Contract Administration Flashcards
What if a client tells you liquidated ascertained damages are to be £100,000 per week?
- I would ask if the LADs figure is based on a genuine pre-estimate of financial loss and explain that in the event that LADs are applied, they would need to substantiate this figure.
- I would also explain that if the figure inserted into the contract is shown to be punitive and not based on a genuine financial loss, it is likely to not be enforceable.
- In this scenario, the employer will need to pursue the
main contractor for any direct loss that can be substantiated through a formal dispute resolution procedure.
What are extensions of time?
Extensions of time adjust the contract completion date and relieves the contractor’s liability to pay liquidated damages for the period of the extension.
What must be in place before LDs can be deducted?
- A non-completion certificate.
- A pay less notice.
What if the employer actually hasn’t suffered a loss or damage?
- It doesn’t matter
- Damages can still be deducted at the value stated on the contract.
What are the benefits of being able to grant an extension of time?
- It mean the contractor does not have liquidated damages deducted for a delay that they did not cause.
- It allows another completion date to be set, allows the employers to deduct liquidated damages at that stage if required.
What happens when ‘time is at large’?
- There is no set completion date.
- The contractor only has the obligation to complete works within a reasonable time.
- No LDs can be deducted as their is no completion date.
- For LDS to be applied, the employer would have to prove that the contractor hasn’t completed the works within a reasonable time.
What are Relevant Events in an SBCC form of contract?
- They are an event that would entitle the contractor to an extension of time.
What are examples of relevant events?
There are 13 relevant events in SBCC contracts including:
- Variations.
- Instructions.
- Deferment of possession of site.
- Execution of an approx. quantity that is not a reasonably accurate forecast.
- Suspension of the works by the contractor due to non-payment.
- The carrying out of works by statutory authorities.
- Impediment, prevention of default by the employer.
- Force majure.
- Civil commotion or terrorism.
What are the main elements you would include within an interim valuation?
- Preliminaries.
- Measured works.
- Variations.
- Materials on-site.
- Less retention.
How do you evaluate interim valuations?
- Go to site and inspect the works to form a view of the extent of works undertaken.
- Check materials stored on-site.
- Value both time related and fixed preliminary items claimed against.
- The interim valuation amount is presented as the gross valuation, less the previous payment made, less retention.
- Finally, as CA, I would prepare and issue the Payment Certificate.
What is the interim certificate conclusive of?
- the interim payment certificate is not conclusive.
- They carry no contractual significance in terms of stating that the quality of materials or workmanship is satisfactory.
- Only the final payment certificate is conclusive.
What is retention?
- It is a percentage of each interim certificate that is deducted and retained from each interim payment to the contractor.
- Retention provides the client with some security that the contractor/sub-contractor will return to correct any defects during the defects defects liability period.
Retention also provides the client with security in the event of the contractor defaulting/ liquidating.
If a non-completion certificate is is not issued when works continue beyond the completion date what is the consequence?
Time is at large.
When is retention released to the principal contractor?
- Half of retention is released in the interim payment following practical completion being achieved.
- The remaining retention is released in the final payment certificate after the certificate of making good defects is issued.
What is a typical retention percentage under SBCC contracts?
Retention is usually between 3%-5%.
What is a retention bond?
- This is where a bond is provided in lieu of taking retention from interim payments.
- It should be equal to the same value as retention deducted.
- The requirement for the bond should be stated in the contract particulars.
- There is a standard form for retention bonds provided in SBCC contracts.
What happens if the contractor does not maintain the retention bond?
- Retention can be deducted from interim payments by the employer.
- If the bond is subsequently taken out then retention moneys taken can be paid thereafter.