16-ITTO Memorization (Input) Flashcards
“Project Management Plan” is NOT input to only 2 processes. What are they?
1-Develop Project Charter
2-Develop Project Management Plan
“Work performance data” is input to which processes?
All M&C processes EXCEPT Integration ones
“Work performance data” is input to which processes?
M&C -1
“Project Management Plan” is input to only 1 process. What is that?
Perform integrated change control
“EEF (Enterprise Environmental Factors)” is input to which processes?
1-All Initiating
2-All Planning
3-All Executing EXCEPT Quality and Risk
4-All M&C EXCEPT Scope, Schedule, Cost, Resource, Risk
“EEF (Enterprise Environmental Factors)” is input to which processes?
1-All Initiating
2-All Planning
3-All Executing -58
4-All M&C -23468
“Accepted deliverables” is input to only 1 process. What is that?
Close project or phase
“Approved Change requests” is input to only 3 processes. What are they?
1-Direct & manage project work
2-Control quality
3-Control procurements
“Deliverables” is input to only 2 processes. What are they?
1-Manage project knowledge
2-Control qutality
“OPA (Organizational Process Assets)” is NOT input to only 2 processes. What are they?
1-Validate Scope
2-Monitor Risk
“Outputs from other processes” is input to only 1 process. What is that?
Develop Project management plan
“Project funding requirements” is input to only 1 process. What is that?
Control costs
“Seller proposals” is input to only 1 process. What is that?
Conduct procurements
“Team performance assessments” is input to only 1 process. What is that?
Manage team
“Verified deliverables” is input to only 1 process. What is that?
Validate scope
“Work performance information” is input to only 1 process. What is that?
Monitor & control project work
“Agreements” is input to which processes of INITIATING and CLOSING?
All of them
“Agreements” is input to only 5 processes of PLANNING. What are they?
1-Collect requirements
2-Develop schedule
3-Determine budget
4-Identify risks
5-Plan stakeholder engagement
“Agreements” is input to which processes of EXECUING?
None of them
“Agreements” is input to only 3 processes of M&C. What are they?
1-Monitor & control project work
2-Control resources
3-Control procurements
“Procurement documentation” is input to only 4 processes. What are they?
1-Close project or phase
2-Identify risks
3-Conduct procurements
4-Control procurements
“Business documents” is input to which processes of INITIATING and CLOSING?
1-Develop Project charter
2-Identify stakeholders
3-Close project or phase
“Business documents” is input to only 3 processes of PLANNING. What are they?
1-Collect requirements
2-Determine budget
3-Plan procurement management
“Project charter” is input to which processes of INITIATING and CLOSING?
1-Identify stakeholders
2-Close project or phase
“Project charter” is input to only 12 processes of PLANNING. What are they?
1-Develop Project management plan
2-Plan scope management
3-Collect requirements
4-Define scope
5-Plan schedule management
6-Plan cost management
7-Plan quality management
8-Plan resource management
9-Plan communications management
10-Plan risk management
11-Plan procurement management
12-Plan stakeholder engagement
“Project documents” is input to which processes of INITIATING and CLOSING?
1-Identify stakeholders
2-Close project or phase
“Project documents” is input to which processes of EXECUTING?
All of them
“Project documents” is input to which processes of M&C?
All of them
“Project documents” is input to which processes of PLANNING/PROJECT SCOPE MANAGEMENT?
Create WBS
“Project documents” is input to which processes of PLANNING/PROJECT SCHEDULE MANAGEMENT?
1-Sequence activities
2-Estimate activity durations
3-Develop schedule
“Project documents” is input to which processes of PLANNING/PROJECT COST MANAGEMENT?
1-Estimate costs
2-Determine budget
“Project documents” is input to which processes of PLANNING/PROJECT QUALITY MANAGEMENT?
Plan quality management
“Project documents” is input to which processes of PLANNING/PROJECT RESOURCE MANAGEMENT?
1-Plan resource management
2-Estimate activity resources
“Project documents” is input to which processes of PLANNING/PROJECT COMMUNICATION MANAGEMENT?
Plan communications management
“Project documents” is input to which processes of PLANNING/PROJECT RISK MANAGEMENT?
All of them
“Project documents” is input to which processes of PLANNING/PROJECT PROCURMENT MANAGEMENT?
Plan procurement management
“Work performance reports” is input to only 4 processes. What are they?
1-Perform integrated change control
2-Manage team
3-Manage communications
4-Monitor risks