Contract Practice Flashcards

1
Q

What is a contract?

A

An agreement between 2 parties

Offer
Acceptance
Consideration
Intention

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the sections of a contract?

A

Definitions
Carry out works
Control of works
Payment
Change
Insurance
PB/CW
Termination
Disputes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the main parts to a contract?

A

Recitals - summary of works
Articles of agreement - obligations
Contract Particulars - project specific items
Attestation - Sign
Conditions - Sections
Schedules - provisional
ERs/CPs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are Building Regulations?

A

Statutory regulations to ensure building requirements are met

A - structure
B- Fire
C - Site Preparation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the Construction Act?

A

Housing Grants Construction and Regeneration Act 1996

Regulations for industy. Ensures to help payment/disputes

Right to stage payments
Right to suspend works for non payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the Local Democracy, Economic Development and Construction Act?

A

Amended the HGCRA

Contracts no longer have to be in writing
Pay when paid is illegal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the difference between HGCRA and LDEDCA?

A

left blank

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the advantages and disadvantages of standard forms of contract?

A

Advantages:
Written by legal experts
Familiarity
Case Law

Disadvantages:
Amended versions impact familiarity
May not be appropriate in every situation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the NEC?

A

New Engineering Contract

A - Priced contract with activity schedule
B - Priced contract with BoQ
C - Target contract with activity shedule
D - Target contract with BoQ
E - Cost reimbursement
F - Management contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a Form of Contract (FOC)?

A

A set of pre-determined arrangements and mechanisms that form a basis of agreement between parties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a Z clause?

A

Additional conditions to an NEC contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the difference between an NEC and JCT?

A

NEC has compensation events where JCT has variations
NEC - programme is a contract document
NEC - Project manager is named party
NEC - more collaborative

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the advantages and disadvantages of NEC?

A

Can be harder to navigate
JCT doesn’t need amending - time and cost
NEC - easier to understand; more collaborative; more admin intensive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are some changes from JCT 2011 to 2016?

A

The interim valuation date
Option for no fluctuations
Intro to BIM Protocol
CDM regulations update

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the client role in a contract?

A

Pay contractor
Describe scope of works
Give possession of site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the difference between CA and EA?

A

CA - Traditional - Third party acting as legal agent, administers contract and make sure parties are fulfilling their obligations.
EA - D&B - act on behalf of client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Role of the contractor?

A

H&S
Construction work in accordance with documents
Submit applications for payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is Novation?

A

The transfer of rights and obligations from one party to another

Advantages - continuity at pre and post contract
Disadvantages - possible conflict of interest

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is Assignment?

A

Transfer of rights but not obligations from party to another

Transfer right to have construction work done and right to sue contractor of defective works
But not obligation to pay

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are Third Party Rights?

A

The right of a person who is not a party to a contract to enforce a benefit of that contract

Act sets out third party must be identified

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What are the advantages and disadvantages of Third Party Rights?

A

Advantages:
Simpler to execute
Less admin

Disadvantages:
Little case law
No physical warranty

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What’s a Collateral Warranty?

A

A side agreement which establishes a contractual link between 2 parties which wouldn’t have existed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What do Collateral Warranties include?

A

Parties/dates/PI

Notified to tenders at time of tender

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is a PCG?

A

A company that controls a ‘subsidiary’ company. The parent company protects the client if the subsidiary company becomes insolvent

letter or minutes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What is a bond?

A

An arrangement where a contractual duty owed by one party to another is backed by a 3rd party

Client needs to prove loss and obligations not fulfilled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What is a Performance Bond?

A

A means of ensuring a client against the risk of a contractor not fulfilling obligations

Includes: dates; cost; parties
On demand
Conditional - conditions are met - insolvency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Performance Bond vs PCG?

A

Bond added to contract sum, PCG is free
Contractor might not have a parent company.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

What is a Retention Bond?

A

Retention amounts paid, Bond provided to recover retention
Retention recovery

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

What is an Advanced Payment Bond?

A

Secure cover for advanced payments
Contractor provides bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

What is a PCSA?

A

Pre-Contract Services Agreement

Document services a contractor has to perform
Good for limited design
The more work carried out, the weaker the client position

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

What is a Letter of Intent?

A

Method of instructing a contractor to carry out work before the contract is executed

Value of works; dates; payment method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

What insurance options [works insurance] are there in the contract?

A

A - New Build - Contractor
B - New Build - Employer
C - Existing - Joint names via employer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

What are Specified Perils?

A

Fire
Lightning
Explosion
Storm
Flood

Events that can cause significant damage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

What is All Risk?

A

Insurance for physical loss or damage to work executed and site materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

What are Excepted Risk?

A

Toxic explosions
Pressure waves

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

What is subrogation?

A

Legal technique where the insurer steps into the shoes of the insured in order to take the benefit of legal rights and remedies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

What is advanced payment?

A

Given to the contractor for long lead times for materials
Payments, values and dates should be set out in the CPs

Disadvantages - less incentive for contractor; bad for employer’s cash flow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

What are timescales for payment?

A

Due date activated 7 days after valuation date
Pay no later than 5 days after certification
Pay less notice 5 days before payment is due (14 days from due date)

39
Q

What if a contractor doesn’t submit a claim?

A

Value myself

40
Q

What is the valuation process?

A

Contractor submits on valuation date
QS reviews
Recommendation sent to CA
CA issues payment cert

41
Q

What is an on account payment?

A

Acknowledging payment for works done, but value not agreed

42
Q

What is a star rate?

A

Works that cannot be valued with contractor rates, so built up by contract rates

43
Q

What payment options are in the contract?

A

A - Stage Payments
B - Periodic Payments

44
Q

What if a QS over certifies a payment?

A

Check to see if there is an overpayment
Calculate the difference
If not processed, rectify
Notify client and state future check remedies

45
Q

What is opening up works?

A

If you are under the impression that the works are not in accordance

46
Q

What options are there for opening up works?

A

Instruct contractor to remove defective work
Can remain
Issue instructions for variations
open up more works to check

Defect: contractor remedies at own expense, no EoT
Non defect: Vice versa of above

47
Q

When do you pay for on site materials?

A

Protected
Covered by works insurance
Only materials around that stage
Materials actually on site

48
Q

When do you pay off site materials?

A

Listed items
Proof of ownership (vesting certificate)
Materials clearly labelled
Covered by insurance
Visit site where located

49
Q

What fluctuations are in the contract?

A

Allows for adjustment of contract sum

A - (Default) - levy and tax
B - Labour and materials and tax
C - Price adjustment formula

50
Q

Which would you recommend? (fluctuations)

A

B and C for long term - contractor can adjust, so less risk added

51
Q

What is Retention?

A

A percentage of the amount certified, held back to ensure the works are carried out as required
3-5% (3 in contract)
Not taken off L&E, charges, suspension of works, fluctuations

52
Q

What is Change Control?

A

Administrative process that implements contract mechanisms for instruction change

Identify
Sign off from CA/Client
Instruction raised
Tracked

53
Q

What is included within an instruction?

A

Description of change
Cost
Programme
Reference to drawings
Signed

54
Q

Can a contractor reject an instruction?

A

If it:
Affects H&S
Affects access
Hinders design process
Days to comply ….

55
Q

What is an extension of time?

A

Allows for CA to extend time of completion date
Stops time becoming at large and postponing clients right to claim liquidated damages

56
Q

What is the procedure for an extension of time?

A

Notify as soon as delay is reasonably apparent
Identify cause of delay
Give any additional info
CA notifies contractor in writing 12 weeks from notification
CA - time awarded and [cannot read]

57
Q

What is Loss and Expense?

A

Enables the contractor to claim direct loss due to delay or disruption
Intended to put contractor back in original position

58
Q

What is a Relevant Event?

A

An event that causes delay to completion of works
Time no money
14 events - section 2

Force majeure
Specified Perils
Adverse weather

59
Q

What is a Relevant Matter?

A

An event that causes delay to completion of works. Contractor entitled to time and money - 5 section 4

Delay in approvals
Change/instruction
Opening up works
Later handover

60
Q

What is the process of L&E?

A

Contractor gives notice with their assessment
Employer must give notice within 28 days and 14 days for others
Once agreed, add to contract sum

61
Q

How do you assess L&E?

A

Prolongation - Prelims, divide into elements
Loss of Profit - Los of profit that could have been made on resource as a result of delay
Interest - Late payment
Office overheads - Hudson formula: Head Office % x (CS/contract period) x Period of delay
Labour - Timesheets

62
Q

What is Practical Completion?
What happens?

A

When all works and obligations within the contract have been carried out

Half retention released
Defects liability starts
Insurance and handover
Can’t claim LDs

63
Q

What documents are required for PC?

A

H&S file
O&M manuals
Building Control approval
Planning permission
Test and Commissioning Certificates

64
Q

What is the Final Certificate?

A

Issued at the end of the defects liability period

Can’t claim loss and expense
2nd retention released
Patent defects complete
Adjustments to contract sum

65
Q

What is the difference between Sectional Completion and Partial Possession?

A

Section:
Refers to pre-defined dates
Same procedure for PC

Partial:
Client takes possession of section before completion
Contract has to agree unless affects H&S/access

66
Q

What are the implications of Partial Possession?

A

Employer is now responsible of damage
Contractors insurance ends
PC assumed

CA issued written confirmation
LDs reduced

67
Q

What is Early Use?

A

Employer occupies an area of storage
Insurances - contractor

68
Q

What are Liquidated Damages?

A

Pre-estimate of loss suffered from late completion

Not a penalty
Applies when certificate issued
inc - loss of rent/third party fees/statutory fees

69
Q

What is the Defects Liability Period?

A

The period where a contractor has an obligation to make good any defect

Defects: Shrinkages/wrong material
Snags: works of a trivial nature

70
Q

What is the Rectification process?

A

PC issued
Default 6 months - 12 months common seasonal
Issue statement within 14 days of end of rectification period
Contractor carries out work at no expense to client
Remainder of retention released

71
Q

Final Account procedure?

A

Prepared throughout project

Inc:
CSA
Variations
PS
Claims
Revised CS minus paid to date

72
Q

What is termination of a contract?

A

Where the contract works are lawfully stopped under the contract. 3 ways:
1- Employer
2 - Contractor
3 - Both/either parties

73
Q

What are ground for employer to terminate?

A

7 grounds:
Insolvency
Breach of contract
Failure of CDM
Failure written instructions

Items 1-5 - written notice
14 days to stop default. If not further 10 days issue second notice

74
Q

Ground for contractor to terminate?

A

6 grounds:
Failure to employer to pay
Suspension of works for continuous period
Insolvency of employer

75
Q

Termination by either?

A

Force majeure
CAI/variation discrepancies
Damage via Specified Perils

76
Q

What is suspension of works?

A

Contractors have right to suspend when payments not made

Default period 2 months
7 days notice
Not suspend statutory duties
Insurance to halt

77
Q

What are antiquities?

A

Artefacts of history; fossils; old foundations

If found - contractor takes reasonable care to preserve
Instruction raised
Contractor entitled to EoT and L&E.
Mitigate - surveys and insurance

78
Q

What is Acceleration?

A

Completion of works in a shorter time

Resequence work
Increase Work time
Increase resource

79
Q

Duties of CA?

A

Technically not till contract administered

Ensure appointments in place
Records
Site inspections
Meetings
Reporting
Instructions
Valuations
EoT
PC
L&E

80
Q

Can a contractor refuse and instruction?

A

No, unless:
affects them meeting terms of contract
affects acces to site

After 7 days written notice of refusal - can instruct others - Deduct from CS

81
Q

What happens with a verbal instruction?

A

Contractor must confirm in writing within 7 days
If not withdrawn it will take affect 7 days after confirmation

82
Q

What is Joint Fire Code?

A

A practice code on protection of fire

By Fire Protection Associations
Projects high risk of fire

83
Q

CA vs PM?

A

CA administers contract

PM manages team from inception:
Makes decisions on behalf of employer
Communications

RICS guidance

84
Q

Certificates a CA issues?

A

EoT
Payment Certificates
Variation
PC
Making good
Final Certificate

85
Q

Culpable Delay?

A

Delay which is completely contractor’s fault

86
Q

Process of Partial Possession?

A

Contractor notifie[d] elements of possession; date
Rectification period starts
Insurances cease
LDs reduce to some proportion

87
Q

What’s Acceleration?

A

Increase rate of progress to complete project earlier

Risk:
Not listed
If contractor takes risk - premium

Standard forms don’t detail how quantified

88
Q

Process of LDs?

A

Issue non-completion certificate
Notified the contractor before due date of final payment no later than 5 days
Further notice
Payless notice

89
Q

Types of Letters of Intent?

A

Client issues:

Comfort Letters - Parties intent to act in a certain way [NOT A CONTRACT]

Instructions to proceed with consent to spend - Work to proceed up to a certain value

Letters recognising existence of building contracts - Issued once contract agreed.

90
Q

What’s Joint Fire Code?

A

Fire prevention on construction sites

Large projects over £2.5M or projects with sifnificant fire risk.

91
Q

Roles of CA?

A

Meetings
Update client
Payment
Variations
Site visits
EoT
Record keeping
Issue certs

92
Q

What are 3 things required for EoT?

A

Relevant event
Demonstrate raised as reasonably apparent
All ways tried to mitigate

93
Q

Advantages/disadvantages for Letters of Intent?

A

Advantages:
Tight timescales, instruct works before execution of contract
Comfort Letter not legally binding

Disadvantages:
Transfer of negotiation risk
Limits to scope