17-ITTO Memorization (Output) Flashcards
“Work performance information” is NOT output of only 10 processes. What they are?
All M&C EXCEPT Integration
“Work performance reports” is output of only 1 process. What is that?
Monitor & control project work
“Basis of estimates” is output of only 3 process. What are they?
All processes starting with “Estimate”:
1-Estimate activity durations
2-Estimate costs
3-Estimate activity resources
“Team performance assessments” is output of only 1 process. What is that?
Develop team
“Accepted deliverables” is output of only 1 process. What is that?
Validate scope
“Activity attributes” is output of only 1 process. What is that?
Define activities
“Activity list” is output of only 1 process. What is that?
Define activities
“Agreements” is output of only 1 process. What is that?
Conduct procurements
“Approved change requests” is output of only 1 process. What is that?
Perform integrated change control
“Assumption log” is output of only 1 process. What is that?
Develop Project charter
“Bid documents” is output of only 1 process. What is that?
Plan procurement management
“Closed procurements” is output of only 1 process. What is that?
Control procurements
“Communications management plan” is output of only 1 process. What is that?
Plan communications management
“Cost baseline” is output of only 1 process. What is that?
Determine budget
“Cost estimates” is output of only 1 process. What is that?
Cost estimates
“Cost forecasts” is output of only 1 process. What is that?
Control costs
“Cost management plan” is output of only 1 process. What is that?
Plan cost management
“Deliverables” is output of only 1 process. What is that?
Direct & manage project work
“Duration estimates” is output of only 1 process. What is that?
Estimate activity durations
“Final product, service, or result transition” is output of only 1 process. What is that?
Close project or phase
“Final report” is output of only 1 process. What is that?
Close project or phase
“Independent cost estimates” is output of only 1 process. What is that?
Plan procurement management
“Issue log” is output of only 1 process. What is that?
Direct & manage project work
“lessons learned register” is output of only 1 process. What is that?
Manage project knowledge
“Make-or-buy decisions” is output of only 1 process. What is that?
Plan procurement management
“Milestone list” is output of only 1 process. What is that?
Define activities
“Physical resource assignments” is output of only 1 process. What is that?
Acquire resources
“Procurement documentation updates” is output of only 1 process. What is that?
Control procurements
“Procurement management plan” is output of only 1 process. What is that?
Plan procurement management
“Procurement statement of work” is output of only 1 process. What is that?
Plan procurement management
“Procurement strategy” is output of only 1 process. What is that?
Plan procurement management
“Project calenders” is output of only 1 process. What is that?
Develop schedule
“Project charter” is output of only 1 process. What is that?
Develop Project charter
“Project communications” is output of only 1 process. What is that?
Manage communications
“Project funding requirements” is output of only 1 process. What is that?
Determine budget
“Project management plan” is output of only 1 process. What is that?
Develop Project management plan
“Project schedule” is output of only 1 process. What is that?
Develop schedule
“Project schedule network diagrams” is output of only 1 process. What is that?
Sequence activities
“Project scope statement” is output of only 1 process. What is that?
Define scope
“Project team assignments” is output of only 1 process. What is that?
Acquire resources
“Quality control measurements” is output of only 1 process. What is that?
Control quality
“Quality management plan” is output of only 1 process. What is that?
Plan quality management
“Quality metrics” is output of only 1 process. What is that?
Plan quality management
“Quality reports” is output of only 1 process. What is that?
Manage quality
“Requirements documentation” is output of only 1 process. What is that?
Collect requirements
“Requirements management plan” is output of only 1 process. What is that?
Plan scope management
“Requirements traceability matrix” is output of only 1 process. What is that?
Collect requirements
“Resource breakdown structure” is output of only 1 process. What is that?
Estimate activity resources
“Resource calenders” is output of only 1 process. What is that?
Acquire resources
“Resource management plan” is output of only 1 process. What is that?
Plan resource management
“Resource requirements” is output of only 1 process. What is that?
Estimate activity resources
“Risk management plan” is output of only 1 process. What is that?
Plan risk management
“Risk register” is output of only 1 process. What is that?
Identify risks
“Risk report” is output of only 1 process. What is that?
Identify risks
“Schedule baseline” is output of only 1 process. What is that?
Develop schedule
“Schedule data” is output of only 1 process. What is that?
Develop schedule
“Schedule forecasts” is output of only 1 process. What is that?
Control schedule
“Schedule management plan” is output of only 1 process. What is that?
Plan schedule management
“Scope baseline” is output of only 1 process. What is that?
Create WBS
“Scope management plan” is output of only 1 process. What is that?
Plan scope management
“Selected sellers” is output of only 1 process. What is that?
Conduct procurements
“Source selection criteria” is output of only 1 process. What is that?
Plan procurement management
“Stakeholder engagement plan” is output of only 1 process. What is that?
Plan stakeholder engagement
“Stakeholder register” is output of only 1 process. What is that?
Identify stakeholders
“Team charter” is output of only 1 process. What is that?
Plan resource management
“Test and evaluation documents” is output of only 1 process. What is that?
Manage quality
“Verified deliverables” is output of only 1 process. What is that?
Control quality
“Work performance data” is output of only 1 process. What is that?
Direct & manage project work
“Change requests” is output of only 1 process in INITIATING (besides other process groups). What is that?
Identify stakeholders
“Change requests” is NOT output of only 1 process in M&C (besides other process groups). What is that?
Perform integrated change control
“Change requests” is NOT output of only 2 processes in EXEXUTING (besides other process groups). What are they?
1-Manage project knowledge
2-Manage communications
“Change requests” is output of only 4 processes in PLANNING (besides other process groups). What are they?
1-Define activities
2-Develop schedule
3-Plan risk responses
4-Plan procurement management
“EEF (Enterprise Environmental Factors) updates” is output of only 4 processes. What are they?
1-Acquire resources
2-Develop team
3-Manage team
“OPA (Organizational Process Assets) updates” is output of only 1 process in PLANNING (besides other process groups). What is that?
Plan procurement management
“OPA (Organizational Process Assets) updates” is output of only 6 processes in EXECUTING (besides other process groups). What are they?
1-Direct & manage project work
2-Manage project knowledge
3-Acquire resources
4-Develop team
5-Manage communications
6-Conduct procurements
“OPA (Organizational Process Assets) updates” is output of only 2 processes in M&C (besides other process groups). What are they?
1-Monitor risks
2-Control procurements
“OPA (Organizational Process Assets) updates” is output of 7 processes in PLANNING & EXECUTING. There is one another process having it as output either in INITIATING, M&C or CLOSING. What it that?
Close project or phase
“Project documents updates” is output of only 1 process in INITIATING (besides other process groups). What is that?
Identify stakeholders
“Project documents updates” is NOT output of only 1 process in EXECUTING (besides other process groups). What is that?
Perform integrated change control
“Project documents updates” is NOT output of only 1 process in EXECUTING (besides other process groups). What is that?
Perform integrated change control
“Project documents updates” output of which process groups?
All process groups - one in initiating, some in Planning/Executing/M&C, and the only process of Closing.
“Project documents updates” is output of only 2 processes in PLANNING/PROJECT SCOPE MANAGEMENT (besides other process groups). What are they?
1-Define scope
2-Create WBS
“Project documents updates” is output of only 3 processes in PLANNING/PROJECT SCHEDULE MANAGEMENT (besides other process groups). What are they?
1-Sequence activities
2-Estimate activity durations
3-Develop schedule
“Project documents updates” is output of only 3 processes in PLANNING/PROJECT COST MANAGEMENT (besides other process groups). What are they?
1-Estimate costs
2-Determine budget
“Project documents updates” is output of only 3 knowledge areas with one processes in PLANNING (besides other process groups/Knowledge areas). What are the processes?
1-Plan quality management
2-Plan procurement management
3-Plan communications management
“Project documents updates” is NOT output of only 1 process in PLANNING/PROJECT RISK MANAGEMENT (besides other process groups/Knowledge areas). What is that?
Plan Risk Management
“Project documents updates” is output of only 1 knowledge areas with ALL its processes in PLANNING (besides other process groups/Knowledge areas). What are the processes?
1-Plan resource management
2-Estimate activity resources
“Project documents updates” is output of some processes in M&C (besides other process groups/Knowledge areas). What is that?
All M&C processes
“Project management plan updates” is output of only 1 process in INITIATING (besides other process groups). What is that?
Identify stakeholders
“Project management plan updates” is output of only 5 processes in PLANNING (besides other process groups). What are they?
1-Define activities
2-Develop schedule
3-Plan quality management
4-Plan communications management
5-Plan risk responses
“Project management plan updates” is NOT output of only 1 process in EXECUTING (besides other process groups). What is that?
Implement Risk Responses
“Project management plan updates” is NOT output of only 1 process in M&C (besides other process groups). What is that?
Validate Scope