18 - Works progress and quality management Flashcards

1
Q

Q. How do decide how often site visits are required during a construction project?

A

A. dictated by the works, contract programme, unforeseen works, inspection details in SoW e.g. laying roof on roof deck.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Q. In what circumstances might a project require more frequent site visits - give examples.

A

A. technical project, a project that uncovers various issues, a lack of confidence in the new contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Q. Give me some examples of the quality standards you include in your specifications.

A

A. BS 8300:12 Decoration
BS 8612 for Dry-fixed Ridge, Hip and Verge Systems
BS EN 845-1:2003 Specification for ancillary components for masonry. Ties, tension straps, hangers and brackets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Q. How does the contract administrator’s role differ from the role of a clerk of works?

A

A. the CA is not site based, whereas the CoW is. CA will make frequent site visits. For large complex projects a CoW may be required to make daily visits and report to CA. for projects I have been involved in I carry out regular site visits to inspect progress and quality.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a clerk of works ?

A

A clerk of works inspects the workmanship, quality and safety of work on construction sites and reports back to senior managers and clients. As a clerk of work, you’d be conducting regular site inspections and checking that building plans are being followed correctly. You’d check that work is being carried out to the correct specifications and legal, safety and environmental standards.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How do you monitor progress on site ?

A

Site inspection based on the programme, schedule of works, quality standards, specification etc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What would you do if a contractor suggest an alterative material ?

A

Consider its application, costs, suitability, guarantees attached and meeting the required standards.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

NCI House - How and why did you define poor workmanship ? Did you reference any documents ?

A

BRE ? BS etc ?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When inspecting works, what kind of things do you look out for? (site health and safety)

A

Quality, workmanship, health and safety of the operatives, progress sin relation to the program, suitable materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How do decide how often site visits are required during a construction project?

A

Dictated by the works, contract programme, unforeseen works, inspection details in schedule of work for inspect for laying roof of roof deck etc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

In what circumstances might a project require more frequent site visits - give examples.

A

A technical project, a project that uncovered various issues, a lack of confidence or new contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Give me some examples of the quality standards you include in your specifications.

A

BS 8300:12 Decoration
BS 8612 for Dry-fixed Ridge, Hip and Verge Systems
BS EN 845-1:2003 Specification for ancillary components for masonry. Ties, tension straps, hangers and brackets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How does the contract administrator’s role differ from the role of a clerk of works?

A

The contract administrator is not a clerk of works; it is not a site based position although frequent site visits are required. For large projects it may be appropriate to appoint a clerk of works to make daily visits and to report to the contract administrator. For most projects this level of oversight is not required but weekly visits and stage inspections with regular meetings are required.

The contract administrator fills many roles. Initially this will include setting up the formal contract, issuing documents to the contractor, checking insurances and that the approvals are in place. It will also involve oversight of the contractors programme; this may include ensuring that specific target dates stated in the tender invitation have been factored in. As the work on site progresses the programme will be used to monitor the contractors performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Q. Explain how you carried out your site inspections to assess the progress and quality of the work undertaken.

A

A. a physical inspection of the site, taking into account H&S, contract programme, quality specified, discussion with site manager.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Q. Explain how you recorded the progress made to date?

A

A. site inspections followed by flash reports with photographs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Q. Explain how you determined if the work was progressing to time. (i.e. how is progress on site measured?).

A

A. checking against the contract programme.

17
Q

Q. Explain how you determined which stages of the project were “critical” and how you timed your site visits to ensure you witnessed the necessary works.

A

A. they were defined in the SoW to allow for this.

18
Q

Q. Explain how you used the specification and preamble to ensure the work was carried out to the appropriate standards

A

A. Within the specification I detailed a number of British standards that ere required.

19
Q

A preamble is an explanation of a document, commonly found in contracts, specifications and bills of quantities. It can help with the interpretation of the document.

A

A preamble might include:

A description of the parties to the contract.
A description of the competence (or lack of it) of the parties to the contract. This can be taken to set a general standard for the quality of goods or services expected, or the level of support required.
The background to the document.
A summary of the negotiations.
Tendering procedures.
The objectives of the project.
Other related documents or previous contracts and their relationship to the current document.

20
Q

Q. How do you manage cost and cost variance on a project?

A

A. by using a variations tracker on spreadsheet. Showing additions and omissions on a project.

21
Q

Q. How did you ensure the materials you specified had been used on site?

A

A. regular site visits and evidence, photos taken.

22
Q

Q. How did you check and record this and what physical checks do you make?

A

A. check on quality, material, placement, sizing etc.

23
Q

Q. Give me some examples of the evidence you include in your reports to verify this.

A

A. photographs along with site inspection notes.

24
Q

Q. What would you have done if you found the project falling significantly behind programme?

A

A. I would raise it with the contractor, sit down and review the programme, discuss re-sequencing activities to bring back in line. Consider acceleration.

25
Q

Q. When you identified the sub-standard workmanship to what quality standards did you refer to identify the work was not to the required standard?

A

A. I referred to the British Standards for the acceptable quality required as previously defined.

26
Q

Q. what is included in a flash report?

A

A. brief statements providing an update on the scheme. Whether there are any H&S issues raised. Photographs. The information needs to be simple to read and provide a valuable update.

27
Q

Q. what is RAG?

A

A. it stands for red, amber and green and can be used to provide a very visual and immediate way of identifying problem areas.

28
Q

Explain how you carried out your site inspections to assess the progress and quality of the work undertaken.

A

A physical inspection of the entire site, taking in account h&S, contract programme, quality specified, discussion with site manager

29
Q

Explain how you recorded the progress made to date?

A

site inspection record and photographs

30
Q

Explain how you determined if the work was progressing to time. (i.e. how is progress on site measured?).

A

in reference to the contract programme

31
Q

Explain how you determined which stages of the project were “critical” and how you timed your site visits to ensure you witnessed the necessary works.

A

They were defined in the schedule of works to allow for this

32
Q

Explain how you used the specification and preamble to ensure the work was carried out to the appropriate standards

A

Within the specification I detailed a number of British standards that ere required.

A preamble is an explanation of a document, commonly found in contracts, specifications and bills of quantities. It can help with the interpretation of the document.

A preamble might include:

A description of the parties to the contract.
A description of the competence (or lack of it) of the parties to the contract. This can be taken to set a general standard for the quality of goods or services expected, or the level of support required.
The background to the document.
A summary of the negotiations.
Tendering procedures.
The objectives of the project.
Other related documents or previous contracts and their relationship to the current document.

33
Q

How do you manage cost and cost variance on a project?

A

A cost tracking spreadsheet to defined cost per items invcding add and omit variations to the eintial SOW

34
Q

How did you ensure the materials you specified had been used on site?

A

regular site inspection and evidence

35
Q

How did you check and record this and what physical checks do you make?

A

Quality, material, placement, sizing etc

36
Q

Give me some examples of the evidence you include in your reports to verify this.

A

Verified and recorded within the site inspection notes and photographs

37
Q

What would you have done if you found the project falling significantly behind programme?

A

Review with the contractor, considerer acceleration

38
Q

When you identified the sub-standard workmanship (NCI House) to what quality standards did you refer to identify the work was not to the required standard?

A

I referred to British standards for the acceptable quality required as previously defined.