10.1 Flashcards

Roles required in the administration of the construction contract

1
Q

Architect Responsibilities:
What is the role of the Architect in the administration of a construction contract?

A

To be the professional advisor to the the owner in interpreting the construction documents and advising the contractor on performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Architect Responsibilities:
What are the office responsibilities of the architect?

A
  • Review submittals
  • Issue Supplemental Instructions (SI), Potential Change Orders (PCO), Change Orders (CO)
  • Respond to Requests for Information (RFI’s)
  • Process and review changes
  • Review progress claims
  • Prepare CFP
  • Coordinate review from consultants
  • Review shop drawings
  • Obtain O+M and closeout docs
  • Prepare record drawings
  • Follow up with warranty items during the warranty period
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Architect Responsibilities:
What are the site responsibilities of the architect?

A
  • Conduct general or field reviews
  • Attend site meetings
  • Interpret contract documents
  • Review and accept samples/mockups
  • Meet with consultants/clients to determine construction progress/percentage of work completed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Owner Responsibilities:
What are the responsibilities of the client/owner?

A
  • Provide financing information if required
  • Making payments to the contractor
  • Review and approve changes
  • Supply owner provided materials
  • Apply for service connections
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Contractor Responsibilities:
What are the responsibilities of the contractor?

A
  • Takes on responsibility/control of construction (Workplace safety, work of all subtrades, pays for labor and materials)
  • Obtain and pay for permits
  • Shop drawings, mock ups, samples
  • Provide schedule updates
  • Progress claims, RFI’s, change requests
  • Apply for substantial performance
  • Provide closeout materials (Warranties, inspections reports, O+M’s, as built’s)