Contract Administration Flashcards
Whats are the main forms of JCT available?
JCT Minor Works 2016
JCT Minor Works 2016 w/ Contractors design
JCT Intermediate Building 2016
JCT Intermediate Building 2016 w/ contractors design
JCT Standard Building 2016
JCT Standard Building 2016 w/ quantities
JCT Standard Building 2016 w/ approx quantities
JCT Major Project Construction 2016
What are the other JCT forms available?
JCT Measured Term 2016
JCT Design and Build 2016
JCT Homeowner 2016
What is a sectional completion certificate
A sectional completion certificate is certificate issued to the part or section of the works completed by the contractor,
Client may take possession of this section.
When would you use the contractors design supplement?
Generally when the works are of specialist nature and require specific detailing. The clients requirements of the design would be outlined during the tender process in a performance specification like criteria.
How does the JCT Measured Term Contract work?
The JCT measured term contract appoints a contractor over a specified period to perform a service usually outlined in a specification or works schedule. The contract usually outlines an envisaged contract sum. The contractor is issued works orders by the Contract Administrator.
Why would you choose a JCT over another form of contract?
I’m familiar and have trained with JCT contracts. More so they are an industry wide and accepted standard contract. I would in the future use other standard forms of contracts subject to training and competence.
What 5 things must be in place for a contract to exist?
Offer Consideration Acceptance Time Agreement
Must contracts be written?
Contracts can be written or oral and still be legally enforceable. However, I would always advise a client to only enter into a written contract.
What are the difference between “Under Hand” and “Signed as a Deed” contracts?
Underhand (i.e. simple)
Action against cannot be brought after 6 years
Less protected than a deed
Quicker as not required to be signed by a bound person.
Higher risk
Signed as a deed
Action against cannot be brought after 12 years
Does not have to be supported by valuable consideration, this offers more protection to the person who hasn’t broken the contract and more remedy from the breaker.
Must be signed by a person who is bound to the company (i.e. director) and witnessed which may be slower
Can a contract be modified once signed?
Yes if all parties to the contract agree to the modifications.
A provision of amendments would usually be attached to the contract.
What constituents a construction contract under the Construction Act?
Construction of structures even where it can move or have moving parts
Installation of a fixture which is annexed or affixed
Enhancement of land or buildings.
What are the payment provisions under the Construction Act?
Payment provisions.
Right to adjudication
Right to suspend performance.
The act states you must provide interim payments if the contract is greater than 45 days.
- Due date set.
- Valuation date is 7 days before due date.
- Certification must be issued no later than 5 days after due date.
- Contractor can submit their own certificate on expiry of the 5th day.
- Client can counter the contracts cert but no later than 5 days before the payment date.
- Payment date is 14 days after the due date.
What contract documentation would you find with a MW?
Specification
Schedule of works
Drawings / details
JCT MW SECTION 1
Definitions and Interpretation
JCT MW SECTION 2
Carrying out the works
JCT MW SECTION 3
Control of the works
JCT MW SECTION 4
Payment
JCT MW SECTION 5
Injury, Damage and Insurance
JCT MW SECTION 6
Termination
JCT MW SECTION 7
Settlement of disputes
What certificates are issued by the CA under a JCT MW
Extension of time Interim payment certificate Non-completion certificate Practical completion certificate Certificate of Making Good Defects. Final certificate (releasing retention)
What is practical completion and what contract mechanisms trigger?
RIBA Stages of Work define PC signifies when the project is handed over to the client from the contractor.
- The defect liability period begins
- Half of the retention is released
- Ending a contractors liability to liquidated damages.
- Employer takes back site and sorts insurance.
What documentation is handed over to the client at Practical Completion?
Building owners manual and user guide
Health and Safety file
Building Log Book
Construction stage report
How are liquidated damages calculated?
They are calculated on a weekly/daily rate in which the loss the client is likely to incur if the contractor fails to meet the completion date.
Calculated by the client.