12 - Project Procurement Management Flashcards

1
Q

Alternative Dispute Resolution

A

When there is an issue or claim that must be settled before the contract can be closed, the parties involved in the issue or claim will try to reach a settlement through mediation or arbitration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Bid

A

From seller to buyer.

Price is the determining factor in the decision-making process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Bidder conference

A

Meeting of all project’s potential vendors to clarify the contract statement of work (SOW) and the details of the contracted work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Claims

A

These are the disagreements between the buyer and the seller, usually centering on a change, who did the change, and even whether a change has occurred. Claims are also called disputes and appeals, and are monitored and controlled through the project in accordance with the contract terms.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Contract

A

A contract is a formal agreement between the buyer and the seller.

Contracts can be oral or written - through written is preferred.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Contract change control system

A

Defines the procedures for how the contract may be changed. The process for changing the contract includes the forms; documented communicaitons; tracking; conditions within the project, business, or marketplace that justify the needed change; dispute resolution procedures; and the procedures for getting the changes approved wihtin the performing organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Contract statement of work (SOW, or CSOW)

A

This document requires the seller fully describe the work to be completed and/or the product to be supplied. The SOW becomes part of the contract between the buyer and the seller.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost plus award fee contract

A

A contract that pays the vendor all costs for the project, but also includes a buyer-determined award fee for the project work.

Buyer assumes risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Cost plus fixed fee contract

A

Contract that requires buyer to pay for the cost of the goods and services procured, plus a fixed fee for the contracted work.

Buyer assumes the risk of a cost overrun.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Cost plus incentive fee

A

Buyer pays a cost for the procured work, plus an incentive fee or bonus if the T/Cs are met.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Cost plus percentage of costs

A

Buyer pays for the cost of the good/services procured, plus a percentage of the costs.

Buyer assumes all risks of cost overruns.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Direct costs

A

Cost incurred by the project in order for the project to exist.

e.g. equipment needed to complete work, salaries of the team, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Fixed price contract

A

AKA firm fixed-price and lump-sum contracts.

Agreements that define the total price for the product the seller is to provide.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Fixed-price plus economic price adjustments

A

Fixed price with special allowance for price increases based on economic reasons such as infaltion or raw material prices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Force majeure

A

act of god

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

independent estimates

A

aka “should cost”

Bringing in an outside organization to predict what the cost should be. Sets a baseline.

17
Q

Indirect costs

A

These are costs attributed to the cost of doing business

e.g. utilities, office space, and other overhead.

18
Q

Invitation for Bid (IFB)

A

From buyer to seller. Requests the seller privide a price for the procured product or service

19
Q

Letter contract

A

Letter contract allows the vendor to begin working on the project immeidately. Often used as a stopgap solution.

20
Q

Letter of intent

A

Not a contract, but a letter stating that the buyer is intending to create a contractual relationship with teh seller.

21
Q

Make or buy decision

A

Process in which the project team determines the cost-effectiveness, benefits, and feasibiliy of making a product or buying it from a vendor

22
Q

Privity

A

The contractual relationship between the buyer and the seller is often considered confidential and secret

23
Q

Procurement management plan

A

PM subsidiary plan that documents the decisoins made in the procurement planning processes

24
Q

Procurement planning

A

Process to identify which parts of the project warrant procurement from a vendor by the buyer

25
Q

Proposal

A

Document the seller provides t othe buyer.

More than just a fee - includes ideas on how work can be completed

26
Q

Purchase order (PO)

A

PO is a form of unilateral contract that the buyer provides to the vendor showing the purchase has been approved by the buyers organization

27
Q

Quotation

A

From seller to buyer. Price is the determining factor in the decisoin-making process

28
Q

Request for Proposal (RFP)

A

From buyer to seller - requests the seller to provide a proposal to cmplete the procured work or provude the procured product

29
Q

Request for Quote (RFQ)

A

From buyer to seller - request the seller to provide a price on the product or service

30
Q

Risk-related contractual agreements

A

When a PM team decides to use transference to respond to a risk, a risk-related contractual agreement is created between the buyer and the seller.

31
Q

Screening system

A

A tool that filters or screens out vendors that don’t qualify for the contract

32
Q

Seller rating system

A

Used by organizations to rate prior experience with each vendor that they have worked with in the past.

Performance, quality, delivery time, etc.

33
Q

Terms of Reference

A

Defines the obligations for the seller, what the seller will provide, and all of the particulars of the contracted work. TOR is similar to statement of work

34
Q

Time and Materials Contract

A

Buyer pays for time and materials. Used on smaller job.

Requires a not-to-exceed clause

35
Q

Weighting system

A

Takes out the personal preferences of the decisoin maker in the organizaiton to ensure the best seller is awarded the contract.

Weights are assigned to the values of the proposals, and each proposal is scored.