Contract Admin Flashcards

1
Q

What are the duties of a contract administrator?

A

Role under JCT - traditional contracts - responsible for administering the contract & offering advice to client on instructions, claims, design, progress etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How are they different from those of an Employer’s Agent?

A

Employers Agent performs the CA role within D&B contracts whereas the Contract Administrator performs the same contract administration role in traditional forms of contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Schedules of JCT

A

“DVI C3B FS

1 - Design package
2 - Variation & Acceleration Quotation procedure
3 - Insurance option (A- contractor / B- client / C - joint existing)
4 - Code of practice
5 - Third party rights
6 - Bonds
7 - Fluctuations
8 - Supplemental provisions”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Who undertakes a Contract administration role under JCT?

A

“Historically and traditionally been the Architect

The JCT form refers to ‘architect / contract administrator’

The scope of who can be the CA has widened to include building surveyors, quantity surveyors, management surveyors and engineers”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Who undertakes a Contract administration role under NEC forms?

A

Project Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Using a typical subcontract, take me through the process of issuing a final certificate. Explain the significance of this.

A

”- Final Certificate - confirmation that contract has been fully completed.
- Issued at end of Defects Liability period and usually triggers release of final retention held.
- Issue of certicate also allows final account to be settled inclusive of any retention release and all patent defects have been remidied.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Sections of JCT

A

“RAC ACS

Recitals
Articles
Contract Particulars
Attestation
Conditions
Schedules”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Take me through the procedure for issuing a certificate for progress payment under JCT.

A

“7, 5, 5, 14-21
- Subcontractor issues application 7 days before valuation date
- I assess & issue application within 5 days of due date
- If I’ve made an error or payless notices needed to be issued should be 5 days before Final date for payment
- Final date for payment 14 days after due date

  • Most of the subcontracts were amended from 14 to 21 days.”
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

As Contract Administrator, how did you control quality on the projects?

A

”- Ensuring subcontractor fully understood their obligations during pre-order meetings
- ensuring regular check points included in subcontracts
- issue of Inspection & Test Plans with monthly application”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Tell me some procedures a CA can put in place to control time?

A

”- Risk Register
- Schedule “

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Tell me some procedures a CA can put in place to control cost?

A

”- Risk Register
- lessons learnt on previous projects
- Regular reporting
- Forecasting turnover & spend and monitoring against actual”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the essential skills of a PM?

A

”- Technical competence
- Communication
- Team motivation
- Risk Management
- Business acument”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the role of a PM

A

”- Planning, monitoring and control of all aspects of a project including risk
- Motivating all those involved to achieve the project goals.
- Project is running on time, on budget and to good quality”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Who is responsible for Administering the building contract?

A

“D&B contracts - Employers agent
Other JCT - Contract Administrator or Architect
NEC - Project manager”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the key responsibilities of the CA?

A

“Determining EOTS and Loss and Expense
1. Issuing Practical Completion Certs
2. Issuing Instructions
3. Certifying Interim Payments
4. Implementing change control procedures
5. Collating and issuing schedules of defects
6. Notifying partial possession
7. Certifying sectional completion
8. Certifying non-completion”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Does the RICS provide any guidance on CA?

A

Yes, Contract Administration Services, however this is for the UK market.

15
Q

How is an AIA contract Structured?

A

“The base structure has 9 Articles - CWD CPD TME

  1. Contract Documents
  2. Work of this Contract.
  3. Date of Commencement & Substantial Completion
  4. Contract Sum
  5. Payments
  6. Dispute Resolutions
  7. Termination or Suspension
  8. Miscellaneous Provisions
  9. Enumeration of Contract Documents”
16
Q

Does the AIA have any exhibits?

A

Yes, can have “Insurance and Bonds” exhibits

17
Q

How will a general contractor submit their application for payment under an AIA.

A

Completion of a G-702 form with supporting lien waivers as applicable.

18
Q

Who issues a final certificate of payment under the AIA

A

Architect

19
Q

Could an email constitute a contract document?

A

Yes providing there is offer, acceptance, intention to create legal relations and the responding email does not vary the conditions, a contract will be created

20
Q

Where can General Conditions of the contract for construction be found.

A

In AIA documents such as A201-2017