Chapter 21 Flashcards

1
Q

AHJ

A

Authority Having Jurisdiction
The building official, electrical
inspector, fire marshal, or other
individuals or entities
responsible for interpretation
and enforcement of local
building and electrical codes.
TDMM.* Page G-14

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

As-Built

A

The documentation of
measurements, location, and
quantities of material work
performed. May be in the form
of marked up documents or
other work order forms.
TDMM.* Page G-12

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Bidders’ Conference

A

A meeting conducted by the
issuer of a request for quote or
request for proposal to review
and address any questions from
respondents (bidders) with
regard to the bid documents.
TDMM.* Page G-20

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

BIM

A

Building Information Modeling
The process of generating and
managing buildina data during a
facility’s life cycle using three-
dimensional models of a building
and incorporating detailed product
information, quantities, and
properties into those models.
TDMM.* Page 21-51

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

BOM

A

Bill of Materials
A list of the quantity and specific
types of materials to be used on
a project. This list also should
consider miscellaneous
hardware (e.g., screws, bolts).
TDMM.* Page G-20

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Change Order

A

Formal document that defines
the required changes in project
scope and identifies associated
changes to the time frame, the
dollar amounts, or both.
TDMM.* Page 21-40

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Code

A

A rule or set of rules intended to
ensure safety during the
installation and use of materials,
components, fixtures, systems,
premises, and related subjects.
TDMM.* Page 21-30

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Commissioning

A

The start-up of a system that
includes testing and adjusting
the systems to ensure proper
functioning and adherence to
design criteria.
TDMM.* Page G-41

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Design-Build
Construction

A

A delivery method whereby the
owner contracts with a single
entity known as the
DB team.
TDMM.* Page 21-37

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

OBS

A

Organization Breakdown
Structure
A hierarchal chart that visually
represents people and
organizations who are
stakeholders in a project
regardless of their company or
organizations. An OBS should
include contact information for
each team member.
TDMM.* Page G-135

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Project Management

A

A discipline that encompasses
planning, organizing, and
managing resources to achieve
successful completion of
specific project goals
and objectives.
TDMM.* Page 21-5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

RFI

A

Request for Information
A type of document or process,
generated by either an owner,
owner’s agent, or contractor, to
obtain information or to clarify
the capabilities of various
products, services, processes or
requirements.
TDMM.* Page G-163

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

RFP

A

Request for Proposal
An invitation for the design
professionals (e.g., architect,
engineer, consultant) or
contractors to submit a
proposal for services.
TDMM.* Page 21-36

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

RFQ

A

Request for Quotation
A type of procurement
document or process used to
solicit prices from prospective
providers of products or
services.
TDMM.* Page G-764

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Risk

A

A vulnerability to or potential for
loss from a threat or event.
TDMM.* Page G-167

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Risk Management

A

The process of identifying risks
and developing the strategy and
tactics needed to eliminate,
mitigate, or manage them.
TDMM.* Page G-167

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Schematic Design

A

A structural or procedural
diagram used in association
with telecommunications and
electrical systems.
TDMM.* Page G-170

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

SoW

A

Scope of Work
A contractual vehicle for
expressing the specific
agreement between contractor
and the owner of the project.
TDMM.* Page 21-10

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Shall

A

A term frequently used in codes
and standards publications that
indicates a mandatory
requirement.
TDMM.* Page G-174

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Should

A

Frequently used in codes and
standards publications, the term
indicates the statement is
advised but not required.
TDMM.* Page G-175

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

WBS

A

Work Breakdown Structure
A breakdown of all of a project’s
main work elements into
smaller, more manageable,
activity groupings.
TDMM.* Page 21-18

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is Six Sigma?

A

A project-driven method aimed
at sustainable business
performance improvement
TDMM.* Page 21-4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Name 8 traits of a good
Project Manager (PM).

A

1 .Conflict management skills
2.Organizational skills
3.Ability to assume authority
4.Ability to focus on key issues
5.Good communication skills
6.Flexibility
7.Personal accountability
8.Ability to coordinate with diverse groups
TDMM.* Page 21-5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Name the 3 basic steps
for managing a
telecommunications
project.

A

1 .Build a project plan
2. Track and manage the project
3.CIose the project
TDMM.* Page 21-6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What is the role of a PM?

A

To develop a team from among
the individuals involved in the
project, which requires both
leadership and planning
TDMM.* Page 21-6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Which TPM knowledge
area includes project safety
and personnel issues?

A

Human resource management
TDMM.* Page 21-6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Which TPM knowledge
area includes a list of
assumptions about the
project?

A

Scope management
TDMM.* Page 21-6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Which TPM knowledge
area covers running
multiple small projects as
one large project?

A

Integration management
TDMM.* Page 21-7

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Which TPM knowledge
area includes the
project’s schedule?

A

Time management
TDMM.* Page 21-7

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Which TPM knowledge
area includes the
project’s budget?

A

Cost management
TDMM.* Page 21-7

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Which TPM knowledge
area includes client value
items such as punctuality?

A

Quality management
TDMM.* Page 21-7

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Which TPM knowledge
area would cover the use
of a “war room”?

A

Communications management
TDMM.* Page 21-7

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

What should be completed
prior to submitting a
project proposal as part of
risk management?

A

Risk assessment
TDMM.* Page 21-7

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Which TPM knowledge
area covers the storage
costs of bulk purchases?

A

Procurement management
TDMM.* Page 21-8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Which TPM knowledge
area includes the
identification of all internal
and external parties holding
an interest in the project?

A

Stakeholder management
TDMM:Page21-81

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

What is the purpose of a
lessons learned meeting?

A

To discuss what went well and
what could be improved
TDMM.* Page 21-9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

What does the scope of
work establish?

A

The requirements for the
performance of work to achieve
the project objectives
TDMM.* Page 21-9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

What do the words “should”
and “may” indicate when
they are included
in the SOW?

A

That the requested action is
purely optional
TDMM.* Page 21-9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

What does the word
“shall” indicate when it is
included in the SOW?

A

That the requested action
is mandatory
TDMM.* Page 21-9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

What are risks associated
with having a poorly
defined SOW?

A

Capable contractors may
decline to bid on the project, or
they may dispute their
responsibilities during the
construction phase.
TDMM.* Page 21-70

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

What step can be taken to
manage a client’s expectations
for a project?

A

Develop detailed documents on
the front end of the project
TDMM.* Page 21-10

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

Name 3 types of Sows.

A

1 .Performance
2.Design
3.Combination of both
TDMM: Page 21-11

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

What type of SOW tells the
contractor the objectives
and parameters to be
accomplished and the
end goal or desired
achievement?

A

Performance type
TDMM.* 21-11

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

What type of SOW directs
the contractor to use
specific products
and materials?

A

Design type
TDMM.* Page 21-11

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

Name the 4 steps that are
involved in preparing
the SOW.

A

1 .Perform basic planning
2.Outline the SOW
3.Organize the project team
4.Write and review
TDMM.* Page 21-11

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

Name 4 benefits of creating an outline for the SOW.

A
  1. Allows full attention to be directed to the technical content
  2. Helps to guard against significant admissions
  3. Aids in achieving continuity throughout the project
  4. Helps eliminate redundant material and work
    TDMM.* Page 21-13
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

True or False
Progress reports are
considered deliverables.

A

False. Progress reports are not
considered deliverables because
they are not the final result
of a task.
TDMM.* Page 21-14

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

Who is responsible for
holding a safety meeting at
the start of the project?

A

Safety coordinator
TDMM.* Page 21-16

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

What is the recommended
method for identifying the
people and organizations
needed to complete the
project as detailed in
the SOW?

A

Organization breakdown
structure (OBS)
TDMM.* Page 21-17

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

Name 4 elements that must be included in a WBS.

A

1 .Planning and design activities
2. Project approval and start
3. ImpIementation of work elements
4. Completing the project
TDMM.* Page 21-18

51
Q

How many hours are
usually included in a
work package?

A

40
TDMM.* Page 21-18

52
Q

How are PERT diagrams used?

A

To calculate the start and finish date for each activity on the project
TDMM.* Page 21-21

53
Q

What does a Gantt chart
use to show the duration
of an activity?

A

Bar chart from start
to finish date
TDMM.* Page 21-22

54
Q

How does a Gantt chart
differ from a PERT chart?

A

Unlike a PERT chart,
the Gantt chart does not show
predecessor or successor
relationships.
TDMM.* Page 21-22

55
Q

Name 5 methods for
developing an estimate.

A

1 .AnaIogous
2.Parametric
3.Engineering
4.Subcontractor bids
5.PERT
TDMM.* Page 21-23

56
Q

What is the basis of an
analogous estimate?

A

The time or cost it took to
perform similar work in the past
TDMM.* Page 21-23

57
Q

Name 3 parameters that
could be used as a basis
for PERT estimates.

A

1 .Dollar/foot
2.DolIar/drop time
3.Cost
TDMM.* Page 21-23

58
Q

Who develops the
engineering estimate?

A

The client
TDMM.* Page 21-23

59
Q

What type of price
is provided in a
subcontractor bid?

A

A price that will not be exceeded
TDMM.* Page 21-23

60
Q

Name the 3 estimates used
by the PERT program to
develop a weighted
average estimate.

A

1 .Optimistic estimate
2.Most likely estimate
3.Pessimistic estimate
TDMM.* Page 21-23

61
Q

What information is
provided in the
optimistic estimate?

A

The lowest projected cost
or fastest time
TDMM.* Page 21-23

62
Q

What is the PERT formula?

A

(Optimistic + (4 x Most Likely) + Pessimistic)/6
TDMM.* Page 21-23

63
Q

What is the relationship
between the pessimistic
and most likely estimates
and project risk?

A

The greater the difference
between the estimates, the
greater the risk.
TDMM.* Page 21-23

64
Q

When is an activity labeled
“high risk” based on PERT
estimates?

A

When the difference between
the most likely and pessimistic
estimates is greater than
10 percent
TDMM.* Page 21-24

65
Q

What does the SPI
represent?

A

The amount a project is ahead
or behind schedule
TDMM.* Page 21-24

66
Q

What does an SPI value
of 1 indicate?

A

The project is on schedule.
TDMM.* Page 21-24

67
Q

What does an SPI value
that is less than 1 indicate?

A

The project is behind schedule.
TDMM.* Page 21-24

68
Q

What does an SPI value
that is greater than
1 indicate?

A

The project is ahead
of schedule.
TDMM.* Page 21-24

69
Q

What does a CPI value of
less than 1 indicate?

A

The project is over budget.
TDMM.* Page 21-26

70
Q

What does a CPI value that
is greater than 1 indicate?

A

The project is under budget.
TDMM.* Page 21-26

71
Q

What is the focus of
conformance quality?

A

Physical quality
TDMM.* Page 21-26

72
Q

What principle does
conformance quality
follow?

A

Plan, do, check, and act
TDMM.* Page 21-26

73
Q

How are the results of
client satisfaction
surveys used?

A

They are used to improve
performance, provide feedback
to management, and, in some
cases, provide bonuses
to employees.
TDMM.* Page 21-26

74
Q

How is client value
quality measured?

A

On a relative basis as compared
with the competition
TDMM.* Page 21-26

75
Q

Who is responsible for
formally approving
change orders?

A

The client
TDMM.* Page 21-28

76
Q

What is the purpose
of a code?

A

*Ensure the practical
safeguarding of persons and
property from hazards
*Ensure the quality of
construction
TDMM: Page 21-30

77
Q

Who is responsible for
enforcing codes once they
are adopted or ratified by
the local government?

A

Authority Having Jurisdiction
(AHJ)
TDMM.* Page 21-30

78
Q

What is a standard?

A

An accepted collection of requirements and recommendations for the defining, construction, evaluation, application, or comparison materials, equipment, products, and services
TDMM.* Page 21-31

79
Q

What is one purpose
of a standard?

A

To ensure a minimal level of
acceptable performance
TDMM.* Page 21-32

80
Q

Name the 5 key members
of a design team.

A

1 .Designated stakeholders
2.Owner/client
3.Architect
4.Engineer
5.Consultant
TDMM.* Page 21-34

81
Q

Name the 3 key members
of a construction team.

A

1 .Construction manager (CM)
2.General contractor (GC)
3.Contractor and subcontractors
TDMM.* Page 21-34

82
Q

Name 5 elements of
the design phase.

A

1 .Programming
2.Schematic design (SD)
3.Design development (DD)
4.Construction document (CD)
5.Bidding and negotiating
TDMM.* Pages 21-35 to 27-36

83
Q

Name 5 types of
bid structures.

A

1.RFP and RFQ
2.Design-bid-build (DBB)
3.Design-build (DB)
4.Construction manager (CM) at risk
5.Integrated project delivery (IPD)
TDMM.* Pages 21-36 to 21-37

84
Q

What is dictated
in the RFP?

A

The scope of the project
TDMM.* Page 21-36

85
Q

How does an RFQ
differ from an RFP?

A

An RFQ usually provides more
detail related to selecting the
material, equipment, and
components than an RFP does.
TDMM.* Page 21-36

86
Q

Name 2 types of bids
that are awarded.

A

1 .Low bid
2.Negotiated bid
TDMM.* Page 21-38

87
Q

Who is the prime
contractor?

A

A contractor who submits a bid
to the owner and who is
awarded a contract for payment
from the owner
TDMM.* Page 21-38

88
Q

What is a punch list?

A

A document that summarizes corrections a contractor must make prior to accepting work as complete
TDMM.* Page 21-40

89
Q

What is the GC’s primary
role during construction?

A

To complete the work
TDMM.* Page 21-39

90
Q

Name 3 types of contracts.

A

1 .Stipulated sum
2.Cost plus fee
3.Unit price
TDMM.* Page 21-40

91
Q

When is a unit price
contract used?

A

When the actual SOW cannot be
determined at the time of the bid
TDMM: Page 21-40

92
Q

Which form tells the
contractor the date to
begin work?

A

Notice to proceed
TDMM.* Page 21-40

93
Q

What is the purpose of
meeting minutes?

A

To keep track of issues
raised in meetings and form the
agenda for subsequent
meetings
TDMM.* Page 21-40

94
Q

What is the purpose
of the RFI?

A

To obtain a formal response to
contract documents
TDMM.* Page 21-40

95
Q

What is the purpose
of a field order?

A

To facilitate minor changes to
the requirements that do not
require a change order
TDMM.* Page 21-40

96
Q

What form is used to solicit
a quotation from the
contractor for a proposed
change to the project
scope?

A

Proposal request
TDMM.* Page 21-40

97
Q

What is summarized
in a punch list?

A

Corrections that a contractor
must make prior to accepting
the work as complete
TDMM.* Page 21-40

98
Q

What is a submittal?

A

Any information that a
contractor must submit to the
design team for review
and approval
TDMM.* Page 21-41

99
Q

When do cutover and first-
use activities begin?

A

As soon as construction is
substantially completed
TDMM.* Page 21-42

100
Q

Name 3 elements included
in a telecommunications
design.

A

1 .Specifications
2.Drawings
3.Cost estimates
TDMM.* Page 21-43

101
Q

Name the 4 main types of
specifications that can
be used to define
requirements.

A

1 .Performance
2.Proprietary
3.Descriptive
4. Reference
TDMM.* Page 21-43

102
Q

What is the focus of a
performance specification?

A

Results
TDMM.* Page 21-43

103
Q

What type of specification
calls out brand names?

A

Proprietary
TDMM.* Page 21-43

104
Q

What is the focus of a
descriptive specification?

A

Exact properties and
installation methods
TDMM.* Page 21-43

105
Q

What type of specification
lists requirements based
on an established
standard?

A

Reference
TDMM.* Page 21-43

106
Q

What is the
MasterFormat@?

A

A list of numbers and titles
compiled to organize the
activities and requirements of a
construction project
TDMM: Page 21-44

107
Q

How are drawings
generally grouped?

A

By discipline
TDMM.* Page 21-46

108
Q

What is the purpose of
the U.S. National CAD
Standard?

A

To allow consistent and
streamlined communication
among owners and
design/construction teams
TDMM.* Page 21-48

109
Q

How are
telecommunications
elements organized in the
BIM process?

A

As families, which consist
of objects
TDMM.* Page 21-51

110
Q

Why does the use of BIM
reduce the number of
change orders issued
for a project?

A

Because the BIM is able to alert
users to conflicts during the
design phase of the project
TDMM.* Page 21-52

111
Q

Name the 4 data fields
used to create a U.S.
National CAD standard
layer format.

A

1 .Discipline designator
2.Major group
3. Two minor groups
4.Status
TDMM.* Page 21-52

112
Q

Which data fields are
mandatory portions of
the U.S. National CAD
standard layer name
format?

A

*Discipline designator
Major group
TDMM.
Page 21-53

113
Q

Name the 6 types
of NCS symbols.

A

1 . Reference
2.Line
3.Identity
4.Template
5.Material
6.Text
TDMM: Page 21-54

114
Q

Name 6 existing conditions
that must be considered in
the cost of a project.

A

1 .Soil conditions
2.Asbestos
3.Displacement and relocation
4.Hazardous materials
5.Environmental impact stories
6.Abandoned cable
TDMM.* Page 21-55

115
Q

What information is
included in a disaster
recovery plan?

A

Processes and procedures for
recovering and protecting a
business or IT infrastructure
in case of disaster or
major incident
TDMM.* Page 21-63

116
Q

True or False
All employees should have
access to the company’s
disaster recovery plan.

A

False. While every employee
should be trained on the steps
and procedures contained in the
plan, access to the plan itself
should be limited to department
managers and those with a
“need to know.”
TDMM.* Page 21-64

117
Q

What risks are associated
with unauthorized persons
gaining access to the
disaster recovery plan?

A

Risks include unwanted
identification of weaknesses in
the organization’s ICT
infrastructure, sabotage,
unauthorized network access,
or other activities that put the
ICT infrastructure at risk.
TDMM.* Page 21-64

118
Q

What is the first step in
developing a disaster
recovery plan?

A

Identifying the potential risks
TDMM.* Page 21-65

119
Q

Where are identified risks
documented?

A

In a risk registry
TDMM.* Page 21-65

120
Q

How should risks in the risk
registry be categorized?

A

By their effect on critical
systems or services
TDMM.* Page 21-65

121
Q

True or False
Every item on the risk
registry, including non-
critical items, should have a
plan documented.

A

True. Each item (critical and
non-critical) should have a
documented plan, even if only to
accept the risk as-is with future
plans for mitigation.
TDMM.* Page 21-65

122
Q

When are disaster recovery
plans typically reviewed?

A

Annually, bi-annually, or
after an incident occurs
TDMM.* Page 21-66

123
Q

What is the goal of a
disaster recovery plan?

A

To recover as quickly as
possible in the event
of a disaster
TDMM.* Page 21-68

124
Q

What is a tabletop
exercise?

A

A practice incident that
is performed with prior
communication to the
response team(s)
TDMM: 21-69