Ch 16 - Project Management Flashcards

1
Q

project

A

endeavor with a specific objective, multiple activities and defined precedence relationships, to be completed in a specified time period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

program evaluation and review technique (PERT)

A

network planning technique used to determine a project’s planned completion date and identify the project’s critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

critical path method (CPM)

A

network planning technique, with deterministic times, used to determine a project’s planned completion date and identify the project’s critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

project activities

A

specific tasks that must be completed and that require resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

precedence relationships

A

establishes the sequencing of activities to ensure that all necessary activities are completed before a subsequent activity is begun

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

activity-on-node

A

network diagramming notation that places activities in the nodes and arrows to signify precedence relationships

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

critical path

A

the longest sequential path through the network diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

probabilistic time estimate

A

process that uses optimistic, most likely, and pessimistic time estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

deterministic time estimates

A

assumption that the activity duration is known with certainty

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

optimistic time estimate

A

the shortest time period in which the activity can be completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

most likely time estimate

A

the normal time that the activity is expected to take

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

pessimistic time estimate

A

the longest time period in which the activity will be completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

beta probability distribution

A

typically represents project activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

crashing

A

reducing the completion time of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

critical chain approach

A

focus on the find due date that is based on the theory of constraints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

project buffer

A

safety time placed at the end of the critical path