Chapter 5 - Schedule Planning Flashcards

1
Q

What is a Project Activity List?

A

A list of tasks needed to complete each work package of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the Project Schedule?

A

The timing for each activity in the Activity List

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the Project Schedule based on?

A
  • the required sequence of work
  • the completion of activities on a certain date
  • the duration of time the activity will take
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a Network Diagram?

A

A useful tool for displaying the logical order of activities

- rectangles define tasks, arrows connect tasks in order of completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the three main types of Project Schedules?

A
  • milestone based
  • activity based
  • dependency based
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a Milestone based Schedule?

A

Each milestone is given with the date it should be completed by
- sorted in chronological order

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is an Activity Based Schedule?

A

Each activity is given with a duration, start date and end date

  • sorted in chronological order
  • can be shown with activities under categories such as “To Do”, “Doing”, and “Done”
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a Dependency Based Schedule?

A

A Gantt Char

  • tasks are shown on a timeline for their duration
  • tasks are connected depending on which tasks need to be done first
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is Finish to Start Dependencies?

A

Task 1 needs to be finished before starting task 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is Start to Start Dependencies?

A

Task 1 and task 2 can be started at the same time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is Finish to Finish Dependencies?

A

Task 1 and Task 2 must end at the same time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is Dependency Lead?

A

Task 2 can start a set of time before (lead) task 1 ends

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is Dependency Lag?

A

Task 2 can start a set of time after (lag) task 1 ends

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is Critical Path?

A

The longest sequence of activities in a project

- this is the earliest the project can be completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is Total Float?

A

The amount of time an activity can be delayed before it delays the project end date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is Forward Pass?

A

The earliest that each activity may occur

  • Early Start (ES)
  • Early Finish (EF)
17
Q

What is Backward Pass?

A

The latest that each activity may occur

  • Late Start (LS)
  • Late Finish (LF)
18
Q

What are the four dependency types?

A
  • Finish->Start
  • Start->Start
  • Finish->Finish
  • Start->Finish
19
Q

What is Baseline?

A
An approved part of the project plan
- scope
- cost
- schedule
Used as a basis for comparison when measuring the progress of the project or considering changes to the plan
20
Q

What is Free Float?

A

Amount of time an activity can be delayed before it delays a subsequent task or the project end date