Chapter 7. Cost Management Flashcards
What are the four processes of Cost Management?
Plan Cost Management
Estimate Costs
Determine Budget
Control Costs
What are the outputs for the four processes of Cost Management?
Plan Cost Management - Cost Management Plan
Estimate Costs - Cost Estimates
Determine Budget - Cost Baseline and Project Funding Requirements
Control Costs - Work Performance Information and Cost Forecasts
What is Life-Cycle Costing?
It looks at the total cost of ownership from purchase or creation, through operations, and finally to disposal. Encompasses the bigger picture of ownership costs.
What is Value Engineering?
The practice of trying to get more out of the project in every possible way, to increase the bottom line, decrease costs, improve quality, shorten the schedule, and generally squeeze more benefit and value out of each aspect of the project.
What is the key to Value Engineering?
Reducing costs without reducing the scope of work.
When is the process of Plan Cost Management performed?
After scope and schedule activities have been performed.
Some exceptions apply: Overall budgets and/or budgetary constraints may be determined before the project is initiated.
What are the inputs to Plan Cost Management?
Project Charter
Project Management Plan
Enterprise Environmental Factors
Organizational Process Assets
What are the tools used in the process Plan Cost Management?
Expert Judgement, Data Analysis, and Meetings
What are the outputs of Plan Cost Management?
Cost Management Plan
What is a Cost Management Plan?
Document that describes how processes of Estimate Costs, Determine Budget, and Control Costs will be carried out. Becomes part of the project management plan. Specifies units of measure (USD, pesos, yen, etc), and levels of accuracy. Also specifies approval thresholds, how those approvals are carried out, and will define how cost performance is measured.
When is the process of Estimate Costs performed?
After Develop Schedule. This is because costs are estimates against schedule activities, so the project’s schedule has to be created first.
See graphic at bottom of p. 295.
What is the leeway for a Rough Order of Magnitude?
-25% to +75%
What is the leeway for a Preliminary Estimate?
-20% to +30%
What is the leeway for a Definitive Estimate?
-5% to +10%
What are the three estimate types?
Rough Order of Magnitude Estimates, Preliminary Estimate, Definitive Estimate
When is a Rough Order of Magnitude used?
During the initation of a project, where very little has been defined.
What is the inputs for the process Estimate Costs?
Project Management Plan Project Documents - Lessons Learned Register - Project Schedule - Resource Requirements - Risk Register Enterprise Environmental Factors Organizational Process Assets
What are the tools used for the process Estimate Costs?
Expert Judgement Analogous Estimating Parametric Estimating Bottom-Up Estimating Three-Point Estimating Data Analysis - Alternative Analysis - Reserve Analysis - Cost of Quality Project Management Information System Decision Making