17-ITTO Memorization (Output) Flashcards

1
Q

“Work performance information” is NOT output of only 10 processes. What they are?

A

All M&C EXCEPT Integration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

“Work performance reports” is output of only 1 process. What is that?

A

Monitor & control project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

“Basis of estimates” is output of only 3 process. What are they?

A

All processes starting with “Estimate”:
1-Estimate activity durations
2-Estimate costs
3-Estimate activity resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

“Team performance assessments” is output of only 1 process. What is that?

A

Develop team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

“Accepted deliverables” is output of only 1 process. What is that?

A

Validate scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

“Activity attributes” is output of only 1 process. What is that?

A

Define activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

“Activity list” is output of only 1 process. What is that?

A

Define activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

“Agreements” is output of only 1 process. What is that?

A

Conduct procurements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

“Approved change requests” is output of only 1 process. What is that?

A

Perform integrated change control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

“Assumption log” is output of only 1 process. What is that?

A

Develop Project charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

“Bid documents” is output of only 1 process. What is that?

A

Plan procurement management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

“Closed procurements” is output of only 1 process. What is that?

A

Control procurements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

“Communications management plan” is output of only 1 process. What is that?

A

Plan communications management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

“Cost baseline” is output of only 1 process. What is that?

A

Determine budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

“Cost estimates” is output of only 1 process. What is that?

A

Cost estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

“Cost forecasts” is output of only 1 process. What is that?

A

Control costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

“Cost management plan” is output of only 1 process. What is that?

A

Plan cost management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

“Deliverables” is output of only 1 process. What is that?

A

Direct & manage project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

“Duration estimates” is output of only 1 process. What is that?

A

Estimate activity durations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

“Final product, service, or result transition” is output of only 1 process. What is that?

A

Close project or phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

“Final report” is output of only 1 process. What is that?

A

Close project or phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

“Independent cost estimates” is output of only 1 process. What is that?

A

Plan procurement management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

“Issue log” is output of only 1 process. What is that?

A

Direct & manage project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

“lessons learned register” is output of only 1 process. What is that?

A

Manage project knowledge

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

“Make-or-buy decisions” is output of only 1 process. What is that?

A

Plan procurement management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

“Milestone list” is output of only 1 process. What is that?

A

Define activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

“Physical resource assignments” is output of only 1 process. What is that?

A

Acquire resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

“Procurement documentation updates” is output of only 1 process. What is that?

A

Control procurements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

“Procurement management plan” is output of only 1 process. What is that?

A

Plan procurement management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

“Procurement statement of work” is output of only 1 process. What is that?

A

Plan procurement management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

“Procurement strategy” is output of only 1 process. What is that?

A

Plan procurement management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

“Project calenders” is output of only 1 process. What is that?

A

Develop schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

“Project charter” is output of only 1 process. What is that?

A

Develop Project charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

“Project communications” is output of only 1 process. What is that?

A

Manage communications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

“Project funding requirements” is output of only 1 process. What is that?

A

Determine budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

“Project management plan” is output of only 1 process. What is that?

A

Develop Project management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

“Project schedule” is output of only 1 process. What is that?

A

Develop schedule

38
Q

“Project schedule network diagrams” is output of only 1 process. What is that?

A

Sequence activities

39
Q

“Project scope statement” is output of only 1 process. What is that?

A

Define scope

40
Q

“Project team assignments” is output of only 1 process. What is that?

A

Acquire resources

41
Q

“Quality control measurements” is output of only 1 process. What is that?

A

Control quality

42
Q

“Quality management plan” is output of only 1 process. What is that?

A

Plan quality management

43
Q

“Quality metrics” is output of only 1 process. What is that?

A

Plan quality management

44
Q

“Quality reports” is output of only 1 process. What is that?

A

Manage quality

45
Q

“Requirements documentation” is output of only 1 process. What is that?

A

Collect requirements

46
Q

“Requirements management plan” is output of only 1 process. What is that?

A

Plan scope management

47
Q

“Requirements traceability matrix” is output of only 1 process. What is that?

A

Collect requirements

48
Q

“Resource breakdown structure” is output of only 1 process. What is that?

A

Estimate activity resources

49
Q

“Resource calenders” is output of only 1 process. What is that?

A

Acquire resources

50
Q

“Resource management plan” is output of only 1 process. What is that?

A

Plan resource management

51
Q

“Resource requirements” is output of only 1 process. What is that?

A

Estimate activity resources

52
Q

“Risk management plan” is output of only 1 process. What is that?

A

Plan risk management

53
Q

“Risk register” is output of only 1 process. What is that?

A

Identify risks

54
Q

“Risk report” is output of only 1 process. What is that?

A

Identify risks

55
Q

“Schedule baseline” is output of only 1 process. What is that?

A

Develop schedule

56
Q

“Schedule data” is output of only 1 process. What is that?

A

Develop schedule

57
Q

“Schedule forecasts” is output of only 1 process. What is that?

A

Control schedule

58
Q

“Schedule management plan” is output of only 1 process. What is that?

A

Plan schedule management

59
Q

“Scope baseline” is output of only 1 process. What is that?

A

Create WBS

60
Q

“Scope management plan” is output of only 1 process. What is that?

A

Plan scope management

61
Q

“Selected sellers” is output of only 1 process. What is that?

A

Conduct procurements

62
Q

“Source selection criteria” is output of only 1 process. What is that?

A

Plan procurement management

63
Q

“Stakeholder engagement plan” is output of only 1 process. What is that?

A

Plan stakeholder engagement

64
Q

“Stakeholder register” is output of only 1 process. What is that?

A

Identify stakeholders

65
Q

“Team charter” is output of only 1 process. What is that?

A

Plan resource management

66
Q

“Test and evaluation documents” is output of only 1 process. What is that?

A

Manage quality

67
Q

“Verified deliverables” is output of only 1 process. What is that?

A

Control quality

68
Q

“Work performance data” is output of only 1 process. What is that?

A

Direct & manage project work

69
Q

“Change requests” is output of only 1 process in INITIATING (besides other process groups). What is that?

A

Identify stakeholders

70
Q

“Change requests” is NOT output of only 1 process in M&C (besides other process groups). What is that?

A

Perform integrated change control

71
Q

“Change requests” is NOT output of only 2 processes in EXEXUTING (besides other process groups). What are they?

A

1-Manage project knowledge
2-Manage communications

72
Q

“Change requests” is output of only 4 processes in PLANNING (besides other process groups). What are they?

A

1-Define activities
2-Develop schedule
3-Plan risk responses
4-Plan procurement management

73
Q

“EEF (Enterprise Environmental Factors) updates” is output of only 4 processes. What are they?

A

1-Acquire resources
2-Develop team
3-Manage team

74
Q

“OPA (Organizational Process Assets) updates” is output of only 1 process in PLANNING (besides other process groups). What is that?

A

Plan procurement management

75
Q

“OPA (Organizational Process Assets) updates” is output of only 6 processes in EXECUTING (besides other process groups). What are they?

A

1-Direct & manage project work
2-Manage project knowledge
3-Acquire resources
4-Develop team
5-Manage communications
6-Conduct procurements

76
Q

“OPA (Organizational Process Assets) updates” is output of only 2 processes in M&C (besides other process groups). What are they?

A

1-Monitor risks
2-Control procurements

77
Q

“OPA (Organizational Process Assets) updates” is output of 7 processes in PLANNING & EXECUTING. There is one another process having it as output either in INITIATING, M&C or CLOSING. What it that?

A

Close project or phase

78
Q

“Project documents updates” is output of only 1 process in INITIATING (besides other process groups). What is that?

A

Identify stakeholders

79
Q

“Project documents updates” is NOT output of only 1 process in EXECUTING (besides other process groups). What is that?

A

Perform integrated change control

80
Q

“Project documents updates” is NOT output of only 1 process in EXECUTING (besides other process groups). What is that?

A

Perform integrated change control

81
Q

“Project documents updates” output of which process groups?

A

All process groups - one in initiating, some in Planning/Executing/M&C, and the only process of Closing.

82
Q

“Project documents updates” is output of only 2 processes in PLANNING/PROJECT SCOPE MANAGEMENT (besides other process groups). What are they?

A

1-Define scope
2-Create WBS

83
Q

“Project documents updates” is output of only 3 processes in PLANNING/PROJECT SCHEDULE MANAGEMENT (besides other process groups). What are they?

A

1-Sequence activities
2-Estimate activity durations
3-Develop schedule

84
Q

“Project documents updates” is output of only 3 processes in PLANNING/PROJECT COST MANAGEMENT (besides other process groups). What are they?

A

1-Estimate costs
2-Determine budget

85
Q

“Project documents updates” is output of only 3 knowledge areas with one processes in PLANNING (besides other process groups/Knowledge areas). What are the processes?

A

1-Plan quality management
2-Plan procurement management
3-Plan communications management

86
Q

“Project documents updates” is NOT output of only 1 process in PLANNING/PROJECT RISK MANAGEMENT (besides other process groups/Knowledge areas). What is that?

A

Plan Risk Management

87
Q

“Project documents updates” is output of only 1 knowledge areas with ALL its processes in PLANNING (besides other process groups/Knowledge areas). What are the processes?

A

1-Plan resource management
2-Estimate activity resources

88
Q

“Project documents updates” is output of some processes in M&C (besides other process groups/Knowledge areas). What is that?

A

All M&C processes

89
Q

“Project management plan updates” is output of only 1 process in INITIATING (besides other process groups). What is that?

A

Identify stakeholders

90
Q

“Project management plan updates” is output of only 5 processes in PLANNING (besides other process groups). What are they?

A

1-Define activities
2-Develop schedule
3-Plan quality management
4-Plan communications management
5-Plan risk responses

91
Q

“Project management plan updates” is NOT output of only 1 process in EXECUTING (besides other process groups). What is that?

A

Implement Risk Responses

92
Q

“Project management plan updates” is NOT output of only 1 process in M&C (besides other process groups). What is that?

A

Validate Scope