Chapter 6: Project Time Management Flashcards

1
Q

Decomposition, rolling wave planning, and expert judgement are tools and techniques for which process?

A

Define Activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The schedule baseline, project schedule, schedule data, project calendars, project management plan updates , and project documents updates are outputs of which project Time Management process?

A

Develop Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How is total float calculated?

How is free float calculated?

A

LS - ES

LF - EF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is meant by the terms “work effort” and “duration”?

A

Work effort: The total number of labor units required to complete an activity, typically stated in parson hours, person days, person weeks, etc.
Duration: The number of work periods hat it will take to complete an activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is reserve analysis?

A

An analytical technique to determine the essential features and relationships of components in the project management plan to establish a reserve for the schedule duration, budget, estimated cost, or funds for a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What do the Project Time Management processes ensure?

A

The timely completion of a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the 2 methods for schedule compression?

A

Crashing: Adding ressources to critical path activities

Fast tracking: Applying a lead to activities that would typically start only after precedent activities are finished

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are 3 ways to graphically edict a project schedule?

A

Network diagram
Bar chart or Gantt chart
milestone chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What does a network diagram show, and what does it not show?

A

It shows the project’s scheduled activities and the logical relationships among those activities. It might or might not show the duration for each activity
It does not show the start and finish dates of the project, nor the resources needed for the activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are 4 types of dependencies?

A

Mandatory
Discretionary
external
Internal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the PMI definition of critical path?

A

The sequence of activities that represents the longest path trough a project, which determine the shortest possible duration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is rolling wave planning?

A

An iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the typical activities of variance analysis?

A

Look at the baseline and the actual differences
Determine the cause of the differences
Determine whether corrective action is necessary

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Activity duration estimates and project documents updates are the outputs for which Project Time Management process?

A

Estimate Activity Durations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the 7 tools and techniques for the Control Schedule process?

A
Performance reviews
Project management software
Resource optimization technique
Modeling techniques 
Leads and lags
Schedule compression
Scheduling tool
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is resource levelling?

Give an example of a resource levelling heuristic

A

Resource leveling: A technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with available supply.
Heuristics examples:
Work can be levelled only between resources of the same type or same skill level.
Critical path activities have priority in leveling over noncritical path activities.

17
Q

What are 2 specific types of network diagrams?

A

AON (activity-on-node)

AOA (activity-on-arrow)

18
Q

What are some risks of crashing or fast-traking a project schedule?

A

Increase costs
Unrealistic alternatives
Communication challenges

19
Q

What is decomposition?

A

A technique used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts.

20
Q

What is the purpose of a resource calendar?

A

To show when, and for how long, resources (such as equipment, people, and materials) are potentially available

21
Q

Expert judgement, alternatives analysis, published estimating data, bottom-up estimating, and project management software are tools and techniques for which Project Time Management process?

A

Estimate Activity Resources

22
Q

What are the 6 tools and techniques for the Estimate Activity Durations process?

A
Expert judgement
Analogous estimating
Parametric estimating
Three-point estimates
Group decision making-techniques
Reserve analysis
23
Q

What are contingency reserves?

A

A budget within the cost baseline or performance measurement baseline that is allocated for identified risks that are accepted and for which contingent or mitigating response are developed.

24
Q

What are the 6 Project Time Management processes and which Process Groups do they fit in?

A
Define Activities: Planning
Sequence Activities : Planning
Estimate Activity Ressources: Planning
Estimate Activity Durations: Planning
Develop Schedule: Planning
Control Schedule: Monitoring and Controlling
25
Q

What are the characteristics of the project schedule?

A

It is calendar based
It has resources assigned
It is signed off as part of the project management plan
It forms the basis for measuring schedule performance

26
Q

What is meant by the terms “lead” and “lag”?

A

Lead: The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Lag: The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity

27
Q

What are 4 types of dependencies or precedence relationships?

A

Finish-to-start
Finish-to-finish
Start-to-start
Start-to-finish

28
Q

Which activities have no slack or float?

A

Typically, the activities on the critical path have no float or slack; therefore, the project manager needs to watch these activities more closely than others that have float or scheduling flexibility.

29
Q

What are the 4 inputs for the Define Activities process?

A

Schedule management plan
Scope baseline
Enterprise environmental factors
Organizational process assets

30
Q

What are the 3 outputs of the Define Activities process?

A

Activity list
Activity attributes
Milestone list

31
Q

What is the formula for the three-point estimate, PERT?

A

Te= (To+4Tm+Tp)/6