Chapter 9. Resource Management Flashcards
What are the six processes associated with Resource Management?
Estimate Activity Resources Plan Resource Management Acquire Resources Control Resources Manage Team Develop Team
What is the standard flow for Resource Management?
Plan, Execute, Monitor and Control
What is the twofold approach to resouce management?
- Define and carefully manage the physical resources on the project.
- Define a role for everyone on the project and define the responsibilities for each of these roles.
Why is influence important in Resource Management?
Project Managers must be able to motivate and persuade people to act in the best interest of the project and must be able to build a team and lead members to give their best efforts.
A project manager delegates in the form of responsibilty and authority. The project manager gives responsibility and authority to the team and expects positive results and accountability in return.
How does emotional intelligence (EI) impact Resource Management?
Project managers should be able to identify, assess and manage their personal emotions, as well as the emotions of a group of stakeholders.
What process groups do the processes of Resource Management fall under?
Planning - Plan Resource Management & Estimate Activity Resources
Executing - Acquire Resources, Develop Team & Manage Team
Monitoring & Controlling - Control Resources
What are the outputs of each Resource Management process?
Plan Resource Management - Resource Management Plan & Team Charter
Estimate Activity Resources - Resource Requirements & Resource Breakdown Structure
Acquire Resources - Physical Resource Assignments, Project Team Assignments, Resource Calendars
Develop Team - Team Performance Assessment
Manage Team - Change Requests
Control Resources - Work Performance Information
What are the inputs for the process Plan Resource Management?
Project Charter Project Management Plan Project Documents Enterprise Environmental Factors Organizational Process Assets
What are the tools used in the process Plan Resource Management?
Expert Judgement
Data Representation - Hierarchival Charts, Responsibility Assignment Matrix, Text-Oriented Formats
Organizational Theory
Meetings
What is a RACI chart?
A responsibility assignment matrix that lists each work package in the rows and the roles in the columns. Each cell is assigned an “R” for responsibile, an “A” for accountable, a “C” for consult, or an “I” for inform.
see. 9. 393 for more information & an example.
What are text-oriented formats?
It follows the format of position descriptions, detailing out what responsibiltiies each position on the project will involve and what qualifications are needed to fill these positions.
How does Organizational Theory impact resource management?
Groups behave differently than individuals. Important to understand how organizations and teams behave, to understanding the amount of work done thus far and how that and the behaviour of the group can pay dividents throughout the project.
What is the main output of the Plan Resource Management process?
The Resource Management Plan.
What is a resource histogram?
A common component of the resource managment plan, it is a visual (bar chart) that shows the resource usage for a given period of time.
3 outputs of the process Plan Resouce Management
Resource Management Plan
Team Charter
Project Document Updates
What is a team charter?
It communicates the ground rules, specifying how the team will interact, communicate, reach decisions, hold meetings, and any other elements important to the team.
What are the inputs for the process Estimate Activity Resources?
Project Management Plan
Project Documents
Enterprise Environmental Factors
Organizations Process Assets
What are the tools for the process Estimate Activity Resources?
Expert Judgement Bottom-up Estimating Analogous Estimating Parametric Estimating Data Analysis Project Management Information System (PMIS) Meetings
What is Bottom-Up Estimating?
It is aggregating individual resource estimates, that will be added up on parent nodes, with some nof these summary nodes (known as control accounts, being tracked more carefully than others). The topmost node of the WBS should contain all of the estimated resources for the project.
*favored technique on the exam.
Which type of estimating uses historical performance to extrapolate and estimate future resource usage?
Parametric Estimating
What is the PMIS?
The Project Management Information System (PMIS) is a software system that helps the project manager store and organize information, experiment with alternatives, and rapidly optimise resource usage, and calculate schedules.
What are the outputs for the process Estimate Activity Resources?
Resource Requirements
Basis of Estimates
Resource Breakdown Structure p. 399
Project Document Updates