Chapter 6: Project Time Management Flashcards
Decomposition, rolling wave planning, and expert judgement are tools and techniques for which process?
Define Activities
The schedule baseline, project schedule, schedule data, project calendars, project management plan updates , and project documents updates are outputs of which project Time Management process?
Develop Schedule
How is total float calculated?
How is free float calculated?
LS - ES
LF - EF
What is meant by the terms “work effort” and “duration”?
Work effort: The total number of labor units required to complete an activity, typically stated in parson hours, person days, person weeks, etc.
Duration: The number of work periods hat it will take to complete an activity
What is reserve analysis?
An analytical technique to determine the essential features and relationships of components in the project management plan to establish a reserve for the schedule duration, budget, estimated cost, or funds for a project.
What do the Project Time Management processes ensure?
The timely completion of a project
What are the 2 methods for schedule compression?
Crashing: Adding ressources to critical path activities
Fast tracking: Applying a lead to activities that would typically start only after precedent activities are finished
What are 3 ways to graphically edict a project schedule?
Network diagram
Bar chart or Gantt chart
milestone chart
What does a network diagram show, and what does it not show?
It shows the project’s scheduled activities and the logical relationships among those activities. It might or might not show the duration for each activity
It does not show the start and finish dates of the project, nor the resources needed for the activities.
What are 4 types of dependencies?
Mandatory
Discretionary
external
Internal
What is the PMI definition of critical path?
The sequence of activities that represents the longest path trough a project, which determine the shortest possible duration.
What is rolling wave planning?
An iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level.
What are the typical activities of variance analysis?
Look at the baseline and the actual differences
Determine the cause of the differences
Determine whether corrective action is necessary
Activity duration estimates and project documents updates are the outputs for which Project Time Management process?
Estimate Activity Durations
What are the 7 tools and techniques for the Control Schedule process?
Performance reviews Project management software Resource optimization technique Modeling techniques Leads and lags Schedule compression Scheduling tool