AUC 358/CONSTRUCTION IN FD FACILITIES Flashcards
Scope of project is developed by ASSISTANT COMMISIIONER OF FACILITIES
COMPANY COMMANDER will be consulted , but facility staff has final determination
ALL REQUESTS from unit for additional work MUST BE SUBMITTED IN WRITING THROUGH CHAIN OF COMMAND TO..
ASSISTANT COMMISSIONER OF FACILITIES
-FDNY PROJECT MANAGER assigned to each project, will be point of contact for OFFICERS of affected units
do NOT contact engineers, contractors, or architects directly , ONLY PROJECT MANAGER
MEMBERS should not direct contractor to stop working..only exception:
imminent health or safety hazard/IMMEDIATE NOTIFICATION TO ASSISTANT COMMISSIONER OF FACILITIES
-do not enter construction zones, unless requested to do so by project engineers, contractors , architects