The ____ ____ is the section of the transmission right-of-way directly under the wires and extending outward about 10 ft (3m) on each side. The ____ ____is the remainder of the active right-of-way.
wire zone, border zone
A ____ is a substance that has an oral LD50 lower than 50mg per kg of body weight or a dermal LD50 lower than 200mg per kg of body weight,
poison
The target of IVM is ____ _____, including noxious weeds and invasive species, that pose potentially unacceptable economic, social, and environmental risks.
incompatible plants
SMART objectives for integrated vegetation management ____, ____,____,____, and ____
Specific, Measurable, Achievable, Relevant, Timely
Level 1 risk assessments review large populations of trees from a specified perspective to identify those that have an ____ or ____ likelihood of failure.
imminent, probable
Vegetation, height, density or other conditions that trigger specific control methods are called ____ ____.
action thresholds
For clearing dense vegetation during initial establishment or reclaiming neglected or overgrown rights-of-way, ____ control methods are most efficient and cost effective.
mechanical
When properly selected and applied, herbicides can enhance ____ ____ ____ diversity and minimize ____ disturbance.
plant and wildlife, soil
____ toxicity results from a single exposure or exposure over a short period of time. ____ toxicity is the delayed damaging effect resulting from repeated exposure to low amounts of a substance, evolving over a long period.
Acute, chronic
Mixing of chemicals should be done with a buffer of at least ____ ft (____m) from a body of water or wetland.
100, 30
____ ____-____ is a technique in which non-translocatable herbicides are applied to control specific branches growing toward utility facilities.
chemical side-pruning
____ ____ is the management of vegetation by establishing and conserving compatible, stable plant communities using natural competition, animals, insects or pathogens.
biological control
The section of a utility transmission right-of-way under the wires and extending out both sides to a specified distance is called the ____ ____.
wire zone
Which of the following steps in the integrated vegetation management program should be completed first?
A) defining action thresholds
B) evaluating the site
C) selecting control methods
D) setting objectives
D) setting objectives
LIDARr technology is precise, and is effective for
A) documenting the distance between trees and conductors
B) calculating fluctuations in the distance between vegetation and conductors under various environmental conditions
C) identifying trees within striking or arcing distance of lines in the event of tree failure
D) all of the above
D) all of the above