Construction Technology Flashcards

1
Q

Describe the external envelope of 163 Bath Street, Glasgow.

A

The roof was dual pitched with a slate covering and featured a cupula above the stair way.

The external walls were of solid wall construction, formed of sandstone, with an ashlar external skin and stone rubble inner skin with small stones within the cavity bonded by lime mortar.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are Building Regulations?

A

Building regulations are statutory instruments which set out the minimum standard for the design and construction of a building.

Principally these include the Building Standards Technical Handbook: Non-Domestic, British Standards and International Standards.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is superstructure?

A

All internal and external works items above the damp proof course.

This is made up of:
- External Walls
- Stairs
- Roof
- Structural Walls
- Suspended Ceilings
- Raised Floors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Describe the super structure of 163 Bath Street, Glasgow?

A

This is made up of:
- Sandstone solid walls with lath and plaster wall and ceiling finishes.
- Dual pitched roof with a slate finish and cupula.
- Timber suspended upper floors with joists embedded within the walls.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are temporary works?

A

Temporary works do not normally appear on construction drawings but may be required depending on the construction method being used.

Temporary works may also be required as a result of health and safety requirements to ensure a safe method of construction, for example temporary propping.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is shoring?

A

Shoring is a form of temporary support given to the existing building.

It’s purpose is to provide a precaution against damage or injury due to collapse.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the main components of concrete?

A

Cement

Aggregate (natural rock, crushed stone, gravel)

Water

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a basement?

A

A story constructed below ground level.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the 3 different types of basement construction?

A

Retaining Wall & Raft - consisting of a raft foundation forming the floor (while distributing the building’s load) with the walls forming retaining walls

Box and Cellular - consisting of a raft foundation forming the floor while the internal structural walls form cells and transmit loads to the raft foundation.

Piled Solution - structural loads are carried to the basement floor by collumns and transmit to the ground via bearing piles. In this example the basement has numerous columns passing through it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the 3 main methods of waterproofing a basement and what are the considerations for each?

A

Dense Monolithic:
- Where the basement is designed and built to form a watertight space using high quality reinforced concrete.
- This requires good workmanship, strict control and careful design of joints.
- Success depends on the water to cement ratio and the degree of compaction.

Tanking:
- This uses materials such as polythene sheeting, asphalt, bitumen and epoxy resin.
- This can be applied both internally or externally to provide a continuous membrane to the base of the slabs and
walls.
- External application is more effective as it protects the structure in addition to the waterproofing.

Drained Cavity:
- Can be designed from new or retrofitted to an existing basement.
- Allows a small amount of water infiltration to occur.
- The water is collected and then drained to a sump or is directly discharged.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the technical advantages of steel frames?

A
  • Quicker to assemble on site than concrete frames.
  • 100% recyclable and inorganic meaning elements will not crack, shift, creep or warp.
  • Highest strength to weight ratio.
  • Lighter than concrete frame systems meaning there is a lesser requirement for foundation provision.
  • Due to strict manufacturing controls, there is consistent material quality that can be obtained due to production taking place in-line with strict standards.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the technical disadvantages of steel frames?

A
  • The price of steel often fluctuates resulting in a lack of cost certainty.
  • Installation of steel frames requires experienced skilled builders, at a greater cost compared to builders required for concrete frame systems.
  • Resource of qualified contractors can be difficult depending on market conditions.
  • Fire protection has to be installed retrospectively.
  • Fixings may require replacement overtime.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are technical advantages of concrete frame systems?

A
  • There is often fire protection inherently within the structure.
  • As concrete frames are slower on-site when compared to concrete frames, it means there is a lower cash flow expenditure at an early stage in the project.
  • Maintenance requirements are generally low compared to steel frames.
  • Concrete frames provide good sound and heat insulation.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the typical disadvantages of concrete frames?

A
  • In comparison to steel frames, they are slower to install.
  • There may be complications during construction as a result of cold weather.
  • The requirement for steel reinforcement means concrete frames are similarly effected by price fluctuations but to a lesser extent.
  • They are heavier and therefor require larger foundations.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What should be considered when repairing sash and case windows?

A

Sash and case windows are generally made of high quality heartwood timber so repairing windows instead of wholesale replacement is beneficial.

Sash and case windows are of a straight forward design and construction meaning they can be readily repaired. Even the most dilapidated windows can be repaired.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the components of a sash and case window?

A
  • Top sash
  • Bottom sash
  • Meeting rails with sash fastener
  • Astragals/ glazing bars
  • Baton rod
  • Sash bottom rail with sash lift
  • Weight box (concealing sash weights
  • Sash weights
  • Pulley cord
14
Q

What should a ventilation system provide?

A
  • Provide outside air to maintain quality sufficient for human restoration.
  • Remove excess water vapour from areas where it is produced in sufficient quantities in order to reduce the liklihood of creating conditions that support the germination of mould, harmful bacteria, pathogens and allergens.
  • Remove pollutants which are a hazard to health from areas where they are produced in significant quantities.
  • Rapidly diliute pollutant odours, where necessary.
15
Q

What is ventilation?

A

It is the process of supplying air to an enclosed space and removing stale air from the space.

It can manage the indoor air quality by both diluting the indoor air with less contaminated air and removing the indoor containments with exhaust air.

15
Q

What are the three ways a building can be ventilated?

A
  1. Natural means.
  2. Mechanical ventilation
  3. Combination of mechanical and natural.
15
Q

What are common defects of sash and case windows?

A
  • Timber decay which can be tested by pushing a key, penknife or screwdriver into the timbers to see if it penetrates.
  • Stiffness of the sash on opening.
  • Sash dropping out of control of counter balance weights.
  • Painted shut sash, unable to move.
16
Q

CONSTRUCTION TECH: Can you describe the partition specified and the details shown on the cross section you provided to the project at 24-26 High Street, Lanark

A
  • The partition was for the purposes of forming an individual office so was required to have a level of sound insulation.
  • The partition specification included:
    1. Two layers of Gyproc wall board fixed to each side of the metal C stud at 600mm centres.
    2. 25mm of Isover acoustic insulation was installed within the cavity formed.
    3. The base and head channels were affixed to the concrete floor slab below and the concrete soffit above respectively.
    4. Gyproc sealant to the wall head was applied to the partition and wall/floor junction to mitigate sound transmitting.
  • Results included:
    a. 30 Minute fire resistance
    b. 49 db sound insulation.
17
Q

CONSTRUCTION TECH: How did you identify the requirement for a mechanical and electrical design at Unit 10, Xsite and why were you not able to undertake this as a designer?

A

Our proposed building warrant floor plans were based on the Clients brief included the forming of meeting rooms, an individual office, kitchen/ tea prep, WC and shower facilities with in an open plan space. The requirement for an M&E design was largely due to the requirement for both ventilation and space heating to these areas.

Firstly, section 3.14 of the Non-Domestic Technical Handbook states that a building should have a means of ventilation either by a mechanical means, natural means or a combination of mechanical and natural and the subject premises had neither with no openable windows available. The same regulation states the requirement for mechanical extract to the WC’s, kitchen and showers.

CIBSE Guide A states that:
- WC’s require 5 air changes per hour
- Showers / Baths = 15L.s-1
- Offices (boardroom, office, open plan) = 10L.s-1
- Office Food Prep:-
1. 15 L/s (microwave and beverages only)
2. 30 L/s (adjacent to the hob with
cooker)

Furthermore, there was no space heating within the premises as existing. This would be required to provide comfort at end use. The clients brief initially included space heating concealed within a suspended ceiling grid. However, this was changed to electric panel heaters as a cost saving exercise. In accordance with Rule 2 of the RICS Rules of Conduct, this design service should be carried out with individuals with the relevant expertise - i.e an M&E consultant.

18
Q

CONSTRUCTION TECH: At Dundas Court, how did you advise your Client in regard to the partitioning specification provided you were required to achieve a ‘high’ floor to ceiling height and a high level of sound insulation?

A

The nature of the tenants organisation included consultation rooms which had sensitive conversations within and the Client wished to provide confidence to their clients.

Similarly I had to find a specification which could span the floor to the underside of the ceiling above which was a height of 4.2m.

In order to find a solution to recommend to the client, I reviewed the British Gypsum white book.

The system I recommended could achieved:
a. Heights of upto 5m
b. 61 dB sound insulation

The specification included>
- Two layers of Gyproc SoundBloc 15mm each side of Gypframe 146 AS 50 AcouStuds at 600mm centres.
-100mm and 50mm Isover Acoustic Partition Roll in the cavity.
- Acoustic sealant at junctions with adjoining structure and other air paths.

19
Q

CONSTRUCTION TECH: At Dundas Court, what specification of windows were there and what window repairs were required?

A

There were window astragals and sections of cills which were decaying due to wet rot. Splice repairs were required before reinstating sand mastic joints.

The windows were painted shut so they were required to be freed by cutting open the paint seal, carefully scraping off excess paint and fully preparing prior to redecoration.

Thereafter they required redecoration.

20
Q

CONSTRUCTION TECH: At Dundas Court, what specification of windows were there and what window repairs were required?

A
  • As per 3.14 of the technical handbook this there is a requirement for ventilation by either mechanical or natural means.
  • There is provision within the Non-Domestic technical handbook for trickle ventilation to achieve the required ventilation for a washroom which requires mechanical extraction capable of at least 30 litres/sec so, I was confident that openable windows could deliver the required 10 L/s required for office areas.
  • We also were provided with building warrant approval on the basis of these proposals.
  • I would say that this certainly reached the limits of my professional competence to provide this advice but I was comfortable that the Building Warrant would provide reassurance if this advice was correct before proceeding with window repairs / natural ventilation.
21
Q

CONSTRUCTION TECH: How did you know that natural ventilation with window repairs was a cheaper option than mechanical ventilation.

A
  • I requested the contractor to provide costs for both options.
  • The window repairs cost circa. £2,000.
  • To install a suspended ceiling and install a ventilation system was to cost circa £6,000.