantities will have been prepared. - Construction is aimed to commence prior to the design being completed
28
When would you use JCT DB?
- When the contractor is responsible for design and construction. - The project should be similar in complexity to that ofstandard building contracts. - The contactor’s proposals form the basis of the contract. - There is no mention of an architect or QS instead this role is replaced by the title of Employers Agent.
29
What are the key differences between JCT Minor Works, Intermediate and D&B Contracts?
- There is no mention of the QS in minor works and D&B however there is in the Intermediate Form - Minor works also has no provision for sectional completion or partial possession - In Minor Works there are no relevant events listed for extension of time, instead it is referred to as ‘anything outside the contractor’s control - The standard retention is 5% for Minor Works and Intermediate and 3% for D&B - There is no provision for third party rights in Minor Works or Intermediate Forms.
30
What is a bespoke contract?
Contract conditions that are drafted specifically for a particular project
31
What the advantages of standard forms over bespoke contracts?
- They are written by legal experts - Risks should have been allocated appropriately between the parties - Rights and obligations of each party are clearly set out to the required level of detail
32
What are the disadvantages?
- Apportionment of risks is rarely questioned and therefore becomes implicit meaning it is not reviewed on whether it is appropriate. - They may not be appropriate to the needs of a particular project or client. - Using an inappropriate standard form for the project will cancel out any advantages.
33
When would use a bespoke contract rather than a standard form?
- They should generally be used for major projects with novel obligations. - When specialist advisors can undertake the amendments as this requires great skill and knowledge. - Drafting from first principles is too daunting for most in the industry.
34
What are the key differences between NEC and JCT?
- The NEC is concise and written in plain English. - There are a number of optional clauses reducing the need to amend contracts compared to the JCT - The Project Manager is presented with options to deal with problems as soon as they become apparent. - Provision of early warning procedure and risk register encourage a proactive approach to the management of the project whereas JCT is more reactive - There is no QS or Employers Agent mentioned in NEC only a Project Manager who takes on both roles. - Retention and delay damages are optional clauses under NEC.