Chapter 4. Integration Management Flashcards

1
Q

What is the one knowledge area where responsibility cannot be delegated to anyone else, that is the project manager’s sole responsibility?

A

Integration Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is Integration Management?

A

Integration Management is the practice of making certain that every part of the project is coordinated:

The project is started, the project manager assembles the project plan, executes the plan and verifies the results of the work…. and then the project is closed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the 7 key processes of Integration Management?

A

Develop Project Management Plan
Develop Project Charter (Project Charter & Assumption Log)
Monitor & Control Project Work (Work Performance Reports)
Close Project or Phase (Final Project, Service or Result Transition, Final Report, Project Documents, Updates)
Perform Integrated Change Control (Approved Change Requests, Project Documents Updates (Change Log))
Direct and Manage Project Work (Deliverables, Work Performance Data, Issue Log)
Manage Project Knowledge (Lessons Learned Register)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the philosophy behind Integration Management?

A
  1. While executing processes, decision-making can be chaotic, and team should be buffered from the clamour as much as possible. The team needs to be focused on executing the work.
  2. Processes that make up project management do not always proceed from start to finish and then move on to the next process. I.e. Adjustments are usually and often needed and plans have to be updated.
  3. Integration processes need to be tailored to fit the size and complexity of the project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Where do the 7 processes of Integration Management fall under the 5 process groups?

A

Initiating - Develop Project Charter
Planning - Develop Project Management Plan
Executing - Direct and Manage Project Work, Manage Project Knowledge
Monitoring & Controlling - Monitor & Control Project Work, Perform Integrated Change Control
Closing - Close Project or Phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the key outputs of each process of Integration Management?

A

Develop Project Charter - Project Charter and Assumption Log
Develop Project Management Plan - Project Management Plan
Direct and Manage Project Work - Deliverables, Work Performance Data and Issue Log
Manage Project Knowledge - Lessons Learned Register
Monitor & Control Project Work - Work Performance Reports
Perform Integrated Change Control - Approved Change Requests and Project Document Updates (Change Log)
Close Project or Phase - Final Product, Service or Result Transition, Final Report, Project Documents Updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a Project Charter?

A

The project’s birth certificate, the document that officially start the project and is the process that creates it. Without a charter, there is no official project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Business documents in Integration Management refers to what?

A

Business case and benefits management plan, which describe the need and how the project is going to satisfy that need and benefit stakeholders. Generally provided to the Project Manager at project start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a business case?

A

The document that explain why this project is being undertaken, the problem it will solve and its benefit cost analysis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a [project] benefits management plan?

A

The document that outlines how the project contributes to the organization’s strategy and expected benefits the project will yield, and how to maximize those benefits.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are common reasons why a project may be undertaken?

A
  1. Market Demand
  2. Organizational Need
  3. Customer Request
  4. Technological Advancement
  5. Legal Requirement
  6. Ecological Impact
  7. Social Need
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are benefit measurement methods?

A

Methods that seek to quantify the monetary benefits and expected costs that will result from a project and compare them to other potential projects to select one most feasible and desirable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Linear Programming and Non-linear Programming are what types of project selection methods?

A

Constrained optimization, in which calculus is applied to solve for maximizations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is Benefit Cost Ratio (BCR)?

A

Benefits to Cost Ratio (i.e. $ return on investment)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is Economic Value Add (EVA)?

A

How much value a project has generated for its shareholders beyond net profits, looking also at opportunity costs (after-tax profits minus capital expenditures x cost of capital).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is an Internal Rate of Return (IRR)?

A

A project’s return presented as an interest rate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What are Present Value (PV) and Net Present Value (NPV)?

A
Present Value (PV) = how much a project is worth right now
Net Present Value (NPV) = how much a project is worth right now minus your costs

The bigger the PV and NPV, the better

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is Opportunity Cost?

A

The cost of the other opportunities that were passed up by investing money and resources into a project. The smaller the opportunity cost, the better (= less loss).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is a Payback Period?

A

How long it will take to recoup an investment in a project. The shorter the period the better.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What is Return on Investment (ROI)?

A

A percentage that shows what return an organization makes by investing in something. Formulas = (benefit - cost) / cost

The bigger the ROI, the better.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is Return on Invested Capital (ROIC)?

A

How an organization uses the money invested in a project, expressed as a percentage.

*Formula = Net Income (after tax) / Total Capital Invested

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Name some of the tools used for Project Selection.

A
Benefit Cost Ratio (BCR)
Economic Value Add (EVA)
Internal Rate of Return (IRR)
Present Value (PV)
Net Present Value (NPV)
Opportunity Cost
Payback Period
Return on Investment (ROI)
Return on Invested Captial (ROIC)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is an agreement?

A

Think of it as a contract for the project, although in some cases it may not be a written contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Who is a Project Charter usually written by?

A

Sponsor and/or customer, but project manager may assist with this

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What information does a Project Charter contain?

A

Project need, how end result with address it, names the project manager, describes the project manager’s level of authority to apply resources and make decisions, describes what circumstances the project may be completed, closed or canceled, high-level project requirements, high-level milestone view of the project schedule, high-level view of the preliminary project budget (summary), objectives and measures, a list of key stakeholders, and who should sign off on the final product.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What is an Assumption Log?

A

Documented created that will live on and be updated throughout the project, a place to capture all assumptions and constraints of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What are assumptions?

A

Unknowns treated as true for the purposes of project planning, usually broad and general in the beginning. Later, they are updated to be lower level and more specific.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

What is the Project Management Plan?

A

A comprehensive document that guides the project’s execution and control, specifying who, what, when, where and how. It is progressively elaborated, meaning developed, refined, revisited and updated but once approved (stabalized), further changes require a change control process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

What are the inputs for developing a Project Management Plan?

A

Enterprise Environmental Factors and Organizational Process Assets.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

What are the tools for developing a Project Management Plan?

A

Expert Judgement, Data Gathering, Interpersonal and Team Skills, Meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

What is the output for development a Project Management Plan?

A

The Project Management Plan - a formal approved document that defines how the project is managed, executed and controlled.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Key points about a Project Management Plan

A
  • is formal
  • a single document
  • may be formed from separate documents combined and approved to become the porject plan
  • approved usually by the project manager, project sponsor, functional managers providing resources for the project, team doing the work
  • once approved, cannot be changed without a change control process
  • may be summarized or detailed, but usually detailed
  • made of several components, most of which are developed via other processes
33
Q

What are the 19 components that can make up a Project Management Plan?

A
Scope Management Plan
Requirements Management Plan
Schedule Management Plan
Cost Management Plan
Quality Management Plan
Resource Management Plan
Communications Management Plan
Risk Management Plan
Procurement Management Plan
Stakeholder Engagement Plan
Change Management Plan
Configuration Management Plan
Scope Baseline
Schedule Baseline
Cost Baseline
Performance Measurement Baseline
Project Life Cycle Baseline
Development Approach
Management Reviews
34
Q

What does Direct and Manage Project Work mean?

A

To execute the work packages and create the project deliverables.

35
Q

What are the Inputs used to Direct and Manage Project Work?

A

The Project Management Plan, Project Documents, Approved Change Requests, Enterprise Environmental Factors and Organizational Process Assets.

36
Q

What are the tools used to Direct and Manage Project Work?

A

Expert Judgement, Project Management Information System, Meetings.

37
Q

What are the outputs of Direct and Manage Project Work?

A

Deliverables, Work Performance Data, Issue Log (Change Requests, Project Management Plan Updates, Project Document Updates, and Organizational Process Assets Updates)

38
Q

How do Approved Change Requests relate to Direct and Manage Project Work?

A

They come out of Perform Integrated Change Control processes and flow as inputs into Direct and Manage Project Work.

39
Q

What is the purpose of an Issue Log?

A

To record issues, or unresolved threats or problems, on the project or at points of disagreement. Helps to organize issues, but lets stakeholders and the team know these are actively being reviewed.

40
Q

How does the process Manage Project Knowledge benefit the project?

A

It leverages lessons learned from previous projects and benefits the performing organization so that it can hold onto lessons learned on this project.

41
Q

When is the most ideal time to perform the Manage Project Knowledge process?

A

Anytime, but most logical after completion of a deliverable or phase of the project.

42
Q

What are the inputs for Manage Project Knowledge?

A

Project Management Plan

Project Documents

43
Q

How do deliverables impact Manage Project Knowledge?

A

They shape the learning that needs to be captured.

44
Q

What tools are used for Manage Project Knowledge?

A

Expert Judgement, Knowledge Management (explicit and tactic knowledge), Information Knowledgement, and Interpersonal and Team Skills

45
Q

What is explicit knowledge?

A

Explicit knowledge is information written down or drawn and easily archived for future lessons learned.

46
Q

What is tactic knowledge?

A

Tactic knowledge includes beliefs, opinions and abilities that are may be more difficult to put into a format for archiving.

47
Q

What is the idea behind Knowledge Management?

A

To get people to interact and share knowledge and experience, includes networking, facilitating workshops, meetings, etc.

48
Q

What is Information Management and how does it differ from Knowledge Management?

A

Information Management is the sharing of documents, tools, templates and lessons learned with other people on your team and in the organization. It requires capturing explicit, codified information. Knowledge Management is often based on experiential knowledge, whereas information is based on concrete data.

49
Q

What are the outputs of Manage Project Knowledge?

A

Lessons Learned Register, Project Management Plan Updates and Organizational Process Assets Updates.

50
Q

What is a lessons learned register?

A

A register documenting what worked well, what did not, what the team would differently if it had this project to do over again.

51
Q

What is the purpose of the process Monitor and Control Project Work?

A

To evaluate the work being performed on a project and make sure the deliverables and way in which they are being produced are in line with the project plan/meeting objectives. Allows the Project Manager to take corrective actions as needed through change requests.

52
Q

What other process is Monitor and Control Project Work closely tied to?

A

Direct and Manage Project Work

53
Q

What are the Inputs for Monitor and Control Project Work?

A
Project Management Plan *primary input*
Project Documents
Assumption Log
Basis of Estimate - backup information for estimates
Cost Forecasts
Issue Log
Lessons Learned Register
Milestone List
Quality Reports
Risk Register
Risk Report
Schedule Forecasts
Work Performance Information
Agreements
Enterprise Environmental Factors
Organizational Process Assets
54
Q

What do cost forecasts and schedule forecasts do?

A

Schedule forecasts are updated projections for the activities and overall schedule based on performance and actual data.

Cost estimates are adjusted for performance using Estimate at Complete (EAC), Estimate to Complete (ETC), Budgeted at Completed (BAC), the Cost Performance Index (CPI), and others.

55
Q

What is the WPI and why is it importance?

A

Work Performance Information that provides actual results that can be compared against the project management plan.

56
Q

What are the tools used in Monitor and Control Project Work?

A

Expert Judgement, Data Analysis, Decision Making, Meetings

57
Q

What are the outputs for Monitor and Control Project Work?

A

Work Performance Reports actionable
(Ex: dashboards, heat reports, burndown charts, and
traffic lights)
Change Requests
Project Management Plan Updates
Project Document Updates

58
Q

What is the idea behind the process Perform Integrated Change Control?

A

Evaluate changes and their impact to the entire project/each area of the project.

59
Q

What is the difference between Perform Integrated Change Control and Control Project Work?

A

Change Control focuses on managing change to the project, while Control Project Work manages the way the work is carried out.

60
Q

What are the inputs for Perform Integrated Change Control?

A
Project Management Plan
Project Documents
Work Performance Reports
Change Requests *** key input - very important***
Enterprise Environmental Factors
Organizational Process Assets
61
Q

What are the tools used for Perform Integrated Change Control?

A
Expert Judgement
Change Control Tools
Data Analysis
Decision Making
Meetings (may consist of Change Control Board per Project Management Plan, committee assigned to review and approve changes)
62
Q

What are the outputs for Perform Integrated Change Control?

A

Approved [or Rejected] Change Requests
Project Management Plan Updates
Project Documents Updates

63
Q

What happens to an Approved Change Request?

A

Channeled back into Direct and Manage Project Work process. Documented on Change Log.

64
Q

What is a key attribute of any project?

A

It has an end, it is temporary.

65
Q

What is the goal of the process Close Project or Phase?

A

To shut down/end the project.

66
Q

Why is Close Project or Phase important?

A

It provides an official close of the project, and releases the team as part of the process.

67
Q

What are the inputs for the process Close Project or Phase?

A
Project Charter *should outline exit criteria*
Project Management Plan
Project Documents
Accepted Deliverables ***Key Input***
Business Documents
Agreements
Procurement Documentation
Organizational Process Assets
68
Q

What tools are used in the process Close Project or Phase?

A

Expert Judgement, Data Analysis and Meetings

69
Q

What are the outputs for Close Project or Phase?

A

Project Documents Update (Lessons Learned Register)
Final Product, Service or Result Transition (acceptance and handover of responsibility)
Final Report
Organizational Process Assets Update (may include formal acceptance documentation, project closure documents, project files, and historical information)

70
Q

Key points re: Agile Perspective on Integration Management

A

On Agile, rather than the 7 processes of Integration Management falling on the Project Manager, they fall on the team as a whole:

Develop Project Charter still key
Assumption Logs less important in Agile
Develop Project Management Plan less important in Agile, risks instead managed by being adaptive and responsive
Direct and Manage Project Work still key, shorter, more rapid iterations of work
Manage Project Knowledge, still key
Monitor and Control Project Work applicable but handled very differently
Perform Integrated Change Control difficult to apply to Agile, changes occur more naturally as part of the process (change embraced)
Close Project or Phase, yes but outputs reduced to “barely sufficient” documentation, receives less emphasis on Agile projects.

71
Q

A defect in the product was brought to the project manager’s attention, and now the project team is engaged in repairing it. Which project management process would be the most applicable to this?

A

Direct and Manage Project Work

72
Q

Change control meetings are held as part of which process?

A

Perform Integrated Change Control

73
Q

Is the following statement about project agreements true of false - Agreements are one of four inputs to create the project charter?

A

True

74
Q

Work performance information is not use for the following reason…

A

To Identify defects

75
Q

You are a project manager, and your team is executing the work packages to produce a medical records archive and retrieval system. Two of the project’s customers have asked for changes that each says should be the number one priority. What would be the best thing to do?

A

Prioritize the changes without involving the team… because prioriting the changes is the job of the Project Manager.

76
Q

The program mamanger is asking why your project is scheduled to take 16 months. He claims that previous projects in the organization were able to be completed in less than half of that time. What would be the BEST thing to do?

A

Look for historical information on previous projects to understand them better. Will either show you how the projects vary, thus justify the schedule, or perhaps show you how someone else accomplished the same type of work in less time… Either way providing a benchmark for your to factor in to your project.

77
Q

Two project are being considered by the project office: Project Clarity, and Project New Scale. The Chief Project Office is planning to evaluate the projected Return on Investment Capital for both projects. In order to do that, what information would be most helpful?

A

Total Projected capital investment and net income (Net Income and Total Capital Investment)

78
Q

Which component(s) of the project management plan is created in the Develop Project Management Plan?

A

The Change Management Plan, the configuration management plan and the performance measurement baseline.