Chapter 7: Project Cost Management Flashcards
What are the 10 tools and techniques for Estimated Costs?
Expert judgement Analogous estimating Parametric estimated Bottom-up estimating Three-point estimating Reserve analysis Cost of quality Project management software Vendor bid analysis Group decision-making techniques
What are the 3 outputs of the Determine Budget process?
Costbaseline
Project funding requirements
Project documents updates
What are the 7 inputs to the Estimated Cost process?
Cost management plan Human resource management plan Scope baseline Risk register Enterprise environmental factors Organizational process assets
What are the 4 processes of Project Cost Management?
Plan Cost Management
Estimate Costs
Determine Budget
Control Costs
What is the Determine Budget process?
The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.
What are the 4 inputs to the Control Costs process
Project management plan
Project funding requirements
Work performance data
organizational process assets
What is bottom-up estimating?
A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS)
What does the scope baseline consist of?
Scope statement
WBS
WBS dictionary
What are the 3 outputs of the Estimate Cost process?
Activity cost estimates
Basis of estimates
Project documents updates
What is the total planned value for a project also known as?
The BAC (Budget at completion)
What are the 8 parameters normally established by the cost management plan?
Units of measure Level of precision Level of accuracy Organizational procedure links Control thresholds Rules of performance measurement Reporting formats Process descriptions
What is the three-point estimate named PERT?
A technique for estimating that applies a weighted average of optimistic, pessimistic, and most likely estimates when is uncertainty with the individual activity estimates.
What are some resources for which cost estimates should be developed on a project?
Labor Materials Equipment Services Facilities Inflation allowance Contingency Cost of financing
What are the 2 main categories of cost in cost of quality?
Conformance and nonconformance
What are the 5 tools and techniques for the Determine Budget process
Cost aggregation Reserve analysis Expert judgement Historical relationships Funding limit reconciliation
What are the 6 tools and techniques for the Control Cost process
Earned value management Forecasting To-complete performance index (TCPI) Performance reviews Project management software Reserve analysis
What are the term EAC mean?
Estimate at completion
What is the most accurate EAC formula that works in every project case and must be used when the original estimates are fundamentally flawed?
EAC = AC + a new bottom-up ETC