All reconstruction work must be authorized by the ……………experienced in
storage tank design, prior to commencement of the work by a reconstruction organization (see 3.23)
authorized inspector or an engineer
……………. in storage tank design shall approve all reconstruction work at the designated hold points and after reconstruction has been completed in accordance with the requirements
of this standard
The authorized inspector or an engineer experienced
The tank shall be ………….d prior to commencement of dismantling
cleaned and gas-free
Bottom plates that will be reused shall be cut by ……………. except where cuts cross existing weld seams
deseaming of lapwelds; or by cutting alongside of the
remaining welds at a minimum of 2 in. away from existing welds,
Any shell ring may be dismantled by cutting out……………….For the purpose of this method, the minimum HAZ to be removed will be …………, on both sides of the weld seam.
- existing weld seams and the heat affected zone (HAZ) of the weld
- 1/2 of the weld metal width or 1/4 in., whichever is less
Any shell ring ………… may be dismantled by cutting through the weld without removing the HAZ
1/2-in. thick or thinner
Shell rings may be dismantled by cutting vertical and/or horizontal cuts through the shell a minimum of …………. away from existing welds, except where cuts cross existing welds.
6 in.
Roof plates shall be cut by ………., or by cutting alongside of the ……………at aminimum of ……
deseaming of lap welds
remaining welds
2 in.
Shell, bottom, and roof plates shall be ………….. prior to dismantling for ready identification and placement
when the tank is reconstructed
marked
Marking material shall be of a ………….type
durable
A minimum of …… sets of matching center punch marks shall be located on the top and bottom edges of
each shell plate to facilitate proper alignment during reconstruction
two
New vertical joints in adjacent shell courses, made in accordance with 10.3.3.1, shall not be ………… but shall be offset from each other a minimum distance of …., where t is the plate thickness of the thicker course at the point of the offset
aligned
5t
No welding of any kind shall be performed when the temperature of the base metal is less than ……
0 °F
When the temperature of the base metal is between ……… or the thickness is in excess ….., the base metal within ….. of the place where welding is to be started shall be heated to a temperature ….. before welding.
0 °F and 32 °F of 1 in 3 in. warm to the hand (approximately 140 °F)
The edges of all welds shall ……..with the surface of the plate without a sharp angle
merge
Tack welds used in the assembly of vertical joints of tank shells shall be ………. and shall not …….. in
the finished joint when the joints are welded …,,….
removed
remain
manually.