201.30 Off-site Electrical Flashcards

1
Q
  • LOT 201.30 Off-site Electrical*
    • *

DESCRIBE the theoretical operation of transformers.

A

Expanding, collapsing, and reversing field caused by AC current flow through primary windings induces EMF in the secondary windings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  • LOT 201.30 Off-site Electrical*
    • *

Characteristics of Wye connected transformer.

A

Phase voltage is less than line voltage by a factor of √3 (1.73) and phase current equals line current.

E1 = √3 E ɸ

I1 = I ɸ

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  • LOT 201.30 Off-site Electrical*
    • *

Characteristics of Delta connected transformers.

A

the line voltage equals the phase voltage and phase current is less than line current by a factor of √3 (1.73).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  • LOT 201.30 Off-site Electrical*
    • *

Where/why are potential transformers used?

A

on high voltage AC sources for indication and protection

(UV and OV relays)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  • LOT 201.30 Off-site Electrical*
    • *

Where/why are current transformers used?

A

measure current flow on high voltage circuits for indication and protection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  • LOT 201.30 Off-site Electrical*
    • *

Function of Off-site Electrical Distribution System

A

provides reliable distribution of power generated from both units and a reliable source for plant auxilary power systems

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  • LOT 201.30 Off-site Electrical*
    • *

Mitsubishi Pneumatic Controlled Breakers (PCB)

(Function/Voltage)

A

Allow control of power distribution and protect grid stability by isolating transmission line faults. “Breaker and a half” scheme allows isloation of any line maintaining distribution from others

345 KV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  • LOT 201.30 Off-site Electrical*
    • *

Disconnects

A

Manual isolation of components to ensure safety of workers. NOT designed to break load.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  • LOT 201.30 Off-site Electrical*
    • *

Main Transformer

A

Step up generator output to yard voltage when generator is online, or step down yard voltage to supply UAT when generator is off-line.

345/25 KV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  • LOT 201.30 Off-site Electrical*
    • *

Standby Transformer

A

Supply the standby buses

345/13.8 KV

2 secondary windings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  • LOT 201.30 Off-site Electrical*
    • *

Unit Auxiliary Transformer

(UAT)

A

Supply the Aux Buses and designated Standby Buses (F, H)through cross tie with respective Aux Bus

25/13.8 KV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  • LOT 201.30 Off-site Electrical*
    • *

Emergency Transformer

A

Provides backup power to one ESF bus in each unit at a time only, via emergency outdoor bus 1(2)K and MODs

138/13.8 KV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  • LOT 201.30 Off-site Electrical*
    • *

Draw and Label Off-Site Electrical Distribution System

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  • LOT 201.30 Off-site Electrical*
    • *

Who is responsible to coordinate switching orders involving offsite elctrical distribution?

A

Unit 1 Control Room

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  • LOT 201.30 Off-site Electrical*
    • *

Who can accept and execute switching orders?

A

Designated Qualified Personnel

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
  • LOT 201.30 Off-site Electrical*
    • *

Which lines cannot be used to satisfy Tech Spec requirements for Off-Site Power?

A

Hillje 44, 64

Blessing 44, 138 KV