7. Cost Flashcards
What is life cycle costing?
Life Cycle Costing (LCC) is an important economic analysis used in the selection of alternatives that impact both pending and future costs. It compares initial investment options and identifies the least cost alternatives for a twenty-year period
What is value engineering / analysis?
Finding a less costly way of doing essentially the same work.
Value engineering is a systematic method to improve the “value” of goods or products and services by using an examination of function. Value, as defined, is the ratio of function to cost. Value can therefore be manipulated by either improving the function or reducing the cost.
What are the calculations used to make funding decisions for an organisation?
• PV, NPV • ROI • IRR • Payback period • Cost-Benefit analysis • EVA: Economic Value Added • Discounted Cash Flow (Definitions are in the Integration section)
What are the types of costs?
- Variable costs: change with the amount of production or amount of work (material, supplies, wages)
- Fixed costs: do not change as production changes (cost of setup, rent, utilities…)
- Direct: expenses billed directly to the project
- Indirect: costs that are shared and allocated among several or all projects.
- Sunk: invested cost unrecoverable
- Opportunity; cost of the loss of potential benefit from the alternatives when a choice is made that excludes those alternatives.
What is Planned Value (PV)?
Or Budgeted Cost of Work Scheduled.
As of today, what is the estimated value of the work planned to be done?
PV = Planned % complete x BAC
What is Earned Value (EV)?
Or Budgeted Cost of Work Performed.
As of today, what is the estimated value of the work actually accomplished?
EV = Actual % complete x BAC
What is Actual Cost (AC) or total cost?
Or Actual Cost of Work Performed.
As of today, what is the actual cost incurred for the work accomplished? Sum of the costs for the given period of time.
What is Budget At Completion (BAC), the cost baseline?
How much did we budget for the total project effort?
What is Estimate At Completion (EAC)?
As of now, what do we currently expect the total project to cost (a forecast)?
EAC = BAC / CPIc
What is Estimate To Complete (ETC)?
From this point on, how much more do we expect it to cost to finish the project (a forecast)?
ETC = EAC - AC
What is Variance At Completion (VAC)?
As of today, how much over or under budget do we expect to be at the end of the project?
VAC = BAC - EAC
What is Cost Variance (CV)?
CV = EV - AC
How much actual cost differ from planned costs.
Negative is over budget, positive is under budget.
What is Schedule Variance (SV)?
SV = EV - PV
Difference between where we planned to be in the schedule and where we are in the schedule.
Negative is behind schedule, positive is ahead of schedule.
What is Cost Performance Index (CPI)?
CPI = EV / AC
How much we are getting for every $ we spend.
Greater than one is good, less than one is bad.
What is Schedule Performance Index (SPI)?
SPI = EV / PV
How fast the project is progressing compared to the project plan.
Greater than one is good, less than one is bad.
We are progressing at x% of the rate originally planned.
EAC: This formula calculates actual costs to date plus a revised estimate for all the remaining work. It is used when the original estimate was fundamentally flawed.
EAC = AC + Bottom-up ETC