Contract Practice Flashcards
What is a contract?
An agreement between 2 parties
Offer
Acceptance
Consideration
Intention
What are the sections of a contract?
Definitions
Carry out works
Control of works
Payment
Change
Insurance
PB/CW
Termination
Disputes
What are the main parts to a contract?
Recitals - summary of works
Articles of agreement - obligations
Contract Particulars - project specific items
Attestation - Sign
Conditions - Sections
Schedules - provisional
ERs/CPs
What are Building Regulations?
Statutory regulations to ensure building requirements are met
A - structure
B- Fire
C - Site Preparation
What is the Construction Act?
Housing Grants Construction and Regeneration Act 1996
Regulations for industy. Ensures to help payment/disputes
Right to stage payments
Right to suspend works for non payment
What is the Local Democracy, Economic Development and Construction Act?
Amended the HGCRA
Contracts no longer have to be in writing
Pay when paid is illegal
What is the difference between HGCRA and LDEDCA?
left blank
What are the advantages and disadvantages of standard forms of contract?
Advantages:
Written by legal experts
Familiarity
Case Law
Disadvantages:
Amended versions impact familiarity
May not be appropriate in every situation
What is the NEC?
New Engineering Contract
A - Priced contract with activity schedule
B - Priced contract with BoQ
C - Target contract with activity shedule
D - Target contract with BoQ
E - Cost reimbursement
F - Management contract
What is a Form of Contract (FOC)?
A set of pre-determined arrangements and mechanisms that form a basis of agreement between parties.
What is a Z clause?
Additional conditions to an NEC contract
What is the difference between an NEC and JCT?
NEC has compensation events where JCT has variations
NEC - programme is a contract document
NEC - Project manager is named party
NEC - more collaborative
What are the advantages and disadvantages of NEC?
Can be harder to navigate
JCT doesn’t need amending - time and cost
NEC - easier to understand; more collaborative; more admin intensive
What are some changes from JCT 2011 to 2016?
The interim valuation date
Option for no fluctuations
Intro to BIM Protocol
CDM regulations update
What is the client role in a contract?
Pay contractor
Describe scope of works
Give possession of site
What is the difference between CA and EA?
CA - Traditional - Third party acting as legal agent, administers contract and make sure parties are fulfilling their obligations.
EA - D&B - act on behalf of client
Role of the contractor?
H&S
Construction work in accordance with documents
Submit applications for payment
What is Novation?
The transfer of rights and obligations from one party to another
Advantages - continuity at pre and post contract
Disadvantages - possible conflict of interest
What is Assignment?
Transfer of rights but not obligations from party to another
Transfer right to have construction work done and right to sue contractor of defective works
But not obligation to pay
What are Third Party Rights?
The right of a person who is not a party to a contract to enforce a benefit of that contract
Act sets out third party must be identified
What are the advantages and disadvantages of Third Party Rights?
Advantages:
Simpler to execute
Less admin
Disadvantages:
Little case law
No physical warranty
What’s a Collateral Warranty?
A side agreement which establishes a contractual link between 2 parties which wouldn’t have existed
What do Collateral Warranties include?
Parties/dates/PI
Notified to tenders at time of tender
What is a PCG?
A company that controls a ‘subsidiary’ company. The parent company protects the client if the subsidiary company becomes insolvent
letter or minutes
What is a bond?
An arrangement where a contractual duty owed by one party to another is backed by a 3rd party
Client needs to prove loss and obligations not fulfilled
What is a Performance Bond?
A means of ensuring a client against the risk of a contractor not fulfilling obligations
Includes: dates; cost; parties
On demand
Conditional - conditions are met - insolvency
Performance Bond vs PCG?
Bond added to contract sum, PCG is free
Contractor might not have a parent company.
What is a Retention Bond?
Retention amounts paid, Bond provided to recover retention
Retention recovery
What is an Advanced Payment Bond?
Secure cover for advanced payments
Contractor provides bond
What is a PCSA?
Pre-Contract Services Agreement
Document services a contractor has to perform
Good for limited design
The more work carried out, the weaker the client position
What is a Letter of Intent?
Method of instructing a contractor to carry out work before the contract is executed
Value of works; dates; payment method
What insurance options [works insurance] are there in the contract?
A - New Build - Contractor
B - New Build - Employer
C - Existing - Joint names via employer
What are Specified Perils?
Fire
Lightning
Explosion
Storm
Flood
Events that can cause significant damage
What is All Risk?
Insurance for physical loss or damage to work executed and site materials
What are Excepted Risk?
Toxic explosions
Pressure waves
What is subrogation?
Legal technique where the insurer steps into the shoes of the insured in order to take the benefit of legal rights and remedies
What is advanced payment?
Given to the contractor for long lead times for materials
Payments, values and dates should be set out in the CPs
Disadvantages - less incentive for contractor; bad for employer’s cash flow