Chapter 12: Project Procurement Management Flashcards

0
Q

What is involved in the Manage Stakeholder Engagement process?

A

Communicating and working with stakeholders to meet their needs and to address issues they bring up as they occur

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

Selected sellers, agreements, resource calendars, change requests, project management plan updates, and project documents updates are outputs for which Project Procurement Management process?

A

Conduct Procurements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the interpersonal skills that the project manager might apply when managing stakeholder engagement?

A

Building trust
Resolving conflict
Actively listening
Overcoming resistance to change

You can find more on interpersonal skills in appendix X3 of the PMBOK® Guide

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the 4 inputs to the Plan Stakeholder Management process?

A

Project management plan
Stakeholder register
Enterprise environmental factors
Organizational process assets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the 3 tools and techniques used in the Control Stakeholder Engagement process?

A

Information management system
Expert judgment
Meeting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is PTA (point of total assumption)?

A

PTA is the not-to-exceed cost, set by the buyer, in a cost-plus contract. When the actual cost differ from the estimated costs, the buyer and the seller split the difference along an agree-upon split. Any costs above the PTA must be paid solely by the seller. The formula for PTA is:

PTA = [ceiling price - Total price\buyer share] + total cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are some characteristics of a contract?

A

It is a formal, mutually binding agreement between parties
Terms are enforceable by the legal system
Changes must be formally controlled and in writing
All requirements should be stated in the contract
All contractual requirements must be met
All requirements including reporting requirements, payments terms, ownership and copyright terms, etc., must be documented in the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the characteristics of a time and material contact?

A

The buyer and the seller both share the risk of cost
It is a cross between fixed-price and cost plus contracts
The unit price is established but not the quantity
The scope of work does not have to be known
The total price of the contracts is initially unknown

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the purpose of the contract SOW?

A

To describe the work the contractor will provide in enough detail that sellers can determine whether they can provide the needed services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are some other terms for “contract”?

A

Agreement
Understanding
Subcontract
Purchase order

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is “procurement”?

A

Purchasing goods, services, or results typically from outside the organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the 4 Project Procurement Management Processes?

A

Plan Procurement Management
Conduct Procurements
Control Procurements
Close Procurements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the 3 main types of contracts?

A

Fixed-price contracts
Cost-reimbursable contracts
Time and material contracts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are some of the components of procurement management plan?

A

Contract types
Procurement documents to be used
Procedure for managing multiple vendors
Processes for handling make-or-buy decisions
Outline of requirements for contracts WBS
List of prequalified sellers
Metrics to be used to evaluate and manage sellers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Which factors are considered in a make-or-buy analysis?

A

Cost
Technical ability of the organization to do the work
Capacity of the organization’s facilities
Available personnel
Time required to complete the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are some examples of source selection criteria (a tool and technique for Plan Procurement Management)?

A
Understanding of need
Overall or life-cycle cost
Technical capability
Risk
Management approach
Warranty
Financial capacity
Production capacity and interest
Business size and type
Past performance of sellers
References 
Intellectual property rights 
Proprietary rights
16
Q

What are some other terms for “buyer”?

A
Client
Customer
Prime contractor
Contractor
Acquiring organization
Government agency
Service requestor
Purchaser
17
Q

What is a “proposal”?

A

Also called a bid, tender, or quote, a proposal is a document prepared by the seller to explain the costs, services, terms, etc., by which the seller will meet the terms of the contract with the buyer.