6. Schedule Flashcards
Activity decomposition
Similar to scope decomposition except that the final result here is an activity list instead of the WBS.
Activity duration estimates
Probable number of periods (weeks, hours, days, months…) this activity should take with the probable range of results.
• 1 week +/- 3 days = activity should take between 2 and 8 days assuming a 5 day work week.
• 1 Month + 20% probability it will be accomplished later = there is an 80% likelihood that the activity will be completed within the month and a 20% chance that it will exceed a month.
Activity list
A list of every activity that will be performed on the project
Activity on Arrow diagram
Network diagram where activities are represented by the arrows connecting the nodes. Nodes are typically represented by circles in this type of project network diagram.
Activity on Node diagram
Network diagram where activities are represented on rectangular nodes with arrows representing the dependencies.
Analogous estimating
A form of expert judgment often used early on when there is little information available. Use similar past project information. Performed from the top down.
Backward pass
The method for calculating late start and late finish dates for an activity.
Beta distribution
A method of estimating activity duration using the formula: (Pessimistic + 4 x Realistic + Optimistic)/6
Critical path
The paths through the network diagram that shows which activities, if delayed, will affect the project finish date. For schedule, the critical path represents the highest risk path in the project.
Dependencies
Activities that must be completed before other activities are either started or completed.
Dummy activity
An activity in a network diagram that does not have any time associated with it. It is only included to show a relationship and is usually represented as a dotted or dashed line. Dummy activities only exist in activity on arrow diagrams.
Delphi technique
A means of gathering expert judgment where the participants do not know who the others are and therefore are not able to influence each other’s opinion. The Delphi technique is designed to prevent groupthink and to find out a participant’s real opinion.
Forward pass
The method for calculating early start and early finish dates for an activity.
Heuristics
Rules for which no formula exists. Usually derived through trial and error. Generally accepted rule or best practice.
Mathematical analysis
A technique to show scheduling possibilities where early and late start and finish dates are calculated for every activity without looking at resource estimates.
Monte Carlo Analysis
A technique that uses computer software to simulate the outcome of a project, based on the three-point estimates (Optimistic, Pessimistic, Most likely) for each activity and the network diagram.
Computer simulation that throws a high number of “what-if” scenarios at the project schedule to determine probable results.
Monte Carlo analysis is also used as a risk management tool to quantitatively analyse risks.
What is the process of schedule management?
- Plan Schedule Management
- Define Activities
- Sequence Activities
- Estimate Activities Duration
- Develop Schedule
- Control Schedule
What are the key outputs of the Define Activities process?
- Activity list
- Activity attributes
- Milestone list
- Change requests