Chapter 8 Managing Project Stakeholders & Communication Flashcards

1
Q

A ____ shows how the scope, features or functionality, or work is being completed over time.

a. Budget report
b. Status report
c. Burn-down Chart
d. Forecast report
e. Progress report

A

: Burn-down Chart

A burn-down chart provides a useful tool for reporting a project’s progress. As the project team “burns” through the scope, the velocity or burn-down rate represents the amount of work that can be delivered in a single iteration. As a result, the completion of the project work can be predicted.

Chapter 8 page 213

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Actual Cost (AC) is ____.

a. how much of the budget we have left to spend on the project
b. how much of the budget we really should have spent on the work completed so far.
c. how much we budgeted to spend at the beginning of the project.
d. None of these
e. how much we actually spent for work completed

A

: how much we actually spent for work completed

*** It is the total direct and indirect costs incurred in accomplishing work on an activity during a given period.

Chapter 8 page

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Earned Value (EV) tells us ____

a. how much we actually spent for work completed
b. how much we budgeted to spend a the beginning of the project
c. None of these
d. how much of the budget we really should have spent on the work completed so far
e. how much of the budget we have left to spend on the project.

A

: how much of the budget we really should have spent on the work completed so far

Chapter 8 page 216

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Information distribution includes all of the following except:

a. Web-based technologies
b. Face-To-Face meetings
c. All of these are examples of information distribution
d. Telephone, e-mail and other wireless devices
e Paper and electronic project reports

A

: All of these are examples of information distribution

Chapter 8 page

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A metric that provides an estimate for completing the scheduled work that remains once the project is started is called the ____.

a. Budged at Completion (BAC)
b. Expected Time Complete (ETC)
c. Actual Cost (AC)
d. Planned Value (PV)
e. Estimate at Completion (EAC)

A

: Expected Time Complete (ETC)

Chapter 8 page

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Expected Time to Completion (ETC) is ____.

a. how much time it took to complete the work
b. how long we expected the task to take
c. how much time we have left to complete the project
d. how much longer it will take to complete the project
e. how much time it should have taken to complete the task

A

: how much longer it will take to complete the project

Chapter 8 page

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The cost incurred for completing a scheduled task or WBS component is the ____ .

a. Estimate at Completion (EAC)
b. Planned Value (PV)
c. Budget At Completion (BAC)
d. Expected Time Complete
e. Actual Cost (AC)

A

: Actual Cost (AC)

Chapter 8 page

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A ____ describes the present state of the project and provides compares the project’s actual progress to the baseline plan.

a. Progress report
b. Budget report
c. Forecast report
d. News report
e. Status report

A

: Status report

Chapter 8 page

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The budgeted cost of work scheduled for an activity or component of the WBS is the ____.

a. Actual Cost (AC)
b. Budget At Completion (BAC)
c. Planned Value (PV)
d. Expected Time Complete (ETC)
e. Estimate at Completion (EAC)

A

: Planned Value (PV)

Chapter 8 page

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

EV - AC = ____

a. Scheduled performance index (SPI)
b. Cost Variance (CV)
c. Cost performance Index (CPI)
d. Minimum funds needed (MFN)
e. None of these

A

: Cost Variance (CV)

Chapter 8 page

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The ____ is an estimate of the value of the physical work actually completed.

a. Actual Cost
b. Earned Value
c. Scheduled Variance
d. Planned Value

A

: Earned Value (EV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Variances are calculated by subtracting the actual cost or planned value from ____.

a. Earned Value
b. Actual Cost
c. Planned Value
d. Scheduled Variance

A

: Earned Value (EV)

V = AC - EV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly