7 - Cost Management Flashcards

1
Q

Actual cost

A

Amount monies spent on the project to date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Analogous estimating

A

Based on historical.

aka top down

Least reliable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Bottom-up estimating

A

Starts from zero; accounts for each component of hte WBS, arrives at a sum.,

Uses project team and is most accurate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Budget estimate

A

Broad estimate, used early in planning processes (and also top-down estimating).

Range: -10% to +25%.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Commercial database

A

Uses database to create cost estimate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Contingency reserve

A

Contingency allowance to account for overruns in cost.

For known risk events.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Cost aggregation

A

Costs for WBS work package aggregated to control account. Control accounts aggregated to top (project cost)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost baseline

A

Time-lapse exposure of when project monies are to be spent in relation to cumulative values of the work completed in the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Cost budgeting

A

The cost aggregation of each activity/work packages i nWBS. Applies costs over time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Cost change control system

A

Examines changes associated with scope changes, cost of materials, and cost of other resources and the impacted change on pverall project cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Cost management plan

A

Subsidiary PM plan - dictates how cost variances will be managed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Cost of poor quality

A

Money spent to recover from not adhering to the expected level of quality.

e.g. defect work.

aka cost of nonconfoirmance to quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Cost of quality

A

Money spent to attain expected level of quality within project.

e.g. safety precautions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Cost performance index (CPI)

A

Part of earned value management suite

Shows overall cost efficiency on the project.

CPI = EV/AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Cost Variance (CV)

A

Earned value management

Difference between earned value and actual cost

CV = EV-AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Definitive Estimate

A

Most accurate type of estimate.

Used in late planning and associated with bottom up.

Need a WBS.

-5% to +10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Direct costs

A

Costs applied directly to the project and not shared.

18
Q

Earned Value (EV)

A

Earned value management

What the project is worth

EV = %complete x BAC

19
Q

Estimate at Completion (EAC)

A

EVM

Forecasted project costs based on current performance

Standard:
EAC = BAC/CPI

Others as well, but not as common.

20
Q

Estimate to completion (ETC)

A

EVM

Predict how much more the project will cost.

ETC = EAC-AC

21
Q

Fixed costs

A

Costs remain constant through life of project

22
Q

Funding limit reconciliation

A

Organizaitons approach to managing cash flow against project deliverables based on a schedule, milestone accomplished, or data constraints.

23
Q

Indirect costs

A

Costs representative of more that one project (e.g. PMIS software licence)

24
Q

Known unknown

A

Event that will likely happen within the project, but when/to what degree is unknown.

Usually risk-related (e..g a delay).

25
Q

Learning curve

A

cost per unit decreases as more units are completed. Workers learn how to be more efficient.

26
Q

Oligopoly

A

Market condition where market is so tight that the actions of one vendor affects the actions of all others. (e..g gas pricing)

27
Q

Opportunity cost

A

Total cost of an opportunity that is refused to realize an opposing opportunity.

28
Q

Parametric estimating

A

Using a paramater and extrapolated

29
Q

Planned Value (PV)

A

What the project should be worth.

PV = percent of BAC where project should be at.

30
Q

Project Variance

A

The final variance, discovered at the end.

VAR = BAC-AC

31
Q

Regression analysis

A

Statistical approach to prediicting what future values may be, based on historical values.

aka analytical technique where a series of input variables are examined in relation to their corresponding output results in order to develop a mathematical or statistical relationship.

Creates quantitative predictions based on variables within one value to predict variables in another.

32
Q

Reserve analysis

A

Cost reserves are for unknown unknowns.

The management reserve ids not part of the project cost baseline, but is included as part of the project budget.

33
Q

Rough order of magnitude (ROM)

A

Used during initiating processes and in top-down.

-25% to +75%

34
Q

Schedule performance index (SPI)

A

EVM

Shows overall schedule adherence

SPI = EV/PV

Greater than 1 = ahead of schedule. Less = behind.

35
Q

Schedule variance (SV)

A

EVM

Difference between earned value and planned value

SV = EV-PV

\+ = ahead of schedule
- = behind
36
Q

Single source

A

Though many vendors can provide what your project needs, you prefer to work with a single one.

37
Q

Sole source

A

One vendor can provide what your project needs to purchase.

38
Q

Sunk cost

A

Monies spent to date.

39
Q

To complete Performance Index (TCPI)

A

Used to predict likelihood of reaching goals (BAC or EAC) based on current performance.

Using BAC
TCPI = (BAC-EV)/(BAC-AC)

using EAC
TCPI = (BAC-EV)/(EAC-AC)

40
Q

Variable costs

A

Changes as prokject goes on

41
Q

Variance

A

Difference between expected and actual

42
Q

Variance at Completion (VAC)

A

EVM

Projection of being over or under budget based on current performance

VAC = BAC-EAC

\+ = under budget
- = over budget