Case Study Flashcards

1
Q

Can you tell me what insurance option 6.4C and why you proceeded with this option? What were the alternative options

A

6.4C - Insurance of Works and Existing Structure by Other Means.

  • The Client requested this as they had struggled to obtain a joint names policy as per Clause 6.4B with suitable cover as insurance for the building is not typically provided on an ‘all risks’ basis and only for damage and loss for specific perils such as fire.
  • Therefor option 6.4C was selected as this provided the opportunity for the Client / Employer to obtain insurance for the structure under their own bespoke terms. The employer also wished to obtain a joint-names policy for the works so that the amount they had invested in the works via interim payments were protected.
  • Clause 6.4A is Joint Names Insurance of the Works by Contractor and is most relevant for new build projects.
  • Clause 6.4B is Joint Names Insurance of the Works and Existing Structures by the Employer.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why did you progress with Partial Possession under SBCC Minor Works and did you consider other options?

A

Partial Possession terms were written into the SBCC Minor Works Contract within a Schedule of Amendments.

This was discussed with the Contractor prior to works progressing on-site so they understood how Partial Possession was going to be implemented within the works and they agreed to accommodate this.

This did provide the required contractual instruments to allow for client access, the passing of responsibilities of the site etc. However, in hindsight this provided the unnecessary risk of the Contractor having a substantial change of position and disputing the partial possession notice, although they would not be able to do so unreasonably.

In hindsight an SBCC Standard form of Contract would have been more suitable and would have required:

  1. The Contract Particulars section of the JCT/SBCC booklet needs to be completed to allow for sectional completion, i.e. descriptions of the sections, dates of possession for each section, dates for completion for each section, section sums and liquidated damages for each section.
  2. On PC of a section being achieved, the employer’s agent/contract administrator would issue a section completion certificate, setting out the date (in their opinion) on which PC of that section occurred under the building contract.
  3. The rectification period for the relevant section starts to run from its PC date, as set out in the section completion certificate.
  4. Risk of loss or damage and insurance responsibly for the relevant section is passed back to the employer on the sectional PC date, as stated in the section completion certificate.

I was working under the oversight of a senior colleague who approved with my course of action and it was also early in my career.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What was the Contract Sum and how much did each section of the works cost?

A

The Contract Sum - £258,425,20
- Prelims = £20,000
- Access & Misc = £20,000
- Downtakings = £5,000
- M&E = £90,000
- Joinery = £15,000
- Decor & Finishes = £60,000
- External Works = £20,000
- 10% Contingency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What were the consequences of Partial Possession being granted to the client on the conclusion of Phase 1

A
  • The rectification period for the ‘Relevant Part’ starts to run from the deemed PC date and the client released half the retention monies.
  • LADs are reduced by the same proportion as the value of the ‘Relevant Parts’ to the Contract Sum.
  • Risk of loss or damage and insurance responsibility for the ‘Relevant Part is passed back to the employer on the deemed PC date.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How much was the retention released on providing partial possession to the client and how was this arranged for? What retention monies were then released at PC?

A

The amount of retention released was 2.5% of the amount of the works to the basement area and this was done through an interim valuation following the ‘relevant date’ for partial possession.

The amount of the works to the basements was £90,000.00 so the retention was 2.5% of this = £2,250.00.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How much were the LADs reduced by following Partial Possession?

A

Following Partial Possession, the contract stated that LADs were to be reduced by the proportion of the ‘relevant part’ i.e the basement to the contract sum. This was 37% of the contract sum.

Therefore the LADs deducted by 37% of £450 which was £283.50 / week.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

If you were to have used a Standard Form of Contract with Sectional Completion, how would you have allowed for that?

A
  • Sectional Completion is within the Standard Terms of the SBCC Standard Building Contract as default so this type of contract would have been selected.
  • Within the contract particulars for the date for sectional completion to the basement, the description of the area which the contractor would take possession of would be required to be inserted, the cost of each section would need to be inserted as well as the LADs for each section.

On the date for sectional completion, a completion of sectional completion would need to be provided by the contract administrator would be required to be issued or, if the works had not been achieved then a certificate of sectional non-completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

You mentioned H&S risks in your presentation within Key Issue 1. I understand you weren’t PD but how would you have identified, managed and communicated H&S risks to the Principal Contractor, Designers, The Client/Employer?

A

To identify these risks, I would have carried out a risk assessment considering hazard and risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How did you pull together the various options for phasing of the works and what was considered in bringing together these options?

A

In pulling together these options, I first obtained an understanding from the client that I discussed proposals and worked together with the principal designer as health and safety within the pre-contract stage was their responsibility.

In carrying out the procurement and tendering and pulling together the specification of works and thereafter, in implementing the phasing and administering partial possession, I had a joint role in pulling together the options and presenting these to the client.

  • The principal consideration was H&S and how various risks could be managed and mitigated
  • Another consideration was the layout of the building and how it lent itself to being separated into different sections.
  • Furthermore, providing care to the client in achieving their objectives while providing a reasonable working environment to the client was considered.

Vacant Possession was an obvious consideration from a H&S perspective but it would fail to provide for the clients objective although would mean the works would be completed speedily.

In terms of providing the client was the highest level of function from the building, the 4-phase option was considered as this best served the clients objective of having access but at a cost and also having the effect of extending the overall disruption with a lengthy programme. It would be very challenging to provide the client with a reasonable working environment as dust pollution and noise pollution would easily dissipate throughout the upper floors.

The 2-phase option provided a balanced approach where access was provided, as per the clients objective. The building layout lend itself to this separation as there were separate access/egress points as well as a large metal lockable security door subdividing the two areas making H&S more manageable. This option also ticked the box of providing a reasonable working environment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Did you have to provide any certificates/notices or other such documents to issue to implement Partial Possession and if so can you explain their contents and how these were issued?

A

The Architect/Contract Administrator gives the Contractor notice on behalf of the Employer identifying the part or parts taken into possession and giving the date when the Employer took possession (“the Relevant Part” and the “Relevant Date” respectively).

Relevant Date = 7/11/22

The Contractor’s permission cannot be unreasonably withheld.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Provided there was a delay in the handover of the basement within Key Issue 2, was an extension of time issued?

A

The Partial Possession notice had not yet been issued at the time of delays being incurred so the ‘Relevant Date’ was amended to allow time for solution to be sought and implemented.

The contractor acted to amend their programme to accommodate for the delay while still achieving the completion date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Why was level access not provided as part of the works?

A
  • Within the Equality Act 2010, level access is limited to making reasonable adjustments, but likewise the client had a statutory duty to protect the character of the historic environment. In the case of 163 Bath Street, this would heavily limit the options to provide access to the front elevation as the Grade-B listing relates to elements of the front elevation.
  • In terms of Building Warrant, Section 4.2 of the non-domestic technical handbook states that in a non-domestic building not served by a lift.
  • We advised the client that under the Equality Act 2010, they may be considered to be in breach of this by not acting reasonably to provide level access such as by seeking to install a wheelchair lift externally that provides access to the basement level as is seen in buildings of a similar nature.
  • We also advised that if this were to be done, Historic Environment Scotland states ‘The resting position of any
    external lift should be as low as possible, and the
    design of the platform and restraints should be as
    transparent as possible’.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What was the architectural period of 163 Bath Street and what other architectural periods are of?

A

163 Bath Street was a Georgian townhouse.

The architectural style that succeeded Georgian architecture and was followed by Edwardian architecture.

Other architectural styles include art deco and brutalism.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How would you identify the difference between Georgian and Victorian Architecture?

A

Georgian Architecture - Symmetrical external facade with evenly spaced windows.

Victorian Architecture - Stonework features to the external elevation are more ornate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are different elements of a Georgian building and what are common defects and the remedies of these defects?

A

Roof

  • Nail Sickness:
    Strip the section of roof and replace the corroded nails with modern copper nails.
  • Slipped or missing slate:
    To replace with a slate that matches the profile and specification, slide the slates in courses above the effected slate and fix a new single holed top slate.
  • Lead flashing wind uplift, surface movement, rips and tears.
    Lead sheet academy provides installation details as well as the different Codes of Lead and their applications (Codes 4,5&6 are usable for flashings).

External Walls

  • Light weathering of stonework.
    Brushing (stiff bristle brush) or dressing masonry back to a sound surface
  • Significant weathering.
    Stone indent repair with petrographically matched stonework, carefully cut out the existing leaving a 100mm bed for the new sandstone section to be set in and thereafter repointed.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What reasons may cause the Contractor to not provide consent for Partial Possession and were these relevant to your building?

A
  • access routes are difficult to achieve
  • it would disrupt the works, or
  • it would incur additional costs
17
Q

In Key Issue 2, if the Client wanted to terminate the appointment of their M&E consultant, what would the process be?

A

The consultant was appointed directly by the client so I was not party to their agreement.

As per the RICS RICS Standard Form of Consultant’s Appointment Scotland:
- The termination of a consultants engagement can occur at any time with 28 days notice provided prior to the termination is required.

  • If the Project is cancelled by the Client or cannot proceed for reasons outside the reasonable control of the Client, either party may immediately terminate the Consultant’s engagement.
  • If a party is in material breach of its obligations under this Appointment and fails to remedy such breach within 14 days after the other party gives it written notice to do so, the client can immediately terminate their Contract.
  • If a party becomes Insolvent, the other party may immediately terminate the Consultant’s engagement under this Appointment

Impact on Fees:
- The fee for services up to the point of the termination are payable and a fair and reasonable proportion of the next instalment of the Fee and all reasonable disbursements due.

The consultants obligations:
- The Consultant performs the Services upon and subject to the terms of this Appointment.

  • The Consultant performs the Services with due regard to the Client’s Brief.
  • The Consultant cooperates with the Lead Consultant
  • The Consultant performs the Services and provides the Documents so as to comply with the Programme, unless the Consultant is prevented from doing so by circumstances outside its reasonable control.
  • The Consultant notifies the Client if it becomes aware that the performance of the Services is delayed or likely to be delayed
18
Q

In Key Issue 2, what was the method or conflict avoidance did you practice?

A

Negotiation.

19
Q

What is the roof construction of a Georgian building?

A

1.Rafters with sarking boards fixed horizontally over the full pitch.
2. Breathable & vapour permeable roof membrane (traditionally horsehair felt / bitumen felt)
3. Slate single head nailed to sarking boards, double lapped.

20
Q

In Key Issue 2, did you deliver the method of conflict avoidance well and if so, how did you?

A
  • I ensured to enable the communication between the parties through myself.
  • I allowed both parties should be allowed to express their position on items being discussed and provide their justification.
  • I ensured to act professionally and remain calm during all discussion and to find areas of mutual agreement.
  • I recorded all agreements via email correspondence and acted upon them.
  • An agreement was made for another individual to take the project forward in terms of finding a solution.
  • Eventually the M&E consultant attended site and was able to specify a fibre optic cable which connected the two areas within a compartment.
21
Q

In Key Issue 2, if you did not manage to avoid the conflict how would you have proceeded? and can you explain the process?

A

As per the Housing Grants, Construction and Regeneration Act 1996, all parties in contract have a right to adjudication so I would have advised that route.

Adjudication is a process of formal dispute resolution were a decision is referred to a dispute to an independent adjudicator to make a decision.

It is fast with a decision usually being provided within 28 days. The decision is binding unless overturned by litigation or arbitration.

22
Q

In Key Issue 2, as PD / lead consultant, did PMP fail their obligations to the client?

A

The PD’s responsibility was to ensure all designers were competent.

We knew the consultant was competent as the engineers were Chartered by the Engineering Council (CEng).

So PMP complied with their obligations.