Any work on a tank that changes its physical dimensions or configuration
alteration
standard that was in effect at the date of the installation of the component
as-built standard
If the date of the installation of the component is unknown, then the .
current applicable standard shall be considered to be the as-built standard
The standard used for repairs or alterations made after original construction is the as-built standard only for those repairs or alterations, …………….
so there may be more than one as-built standard for a tank
Authorized Inspection Agency
- Inspection organization of the jurisdiction
- Insurance company which is licensed or registered
- Owner/operator of one or more above ground storage
tank(s) and not for sale or resale. - Organization or individual under contract / direction of
an owner/operator and
recognized by the jurisdiction.
The area on a tank bottom where settlement begins.
Breakover point
The tank(s) for which corrosion rates are not known
Candidate Tank
A change operating conditions involving different properties of the stored product (specific
gravity/corrosivity/temperature/pressure)
change in service
The tank(s) for which corrosion rates and service history are known and documented
control tank
corrosion rate
The total metal loss divided by the period of time over which the metal loss occurred
critical zone
The portion of the tank bottom or annular plate within 3 in. of the inside edge of the shell, measured radially inward
current applicable standard
The current edition of the standard that applies if the tank were built today.
A plate (or plates) cut from an existing tank shell to create a temporary access opening. After planned work is completed, the door sheet(s) shall be reinstalled or replaced
door sheet
hot tap
Identifies a procedure for installing a nozzle in the shell of a tank that is in service.
The side of the tank that is in contact with the stored liquid product