Chapter 6. Special Focus: Earned Value Flashcards

1
Q

Budget at Completion (BAC)

A

How much was original planned for this project to cost.

Formula:
n/a - derived by looking at the total budgeted cost for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Planned Value (PV), aka Budgested Cost of Work Schedule (BCWS)

A

How much work should have been completed at a point in time based on the plan. Delivered by measured planned work completed at a point in time.

Formula:
PV = Planned % Complete x BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Earned Value (EV), aka Budgest Cost of Work Performed (BCWP)

A

How much work was actually completed during a given period of time. Derived by measuring actual work completed at a point in the schedule.

Formula:
EV = Actual % Complete x BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Actual Cost (AC), aka Actual Cost of Work Performed (ACWP)

A

The money spent during a given period of time.

Formula:
Sum of the costs for the given period of time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cost Variance (CV)

A

The difference between what we expected to spend and what was actually spent

Formula:
CV = EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Schedule Variance (SV)

A

The difference between where we planned to be in the schedule and where we are in the schedule

Formula:
SV = EV - PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Cost Performance Index (CPI)

A

The rate at which the project performance is meeting cost expectations during a given period of time

CPI = EV / AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cumultative CPI (CPIc)

A

The rate at which the project performance is meeting cost expectations from the beginning up to a point in time. CPIc is also used to forecast the project’s costs at completion

Formula:
CPIc = EVc / ACc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Schedule Performance Index (SPI)

A

The rate at which the project performance is meeting schedule expectations up to a point in time.

Formula:
SPI = EV / PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Estimate at Completion (EAC)

A

Projecting the total cost at completio based on project perofrmance up to a point in time.

Formula:
EAC = BAC / CPIc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Estimate to Completion (ETC)

A

Projecting how much more will be spent on the project, based on past performance.

Formula:
ETC = EAC - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Variance at Completion (VAC)

A

The difference between what was budgeted and what will actually be spent.

Formula:
VAC = BAC - EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

To-Complete Performance Index (TCPIc)

A

Performance that must be achieved in order to meet financial or schedule goals.

Formula:
TCPIc = (BAC - EV) / Remaining Funds

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Types of Cost

A

Fixed - Costs that stay the same throughout the life of the project.

Variable - Costs that may vary on a project.

Direct - Expenses billed directly to the project.

Indirect - Costs that are shared and allocated among several or all projects.

Sunk - Costs that have been invested into or expended upon the project.

Opportunity - the cost of the loss of potential benefit from the alternatives when a choice is made that excludes those alternatives. Most often associated with project selections.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly