15 - Design and Spec Flashcards

1
Q

When do you enlist the services of sa third party ? How do you appoint them ?

A

direct appointment from the client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is NBS Chorus ?

A

NBS Chorus is a collaborative specification platform supporting global design and construction, aimed at those professionals who need to produce high quality specifications efficiently. … We see NBS Chorus as the future of specification and see true value for anyone who wants to come on this journey with us.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a specifications ?

A

Specifications describe the products, materials, and work required by a construction contract. They do not include cost, quantity, or drawn information, and so need to be read alongside other information such as quantities, schedules, and drawings. … For more information, see Performance specification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a schedule of works ?

A

A Schedule of Works is a contract document that lists the works required on a project. The Schedule references the requirements included in the specifications and contract drawings plus any additional ‘builders work’ or ‘fixing schedule’ type items, this is commonly referred to as a specified schedule of work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a bill of quantities ?

A

A bill of quantities is a document used in tendering in the construction industry in which materials, parts, and labour are itemized. It also details the terms and conditions of the construction or repair contract and itemizes all work to enable a contractor to price the work for which he or she is bidding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the type of specifications ?

A

Prescriptive
Descriptive
Performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are Preliminaries ?

A

‘Preliminaries’ in a construction contract, or ‘prelims’, is typically taken to mean the section in the bills of quantities which groups together items which are necessary for the contractor to complete the works, but will not actually become part of the works, such as scaffolding, plant, water, the cost of power to the site and other site overheads. The preliminaries section also often summarises the contractual terms and services to be provided by the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are Preambles ?

A

A preamble is an explanation of a document, commonly found in contracts, specifications and bills of quantities. It can help with the interpretation of the document.

A preamble might include:

A description of the parties to the contract.
A description of the competence (or lack of it) of the parties to the contract. This can be taken to set a general standard for the quality of goods or services expected, or the level of support required.
The background to the document.
A summary of the negotiations.
Tendering procedures.
The objectives of the project.
Other related documents or previous contracts and their relationship to the current document.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What conditions have you implemented from planning and building control ?#

A

Planning
The development to which this permission relates shall begin not later than the expiration of three years beginning with the date of this decision.
Reason: As required by Section 91 of the Town and Country Planning Act 1990, as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.

The development to which this permission relates shall be carried out in accordance with the approved plan(s) referenced: P2008017/02 received 21.01.21
Reason: For the avoidance of doubt and in the interests of proper planning, and in order to achieve a satisfactory form of development in accordance with the National Planning Policy Framework and DM20 of the Development and Allocations Plan and Policies CS1 of the Core Strategy and Urban Core Plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the difference between preamble and preliminaries

A

Preambles are the explanation of the works that doesn’t form part of the costings, preliminaries of the costed items required to complete the works, scaffolding, plants etc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a feasibility survey. ?

A

Feasibility studies are preliminary studies undertaken in the very early stage of a project. They tend to be carried out when a project is large or complex, or where there is some doubt or controversy regarding the proposed development. If an environmental impact assessment (EIA) is required, this may involve assessments best undertaken as part of feasibility studies.

The purpose of feasibility studies is to:

Establish whether the project is viable.
Help identify feasible options.
Assist in the development of other project documentation such as the business case, project execution plan and strategic brief.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

• Concrete rear extension onto a timber main floor. What design considerations did you make to sub floor ventilation?

A

Allow for supply and installation of uPVC pipe from ducted vents to new rear extension walls to the sub floor voids to existing house. Ensure any joints are taped. New external air brick to be clay terracotta NOT uPVC.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

• Talk me through the obligations contained within part L of the BR? What pros and cons were presented to your client?

A

– Approved document L1B – Conservation of fuel and power within existing dwellings. obligations include :
Upgrading the existing structure to ensure complaint to the u values set out within
Walls – 0.30 W/m2K
Floor – 0.25
Flat roof – 0.18

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

• With regards to Pethfoot House, can you explain your involvement in the design of the works and specifically what works formed part of the application Planning (listed building and conservation areas) act 1990?

A

my involvement in the design stage include organising and chairing meetings to fully understand the client objectives for the project at an early stage. This would fall with RIBA plan of work stage 0 – strategic definition.
Listed building consent is required to all works of demolition, alteration and extension of a listed building that agents its character. In this example as the listed related to the whole building our works including removal of the sun room in its entirety, remedial works to chimney and internal alterations required this application.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

• I can see you have referenced a couple of the approved documents, what are they?

A

They are document that provide guidance on how building regulation can be satisfied that fall under the Building Act 1984. (Just be aware of the differences between the Regs and Approved Documents )

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

• When do you need to comply with building regs?

A

For any new dwelling or new construction work to the affected areas. Not required to comply for the whole building retrospectively.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Are you aware of any British standard for disabled design ?

A

BS8300 is a British Standard that sets out how buildings should be designed,

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What u values did you achieve for the extension ?

A

Floor 0.25
Walls 0.28
Ceiling 0.18

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What does SAP stand for ?

A

The Standard Assessment Procedure (SAP) is a methodology introduced by the Government to assess and compare the energy and environmental performance of buildings to make sure that any new developments will not only meet Building Regulations, but also all energy and environmental policy initiatives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Pinehaugh: Who was liable for the structural designs?

A

The structural Engineer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Did you carry out the measured survey? If not how could rely on the measurements? (carry out site checks)

A

I carried out the measured survey

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What standards did you refer to for the disabled bathroom? Look up BS:8300

A

Approved Doc M - Access to and use of building

BS 8300 - Design of an accessible and inclusive built environment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What was the clear width door opening?

A

800mm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What information is included in the RICS Guidance Note on Design & Specification?

A
Principles behind the role
 Design process management
 Establishing the project
 Outline design and specification
 Preparing for detailed design
 Design production
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

How do you make your client aware of their duties under the CDM Regulations?

A

During the initial project meeting, my company adopted the durites of the client via a formal agreement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What are the different stages of the design process?

A
0 - Strategic definition.
 1 - Preparation and briefing.
 2 - Concept design.
 3 - Spatial coordination.
 4 - Technical design.
 5 - Manufacturing and construction.
 6 - Handover.
 7 - Use.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Outline the key stages of the RIBA plan of work.

A
0 - Strategic definition.
 1 - Preparation and briefing.
 2 - Concept design.
 3 - Spatial coordination.
 4 - Technical design.
 5 - Manufacturing and construction.
 6 - Handover.
 7 - Use.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

At what stage would a building regulation application be made?

A

4 - Technical Design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Following a client instruction, how might you ensure that their brief is met?

A

Reviewing the KPI and key requirements, feedback and communication throughout.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

What do you understand by the term, “modern methods of construction”?

A

Modern methods of construction is a process which focuses on off-site construction techniques, such as mass production and factory assembly, as alternatives to traditional building. Creating panelled units in factories, which can be quickly assembled onsite to create 3D structures.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Give me some examples of modern methods of construction which you have experience/knowledge of.

A

Timber frame

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

What is the purpose of the preambles in contract documentation?

A

A preamble is an explanation of a document, commonly found in contracts, specifications and bills of quantities. It can help with the interpretation of the document.

A preamble might include:
A description of the parties to the contract.
A description of the competence (or lack of it) of the parties to the contract. This can be taken to set a general standard for the quality of goods or services expected, or the level of support required.
The background to the document.
A summary of the negotiations.
Tendering procedures.
The objectives of the project.
Other related documents or previous contracts and their relationship to the current document.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

When are design risk assessments required?

A

Under CDM by the Principal Designer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Why is CDM important in the design process?

A

Allows for risk and hazards to be design out

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

What technical standards are you aware of and do you use when writing specifications?

A

BRE digest
BS - British Standards Manufacturer Documents
Approved Documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

How might an existing building be made more energy efficient?

A
Renewable Energy
New Glazing
Led Lighting
Increasing insulation
Draft Stripping
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Explain the different forms of specification available.

A

Performance – describes the operational requirements of the concept.
Prescriptive – describes the materials and workmanship required for a development

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Explain the key difference between prescriptive and performance specifications.

A

Performance – describes the operational requirements of the concept.
Prescriptive – describes the materials and workmanship required for a development

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

Why might you recommend the use of a performance specification?

A

Prescriptive specifications give the client more certainty about the end product when they make their final investment decision (i.e. when they appoint the contractor), whereas a performance specification gives the contractor and suppliers more scope to innovate and adopt cost effective methods of work, potentially .

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

How would the tender evaluation differ when using a performance specification to ensure you chose the best solution offered by the tenderers, rather than simply selecting the cheapest?

A

The request for further information regarding how the contractor proposes to complete this.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

What are the advantages and disadvantages of using specification writing software such as NBS?

A

Time-consuming

Costly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

How do you determine the length of contract period for a project - what factors are considered?

A

Size
Complexity
Client requirements
KPI’s

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

List the various constituent parts that make up a specification.

A

Specifications describe the products, materials, and work required by a construction contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

What current challenges is Covid and/or Brexit bringing to Design & Specification?

A

Labour, material, delivery, face to face meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

Q. what is the size of a disabled parking space?

A

A. standard parking space applies which is 2.4 x 4.8m plus 1.2m on either side for the doors to open and wheel chair operation. Plus dropped kerb providing access.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

Q. what considerations did you consider when designer the car park?

A

TBC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

Q. what was the tarmac build up?

A

TBC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

Q. what other approved documents did you consider when designing the car park?

A

TBC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

Q. what design consideration did you consider as part of the accessible WC?

A

A. from a building perspective to ensure level access was provided. Also looking at foul drainage to be connected into existing foul connections.

50
Q

Q. what other details were specified to ensure WC requirements?

A

A. Doc M pack? Anti slip vinyl floor covering – ensuring the spec and gauge were suitable to application, grab rails, HWB, WC, emergency pull cord.

51
Q

Q. what is the min. door width for accessible WC? Turning circle?

A

A. turning circle 1500mm.

52
Q

Q. What did you do to ensure the designers/engineers had the full information as part of the WC?

A

A. I held DTM’s with the relevant engineers to ensure they are fully briefed on the design requirements.

53
Q

Q. what is included in the tender documents?

A

A. tender documents may include: a letter of invitation, the form of tender, prelims including PCI, the form of contract and contract conditions and amendments, a tender pricing document (or contract sum analysis on D&B, design drawings, specifications.

54
Q

How did you decided how big the new extension needed to be?

A

Based on the clients requirements

55
Q

How did you design the layout of the new extension?

A

Inline with the clients requirements

56
Q

When positioning the new window openings how did you determine structural integrity would be maintained?

A

I reviewed Approved Document A in relation to masonry v glazing and fht applicable sizing

57
Q

Explain how the existing loads would be supported whilst the new structural openings were formed.

A

Via Acro needle / pin props

58
Q

Explain how you specified the stonework repairs/replacement

A

TBC

59
Q

Explain how you sized the replacement floor and ceiling joists.

A

I reviewed current Traata tables to conform the required timber size, depth grade and centres.

60
Q

What other details were specified to ensure the floor joist were installed properly?

A

The ends were wrapped in DPM, the tier was treated and acclimatised on site.

61
Q

What floor structure was specified and explain how you specified for it to be fixed?

A

Timber suspended floor

62
Q

What type of lintels were specified for the new structural openings?

A

Sought confirmation from the conservation officer than create lintel could be installed as they would be hidden from the face

63
Q

Explain how the new lintels were installed.

A

Via Acro needle / pin props

64
Q

Explain the specification of the new casement windows.

A

Double glazed casement open out windows to match ns scale, material and size of the original

65
Q

How were the new windows fixed into the structural openings?

A

Frame installed and fix the stonework via resin anchor bolts.

66
Q

Level 3

A

TBC

67
Q

Q. what were you design consideration on the flat roof?

A

TBC

68
Q

Q. what approved documents did you consider?

A

TBC

69
Q

Q. what were the U-values for an existing flat roof replacement you achieved?

A

TBC

70
Q

Q. explain a flat roof build-up?

A

TBC

71
Q

Q. what is the difference between warm and cold deck flat roof?

A

TBC

72
Q

Q. what is an inverted flat roof?

A

TBC

73
Q

Q. what alteration works were required to the adjacent windows?

A

TBC

74
Q

Q. what were the end user requirements for the windows?

A

TBC

75
Q

Q. draw design detail of the window?

A

TBC

76
Q

Q. you said, Part L was considered for thermal efficiency, what did you consider?

A

TBC

77
Q

Q. you said you discussed with the LPA and was considered under permitted development, what is permitted development?

A

A. certain types of works can be carried out without needing to apply for planning permission. These are called Permitted Development rights. I liaised with the LPA to discuss the proposals and I asked for a ‘lawful development certificate’ at a fee.

78
Q

Q. explain what advise you gave in respect of the roof replacement?

A

TBC

79
Q

Q. What factors did you consider when giving this advice?

A

TBC

80
Q

Q. how did you ensure the practicality of installing the new roof covering to the new roof?

A

A. with it being a live school, I ensured there was clear separate access for the pupils and staff, ensuring that the contractors are aware not to keep materials and plant unattended at any time. Ensuring that the contractors closed the gate to the site compound area. Ensure the site hoarding was maintained properly to stop access from the school grounds.

81
Q

Q. with the removal of the load bearing wall, what factors did you consider when offering this advice?

A

A. I advised the council that the installation of a steel beam will be required and input from a SE will be needed to calculate and specify the correct size of the beam. Also temporary support will be required for the roof structure.

82
Q

Q. what is the required bearing of the beam?

A

A. in accordance with the part A the minimum bearing is 150mm.

83
Q

Q. how did you ensure the practicality of installing the new beam?

A

TBC

84
Q

Q. what other approved documents did you consider for the beam?

A

A. Part b – fire protection. I advised the client that fire board will be required for the new beam to provide adequate fire protection.

85
Q

Q. was there any need for asbestos consideration?

A

TBC

86
Q

Q. explain the advice you offered in respect of asbestos?

A

TBC

87
Q

Explain what advice you gave in respect of the size of the Velux windows to be installed in the loft conversion.

A

Various sizes were available but consideration and advice wa sigvenr regarding rh spacing between and the support required for these openings.

88
Q

What factors did you consider when offering this advice?

A

Cost, time, quality

89
Q

How did you ensure the practicality of installing the new structural steelwork into the roof?

A

The roof was to be recovered, so the insertion of the steelwork was installed during the period of re roofing where the roof was covered with a tin hat’

90
Q

Explain the reasoned advice you gave in respect of the client’s expectations and their limited budget.

A

I create initial design and then in turn cost estimates for the work using past tender documentation and BCIS.

91
Q

Explain the advice you gave to try and ensure the floor layouts suited the client’s needs

A

I produced a number of proposed floor plans that were reviewed din person with the client, these were in reference to the client brief and in line with budget requirements.

92
Q

Explain the advice you offered in respect of asbestos

A

As the building was constructed in 1910 I advised the client of the requirements for asbestos refurbishment and demolition survey to comply with the Control of Asbestos Regulation 2012. To protect the works in due course.

93
Q

What features did you recommend to suit your client’s requirement’s?

A

The floor plan including the provision of the accommodation and disability bathroom and bedroom.

94
Q

Explain why it was important to get early inclusion from the specialist sub-contractor?

A

Are they can have a direct impact on cost, time, programme of the project.

95
Q

What design guides were used to ensure the spatial requirements suited your client’s needs?

A

BS 8300 Design of an accessible and inclusive building

Approved document M - access to and use of buildings

96
Q

What are the contents and general items contained within the RICS Design and spec guidance note

A
"Principles behind the role
 Design process management
 Establishing the project
 Outline design and specification
 Preparing for detailed design
 Design production"
97
Q

What is CDM 2015 ?

A

The Construction (Design and Management) Regulations 2015 (CDM 2015) cover the management of health, safety and welfare when carrying out construction projects. CDM 2015 replaced the Construction (Design and Management) Regulations 2007 (CDM 2007) from 6 April 2015

98
Q

Q. what is the NBS? (National Building Specification)

A

“It is a UK based system of construction specification used by architects and building professionals to describe the materials, standards and workmanship of a construction project.
NBS governs the regulations of a specification.”

99
Q

Q. explain what your understanding is about the RICS guidance note Design and Specification

A

TBC

100
Q

Q. What information is included in the RICS Guidance Note on Design & Specification?

A

TBC

101
Q

Q. How do you make your client aware of their duties under the CDM Regulations?

A

TBC

102
Q

Q. What are the different stages of the design process?

A

TBC

103
Q

Q. Outline the key stages of the RIBA plan of work.

A

TBC

104
Q

Q. At what stage would a building regulation application be made?

A

TBC

105
Q

Q. Following a client instruction, how might you ensure that their brief is met?

A

TBC

106
Q

Q. What do you understand by the term, “modern methods of construction”?

A

TBC

107
Q

Q. Give me some examples of modern methods of construction which you have experience/knowledge of.

A

TBC

108
Q

Q. What is the purpose of the preambles in contract documentation?

A

TBC

109
Q

Q. When are design risk assessments required?

A

TBC

110
Q

Q. Why is CDM important in the design process?

A

TBC

111
Q

Q. What technical standards are you aware of and do you use when writing specifications?

A

TBC

112
Q

Q. How might an existing building be made more energy efficient?

A

TBC

113
Q

Q. Explain the different forms of specification available.

A

TBC

114
Q

Q. Explain the key difference between prescriptive and performance specifications.

A

TBC

115
Q

Q. Why might you recommend the use of a performance specification?

A

TBC

116
Q

Q. How would the tender evaluation differ when using a performance specification to ensure you chose the best solution offered by the tenderers, rather than simply selecting the cheapest?

A

TBC

117
Q

Q. What are the advantages and disadvantages of using specification writing software such as NBS?

A

TBC

118
Q

Q. How do you determine the length of contract period for a project - what factors are considered?

A

TBC

119
Q

Q. List the various constituent parts that make up a specification.

A

TBC

120
Q

Q. What current challenges is Covid and/or Brexit bringing to Design & Specification?

A

TBC