14 - Contract Administration Flashcards
Why do you have predominate experience ewijt JCT MW ?
As I deal with similar sized projects, however I do have knowledge of the other forms of contract such as intermediate and standard building contract.
What other suites of contracts are available ?
NEC - NEC was first published in 1993 as the New Engineering Contract. It is a suite of construction contracts intended to promote partnering and collaboration between the contractor and client. It was developed as a reaction to other more traditional forms of construction contract which have been portrayed by some as adversarial.
FIDIC - International Federation of Consulting Engineers - FIDIC stands for ‘Fédération Internationale des Ingénieurs - Conseils’, which is best translated from French as The International Federation of Consulting Engineers.
What are the difference between jct and nec ?
JCT is adversial where as NEC is collaborative
NEC uses the contract programme as a contract document
Contract Administrator v Project manager
Relevant events / matter v compensation event (both time and money)
NEC does not allow for provisional sums
What is the role of a contract administer ?
A contract administrator manages contracts made between building contractors, employers, and clients. Their responsibility is to administer construction contracts, whereby they may act as project managers, engineers, consultants and client representative
You mention the RICS Guidance note son contract administration, can you expand on its contents please ?
Its now been withdrawn however it contains the Roles and responsibilities
appointment of the contract administrator
site inspections
meetings
You mention the RICS Guidance note on retention, can you expand on its contents please ?
Reasons for inclusions
General principals of release of retention
Alternatives - Bonds etc
Contract specific clauses
You mention the JCT practice note deciding on the appropriate jct contract, can you expand on its contents please ?
This is a document detailing the difference between the contracts. This document also includes a flow chart to help guide the decision.
What is a employers agent ?
The contract administer on a design and build contract
What does practical completion trigger ?
Practical Completion is a contractual term used in the Building Contract to signify the date on which a project is handed over to the client. The date triggers a number of contractual mechanisms including, releasing half of the retention, ending the contractor liability for liquidated damages, starting the rectification period.
What are the contents of the contract documents ?
Drawings, schedule of work, preliminaries, pre ambles, construction programme, the contracts, photo report, asbestos information etc
What is required for a contract under hand ?
Signed by director and a the company secretary, liability for 6 years.
What is required for a contract under deed ?
Signed by two directors and attached the common seal of company
At Kenton lodge can you discuss me through the payment timeline in relation to this amendment ?
The contractor agreed with my conclusion and amended the valuation and re issued the same day. My payment certificate was then compiled and issued in due course, in line wit the 5 days for intermin JCT MW payments from the due date.
What is the final account ? What are the timelines attached to this ?
The final account is the conclusion of the contract sum (including all necessary adjustments) and signifies the agreed amount that the employer will pay the contractor. It includes any works that are paid to the contractor through the main contract. The timeline is as follows :
Contractor submit valuation up to 28 days before the due date
CA assesses and issue Payment certificate within 5 days of due date
Employer can issue a pay less notice up to 5 days before final date for payment
Final date for payment is 14 days from due date
What is partial completion ? What contract did you run this under ?
The client may wish to take possession of part of a building or site, even if works are ongoing. This can be programmed within the original contract documents it the need can be foreseen through a requirement for sectional completion which is not allowed under JCT MW, but in the absence of such a provision many contracts offer the more open-ended option of partial possession.
The effect of partial possession is that:
Any part for which partial possession is given is deemed to have achieved practical completion.
Half of the retention for that part must be released.
The defects liability period begins for that part.
Liquidated damages reduce proportionally.
The client is responsible for that part and should insure it.
The contractor is not obliged to allow partial possession (although permission cannot be unreasonably withheld), and may not wish to if, for example, access routes are difficult to achieve, it would disrupt the works, or it would incur additional costs. There could also be additional difficulties if the occupants of the part that has been possessed disrupt the contractor, which could result in a claim for extension of time and/or loss and expense.
What stage of riba is the building regs ?
Stage 4 - Technical Design
What affect did COVID have on your jct contract ?
Potential delay - consideration of if relevant event or relevant matter
How would you review and extension of time ?
Assess the contractors claim - should be notified whenreasonbale apparent
Consider was this a relevant event
Assess the claim
Formally confirm the outcome
How would you formal define at extension of time ?
Via a formal letter to contractor and employer
What were your insurance revisions under the jct contract ? Joint names ?
JCT MW
- 4A (Work insurance by Contractor in joint names) - New dwelling
- 4B (Works and existing structures insurance by employer in joint names)
- 4 C (Works and existing structure insured by other means)
What would you look at when assessing contractors and sub consultants ?
Credit rating Reference Size Experience Availability Willingness H&S
Partial completion under jct mw ?
Not within the contract but an adhoc agreement can be made
What might you do as a contract administrator prior to the contract being signed ?
The role of contract administrator does not technically commence until a building contract is in place between the employer and the contractor; however, in practice the responsibilities of the CA will have commenced before the building contract exists. However, the contract administrator would normally draft the contract prior to a pre start meeting.
What are payment timescales under jct mw?
Interim
Interim Valuation date is 7 days before the due date. contractor can submit valuation application for payment prior to this.
CA has 5 days from due date to create payment certificate
Final date for payment is 14 days from due date
Employer has up to 5 days before due date to issue a pay less notice
Final
Contractor has 28 before due date to submit valuation
CA as 5 days from due date to create payment certificate
Final date for payment is 14 days from due date
Employer has up to 5 days before due date to issue a pay less notice