Chapter 7 - Project Team Planning Flashcards

1
Q

What document is used to determine the types of human resources required and their timing?

A

The Project HR Requirements document

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What does the Resource Manager do?

A
  • helps projects acquire human resources that are needed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the Project HR Requirements document?

A

A document holding human resource requirements

  • type of human resources needed
  • amount of time they’re needed for
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the Project Roles and Responsibilities document?

A

A document that lets team members know their role and what is expected of them

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a RAM (project management terms)

A

Responsibility Assignment Matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What does the Responsibility Assignment Matrix do?

A

clarify the planned involvement of people

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a RACI Chart?

A

Responsible
Accountable
Consulted
Informed

  • team members are assigned to be responsible, accountable, consulted, informed for specific activities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the use of an Organization Chart?

A

Hierarchical chart that demonstrates organization of project and how areas of responsibilities interrelate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly