Ch 7. Review Flashcards

1
Q

You are asked to prepare an estimate for a project that involves planting new trees in the parking lot. The trees cost $800 each, and the labor to install them is $75 per hour. You are planting 10 new trees, and each tree takes one hour of labor to plant, stake, and water. What is the estimated cost of the labor for this project, and which technique are you using to determine this estimate? Choose two.

A. $8,000

B. Three-point estimate

C. Bottom-up method

D. $750

E. Analogous method

F. Parametric method

G. $8,750

A

D. $750

F. Parametric method

The labor is $75/hour times 10 trees is $750. This is the parametric method of estimating because you are multiplying the quantity times the rate. Analogous estimating involves using estimates from similar projects, and three-point estimates use the average of three estimates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Top-down estimating is another name for which type of estimating technique?

A. Parametric estimating

B. Analogous estimating

C. Three-point estimating

D. Expert judgment

A

B. Analogous estimating

Top-down estimating is another name for analogous estimating.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The total time it will take for one person to complete a task from beginning to end without taking into account holidays, time off, or other project work is known as this.

A. Duration estimate

B. Work effort estimate

C. Bottom-up estimate

D. Parametric estimate

A

B. Work effort estimate

A work effort estimate or person-hour estimate is used to develop the cost estimates. This is the amount of time it will take to complete the task from beginning to end without accounting for work breaks, holidays, and so on. Duration estimates account for holidays, work breaks, and so on. Bottom-up estimates are estimates for individual components of work that are rolled up into the overall estimate, and parametric estimates are usually derived by multiplying quantity by rate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A discretionary fund used by the project manager to cover the cost of possible adverse events during the project is known as which of the following?

A. Management reserve

B. Chart of accounts

C. Contingency fund

D. Cost baseline

A

C. Contingency fund

A contingency fund is an amount allocated to cover the cost of possible adverse events, and the project manager generally has the ability to use this fund. The project manager does not usually have the authority to spend money from the management reserve. The chart of accounts is a description of the accounts listed in the accounting ledger, and the cost baseline is the total expected cost for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

You are in the process of determining the cost baseline. All of the following are used in the cost baseline except for which one?

A. Management reserves

B. Chart of accounts

C. Human resource cost estimates

D. Materials and equipment estimates

A

A. Management reserves

Management reserves are not part of the project cost budget or cost baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

You are developing a bottom-up estimate for the first phase of your project. Which of the following is the most important input to complete this task?

A. Historic data from a similar project

B. Chart of accounts

C. The WBS

D. The scope statement

A

C. The WBS

Bottom-up estimates start at the work package level of the WBS. Each work package on the WBS for the first phase of the project is summed to come up with an overall estimate for this phase. Historical data would be useful if you were using the analogous estimating technique. The chart of accounts doesn’t help at all with this exercise, and the scope statement will give you an understanding of what’s detailed on the WBS, but it won’t help with estimating.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is considered the most accurate estimate?

A. Analogous estimate

B. Bottom-up estimate

C. Estimates based on expert judgment

D. Parametric estimate

A

B. Bottom-up estimate

Bottom-up estimates are the most accurate estimates, and analogous estimates are the least accurate. Estimates based on expert judgment are analogous estimates. Parametric estimates are only as accurate as the data you’re using for the parametric model.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

You are asked to present and explain your project cost baseline. All of the following are true except which one?

A. The baseline will be used to track actual spending against the cost estimates.

B. The baseline can be used to predict future project costs.

C. The baseline is calculated and approved by the project manager.

D. The baseline is the total expected cost for the project.

A

C. The baseline is calculated and approved by the project manager.

The cost baseline is approved by the project sponsor, not the project manager.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Your project task is complex and you decide to use a three-point estimating technique. Which of the following options determine the three-point estimate? Choose three.

A. Quantity estimate

B. Work package level estimate

C. Materials estimate

D. Pessimistic estimate

E. Resource estimate

F. Rate estimate

G. Optimistic estimate

H. Most likely estimate

A

D. Pessimistic estimate

G. Optimistic estimate

H. Most likely estimate

Three-point estimates are the average of the most likely, optimistic, and pessimistic estimates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How is burn rate typically calculated?

A. CV

B. Determining spending rates over time

C. CPI

D. AC—PV

A

C. CPI

The burn rate is typically calculated using the cost performance index (CPI). This tells you the efficiency or benefits of the money spent at any point in the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The work effort multiplied by which of the following will bring about the total estimate for each task?

A. Duration

B. Rate

C. Number of resources

D. Number of hours

A

B. Rate

The rate that is established for a given resource times the work effort (usually expressed in hours) will yield the total estimate for the task.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Your project has a potential for a future risk event. The sponsor has told you that the organization cannot sustain the consequences of this risk. You recommend purchasing insurance so that if the risk event occurs, the organization can recoup their expenditures for the impacts of the risk. What risk strategy is this known as?

A. Avoid

B. Mitigate

C. Accept

D. Transfer

A

D. Transfer

Transfer is a risk strategy that transfers the consequences of the risk to another party.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

This technique can be used to help identify risks.

A. SWOT

B. CPI

C. EVM

D. CV

A

A. SWOT

SWOT stands for strengths, weaknesses, opportunities, and threats. Examining the project from each of these perspectives helps you identify risks. The other options are cost performance measurements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The risk register typically contains several pieces of information. Which of the following would you expect to see on a risk register? Choose three.

A. Risk owner

B. Description of risk

C. Risk score

D. Cost estimate for response plan

E. Resource costs to track risks

F. Cost estimate of the consequences of the risk

A

A. Risk owner

B. Description of risk

C. Risk score

During the early stages of risk planning, a risk register typically has a risk identification number, a description of the risk, the probability and impact of the risk event, risk score, and risk owner. Your risk register could also contain the risk trigger and other pertinent information about the risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

You have identified a risk on your project, and the team decides they won’t create a response plan; if the risk happens, they’ll deal with consequences when they occur. This is an example of which risk strategy?

A. Exploit

B. Avoid

C. Mitigate

D. Accept

A

D. Accept

The risk strategy of accepting a risk involves dealing with the consequences when they occur. You don’t prepare a risk response plan for risks you plan to accept.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The difference between planned expenditures and actual expenditures is known as which of the following?

A. Planned value

B. Variance

C. Expenditure reporting

D. Burn rate

A

B. Variance

The difference between what you planned to spend and what was actually spent is known as a budget variance.

17
Q

The clouds are rolling in over the horizon and the wind is picking up. Your outdoor event is about to get rained out. What is this an example of?

A. Risk trigger

B. Risk analysis

C. Risk probability

D. Risk response

A

A. Risk trigger

Risk triggers are symptoms or signs that a risk event is about to occur.

18
Q

All of the following are strategies for dealing with negative risks, except for which one?

A. Accept

B. Transfer

C. Share

D. Mitigate

A

C. Share

Sharing is a positive risk strategy. The negative risk strategies are avoid, transfer, mitigate, and accept.

19
Q

Project costs when displayed graphically over time represent which of the following?

A. S curve

B. C curve

C. Evenly distributed expenditures

D. Erratic expenditures

A

A. S curve

When project costs are displayed graphically over time, they represent an S curve. This is because spending starts out slowly on the project, picks up speed during the middle of the project, and tapers off at the end.

20
Q

You are determining the risk score for each of the risks in your risk register. You need which of the following to determine this score? Choose two.

A. Response plans

B. Risk owners

C. Probability the risk will occur

D. Contingency reserves

E. Risk trigger scores

F. Impact if the risk occurs

A

C. Probability the risk will occur

F. Impact if the risk occurs

The risk score is calculated by multiplying the probability by the impact. Probability is the likelihood a risk event will occur. It is expressed as a number from 0.0 to 1.0. Impact is the consequence of the risk event if it occurs and can also be expressed as a number from 0.0 to 1.0.