Zoe 2019 (Oakland Mock) Flashcards

1
Q

Contract forms and General Conditions are best provided by the:

A. Owner.

B. Architect/Engineer.

C. Building official.

D. Contractor.

A
  • Contract forms and General Conditions are best provided by the:*
  • A. Owner.*
  • B. Architect/Engineer.*
  • C. Building official.*
  • D. Contractor.*

A. - PDPG Conditions of Contract, 12.3.1.2, (312), 12.3.3, (316), & 7.10.2, (127)

12.3.1.2 00 52 00 Agreement Forms

  • 00 52 13 Agreement Form - Stipulated Sum (Single-Prime Contract)
  • 00 52 16 Agreement Form - Stipulated Sum (Multiple-Prime Contract)
  • 00 52 23 Agreement Form - Construction Management (Single-Prime Contract)
  • 00 52 26 Agreement Form - Construction Management (Multiple-
  • Prime Contract)
  • 00 52 33 Agreement Form - Cost-Plus-Fee (Single-Prime Contract)
  • 00 52 36 Agreement Form - Cost-Plus-Fee (Multiple-Prime Contract)
  • 00 52 43 Agreement Form - Unit Price (Single-Prime Contract)
  • 00 52 46 Agreement Form - Unit Price (Multiple-Prime Contract)
  • 00 52 53 Agreement Form - Design/Build (Single-Prime Contract)
  • 00 52 56 Agreement Form - Design/Build (Multiple-Prime Contract)
  • 00 52 63 Agreement Form - Purchase Contract

The nature of an agreement, in general, has been previously discussed in Chapter 7. The essence of an agreement is the meeting of the minds of two parties about a specific scope of work in exchange for an amount of compensation, which is then put in written form. While an owner has a right to use whatever form of agreement desired, it is prudent to use standardized agreements.

Standardized agreement forms are listed in Section 7.10.

12.3.3 00 70 00 Conditions of the Contract

Conditions of the contract define basic rights, responsibilities, and relationships of the parties involved in the performance of the contract. These conditions are an inherent part of the owner-contractor agreement and are considered the general conditions of the agreement. Limited services or abbreviated agreements normally contain the general conditions within the agreement. However, the involvement of other participants (e.g., architect/engineer or construction manager) and the delegation of responsibilities to subcontractors lead to the relatively public nature of the conditions of the contract. The need for review by those not signatory to the agreement has led to the use of conditions of the contract separate from the agreement

Though not a signatory to the owner-contractor agreement, the architect/engineer commonly has duties and responsibilities described in the conditions of the contract and may assist in their preparation. Under AIA A201, architect/engineer duties and responsibilities under conditions of the contract generally include administration of the construction contract in the following ways:

  • Acting as an owner’s representative for matters concerning the work.
  • Visiting the construction site to become familiar with the work, confirming the work is in conformance with the contract documents, and evaluate progress.
  • Validating the progress of the work to authorize progress payments.
  • Preparing the following:
  • Architect’s Supplemental Instructions or field orders.
  • Construction change directives or work change directives.
  • Change orders.
  • Clarifying and interpreting the contract documents.
  • Reviewing, approving, or taking other appropriate action on submittals such as shop drawings, mock-ups, and samples
  • Rejecting defective work.
  • Determining dates of substantial completion and final completion.

Conditions of the contract need to be closely coordinated with related documents such as the design and construction agreements and Division 01 - General Requirements. Changes in one document may necessitate changes in the other documents.

General and supplementary conditions are conditions of the contract and have legal consequences. The architect/engineer should not prepare general or supplementary conditions without explicit approval and guidance from the owner, the owner’s legal counsel, and the owner’s insurance adviser.

7.10.2 Standardized Agreements and Forms

Several professional associations have developed various standardized agreements and forms that are compatible with their respective general conditions and are tailored to specific types of project delivery and basis of compensation for design agreements and basis of payment for construction agreements.

This standardization of agreements and forms is desirable because it saves preparation time and offers reasonable assurance of a complete and accurate document. Through repeated use, standardized agreements and forms have become well understood by owners, architect/engineers, contractors, subcontractors, and suppliers and are less subject to misinterpretation. The agreements and forms to be used on a project should be reviewed carefully by the party’s legal counsel before modification and execution.

Standardized agreements and forms have a long history of legal precedence, have been interpreted and adjudicated by the legal profession and the courts, are under constant review, and are updated and reissued on a periodic basis. Because of this, modifications should be made with caution and not without review by an attorney.

Modifications to one document may require coordination with and modification to another. For example, modifications without proper coordination with the general conditions may create conflicts and problems within the contract documents.

With the assistance of the architect/engineer, the owner, in consultation with their legal counsel, should determine the appropriate contractual conditions and forms of agreements that should be used for a project. These general conditions and agreements should be coordinated and compatible with other project agreements to ensure that dudes, rights, and responsibilities are consistent among stakeholders and participants. These general conditions and agreements must be compatible for the architect/engineer and the contractor to ensure that liabilities and responsibilities are property assigned. In some types of project delivery methods, these responsibilities may be combined; however, the licensing requirements and liability issues need to be dearly delineated in the general conditions and agreements.

The proper conditions are significant issues to ensure proper execution of the work.

While either party has the right to use custom-drafted agreements for its projects, caution is advised because the project delivery of design and construction is a very complex process. Private projects tend to rely on standardized agreements and forms that have been developed, monitored, and maintained by professional associations. However, some corporations and public agencies have developed specific agreement forms that must be used on their projects. In today’s world, the use of standard agreements and forms, modified for the specific project, instead of using custom-drafted agreements is considered by many to be good professional practice.

Standardized agreements and forms provide many advantages for projects, including, but not limited to, the following:

  • Language consistency and enforcement predictability.
  • Legal preparation time, and therefore expense, is less than for custom-drafted documents.
  • Reflect both industry practices and customs, or may be based on a consensus of those that use the forms.
  • Risks and responsibilities are assigned to the party that is best able to control them or protect from unexpected costs.
  • Developed with the understanding that they would be tailored by attorneys to fit the unique requirements of a specific project.

Users of any of the standardized agreements and forms should understand that each of the five professional associations have created standardized agreements and forms that are distinctly different and unique and are written from the standpoint of their respective professional association. While there are similarities in a document types, such as general conditions, there are also many differences. Also, users are discouraged from using a document from one professional association and another from a different professional association in combination for a single project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Modifications to Contract Document are made during which phases of the project?

A. Planning and design.

B. Design and construction.

C. Design and bidding.

D. Bidding and construction.

A
  • Modifications to Contract Document are made during which phases of the project?*
  • A. Planning and design.*
  • B. Design and construction.*
  • C. Design and bidding.*
  • D. Bidding and construction.*

D. - PDPG 13.4.2.8, (333) & 15.11.2, (403)

13.4.2.8 Addenda

Addenda are issued after the bidding period starts and before the bids or proposals are submitted to the owner. Examples of addenda modifications include, but are not limited to, the following:

  • Provide answers to questions proposed by bidders.
  • Documentation of new requirements.
  • Make changes to the work.
  • Correct errors or omissions in the procurement documents.
  • Include additional qualified products or approved substitutions.

Administrative requirements for addenda, the method of issue, and other pertinent facts concerning addenda are included in the instructions to bidders. Also, addenda are acknowledged on the bid form. Addenda requirements applicable to the contract documents will be incorporated into the contract between the owner and contractor. An example of an addenda is shown in Figure 13.1.

15.11.2 Contract Modifications

As discussed above, changes to the contract documents are inevitable during construction. The method to formally document changes begins with determining which of the following classifications a change belongs to:

  • Those that affect the contract time or contract cost.
  • Those that do not affect the contract time or contract cost.

Well-prepared and coordinated general conditions, and the specifications in Division 01-General Requirements, details the methods under which changes to the contract documents can be formally made and documented. Several methods are provided to make contract document changes:

  • Minor changes (that do not affect contract time or contract cost):
  • Architect’s supplemental instructions (AIA).
    • Owner’s written order (ConsensusDocs®).
    • Minor variations in the work (CMAA).
    • Minor change (DBIA).
    • Field order (EJCDC).
    • Written interpretation or clarification (EJCDC).
  • Change directives (directs change to be made; contract time or contract time adjusted later in the form of a change order):
    • Construction change directive (AIA).
    • Interim directed change (ConsensusDocs®).
    • Work change directive (DBIA).
    • Work change directive (EJCDC).
  • Change orders (directs change to be made with the stipulated contract sum and/or contract time adjustments).

Several additional considerations about contract modifications include, but are not limited to, the following:

  • The architect/engineer should avoid relying on modifications to correct inadequately prepared drawings or specifications.
  • A request for a contract modification can be initiated by the owner, the contractor, or the architect/engineer.
  • Contract modifications are not required when a response to a request for information (RFI) does not require a change to the contract documents.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The Procurement Requirements usually include:

A. Invitation to Bid, Instructions to Bidders, Information Available to Bidders, Bid Forms and Attachments, and Bid Security Forms.

B. Instructions to Bidders, Information Available to Bidders, Bid Forms and Attachments, and Bid Security Forms.

C. Instructions to Bidders, Information Available to Bidders, Bid Forms and Attachments, Bid Security Forms, Conditions of the Contract, Specifications, and Drawings.

D. All the documents necessary to bid the project.

A
  • The Procurement Requirements usually include:*
  • A. Invitation to Bid, Instructions to Bidders, Information Available to Bidders, Bid Forms and Attachments, and Bid Security Forms.*
  • B. Instructions to Bidders, Information Available to Bidders, Bid Forms and Attachments, and Bid Security Forms.*
  • C. Instructions to Bidders, Information Available to Bidders, Bid Forms and Attachments, Bid Security Forms, Conditions of the Contract, Specifications, and Drawings.*
  • D. All the documents necessary to bid the project.*

A. - PDPG 12.2, (297 - 311)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The document that guarantees the surety will either complete the Contract or provide sufficient funds to do so, if the contractor defaults, is called a:

A. Certificate of insurance.

B. Payment bond.

C. Performance bond.

D. Bid bond.

A
  • The document that guarantees the surety will either complete the Contract or provide sufficient funds to do so, if the contractor defaults, is called a:*
  • A. Certificate of insurance.*
  • B. Payment bond.*
  • C. Performance bond.*
  • D. Bid bond.*

C. - PDPG 12.4.5, (320)

12.4.5 Performance Bond

A performance bond provides the most important protection for the owner by guaranteeing that if the contractor defaults, the surety will either complete the contract in accordance with its terms or provide sufficient funds, up to the penal amount of the bond, to fund such completion.

If there is a default and the owner makes a demand upon a surety to perform under the terms of the performance bond, the surety will investigate the owner’s claim against the contractor. This investigation will include examining both the owner’s and the contractor’s positions and making an independent analysis of the situation. Once the validity of the claim has been established, the surety has several options as to how it will fulfill the bond obligation that includes the following:

  • If the contractor’s work is satisfactory and the problems are only financial, the surety may choose to finance the contractor to complete the project. Under this option, the surety provides funds to the contractor so that the contractor can pay subcontractors and suppliers, buy materials, make payroll, and take other steps necessary to complete the project.
  • If the owner has terminated the contract, the surety can complete the project by taking over the work itself and hiring another contractor, or by arranging for a completion contractor to work directly for the owner.
  • The surety may also leave it up to the owner to finish the project and pay the difference between the balance left in the original contract and the actual cost of completion.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Specifications are responsible for defining the:

A. Qualitative requirements for materials.

B. Level of workmanship required.

C. Administrative procedures and quantitative requirements for materials.

D. Administrative procedures, qualitative requirements for materials and level of workmanship required.

A
  • Specifications are responsible for defining the:*
  • A. Qualitative requirements for materials.*
  • B. Level of workmanship required.*
  • C. Administrative procedures and quantitative requirements for materials.*
  • D. Administrative procedures, qualitative requirements for materials and level of workmanship required.*

D. - PDPG 11.3.2, (252); 11.3.5.4, (255) & 11.3.5.6, (257)

11.3.2 Nature of Specifying

A simple definition of the word specify is to describe or define an object, idea, or concept in such detail that it is easily understood by most people. It is not practical for construction drawing notes to include sufficient information to properly specify products and their installation. While construction drawings show products, materials, and equipment quantitatively, specifications detail their qualitative requirements.

Whether specifying buildings, civil structures, or bridges, specifications should describe each product, material, or piece of equipment in sufficient detail so each can be purchased, manufactured, or fabricated according to the contract requirements. It is not necessary for a specification to include every attribute, physical property, or characteristic of a product, only those that will facilitate its incorporation into the project.

11.3.5.4 Specifying Workmanship

Workmanship requirements have measurable properties and can be specified with a means to verify compliance. Workmanship can be controlled in several articles of a specification section. These articles specify qualifications, tolerances, and various other aspects of quality assurance and quality control. Workmanship can be divided into two main categories:

  • Workmanship relating to the manufacturing and fabrication of products.
  • Workmanship relating to the application, installation, or erection of products.

It is a combination of materials and workmanship that results in the final characteristics of the product. Workmanship requirements are specified to an appropriate level in accordance with the needs of the project. Project requirements should be specified without demanding conformance to unattainable standards or to standards exceeding those necessary for the requirements of the overall project.

  • Workmanship requirements should be measurable. Avoid broad generalities such as “best possible workmanship.”
  • Appropriate methods for achieving desired workmanship include:
  • Referring to applicable standards and codes.
  • Establishing qualifications of manufacturer, fabricator, and/or installer.
  • Referring to workmanship requirements of trade associations.
  • Requiring samples to establish an acceptable level of workmanship and a basis forjudging subsequent work.
  • Specifying tolerances and performance or physical requirements.
  • Establishing testing and inspection requirements.
  • Mock-ups for critical design features or assemblies.

11.3.5.6 Specifying Quality Assurance and Quality Control

The agreed upon requirements, extent (scope), time (schedule), and cost (budget) establish the project quality. Specifications generally stipulate qualitative requirements and the drawings generally indicate quantitative requirements.

QUALITY ASSURANCE IN THE CONDITIONS OF THE CONTRACT. The basis for quality assurance (QA) is included in the conditions of the contract. Some assurances are based in the legalities of the contract. Most standardized general conditions published by professional associations include warranty provisions requiring the following:

  • Contractor’s affirmation that materials and equipment will be new and of good quality, unless otherwise required or allowed.
  • The Work will be free from defects not inherent in the quality required or allowed.
  • The Work will conform to the requirements of the contract documents.

QUALITY CONTROL IN THE CONDITIONS OF THE CONTRACT. The quality control (QC) provisions in the conditions of the contract are to verify conformance with the contract requirements. For example, AIA A201™ include the following requirements of the contractor:

  • To supervise the work using expertise, skill, and attention.
  • To be solely responsible for controlling the means, methods, techniques, sequences, and procedures for construction and is therefore responsible for controlling the quality of the work.

Also, AIA A201™ include the following requirements of the architect:

  • To visit the site to become generally familiar with the progress and quality of the completed work.
  • Based on field observations, the architect reviews the contractor’s applications for payment and certifies payment of amounts due.
  • To reject work that is defective or does not conform to the contract documents. This authority does not constitute control of the work, nor does this authority establish a responsibility for means, methods,

techniques, sequences, or procedures for construction. To require additional independent inspection and testing when necessary.
DIVISION 01-GENERAL REQUIREMENTS. The following are several Division 01 sections that often include provisions for quality assurance or establish quality controls over the work:
• Regulatory Requirements,
• Project Management and Coordination,
• Submittal Procedures,
• Quality Assurance,
• Quality Control,
• Substitution Procedures, and
• Commissioning.
SPECIFICATIONS. Divisions 02 through 49 are composed of individual sections, each addressing a distinct work results area. The issues and requirements concerning quality assurance and quality control specific to that section are addressed within the specification. The contract documents are so interrelated none of them can stand alone. An examination of Section Format™ will help clarify the interrelationships between the requirements of articles within individual sections in Divisions 02 through 49 and Division 01 specification sections. The requirements in Division 01 are dependent upon provisions in the conditions of the contract.
For example, the articles within a specification that specify various aspects of quality include the following:
PART 1 - GENERAL. Includes articles on administrative matters. The following articles that deal specifically with quality are:
• Administrative Requirements,
• Submittals, and
• Quality Assurance.
PART 2 - PRODUCTS. Includes articles related to the manufacture and fabrication of products. The following articles that deal specifically with quality are:
• Assembly or Fabrication Tolerances,
• Source Quality Control,
• Tests,
• Inspections, and
• Manufacturer Services.

PART 3 - EXECUTION. Covers work performed at the project site. The following articles that deal specifically with quality are:
• Tolerances,
• Field or Site Quality Control.
• Field or Site Tests.
• Field or Site Inspection.
• Manufacturer’s Services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The element of the construction documents that contains the Procurement Requirements, Contract, Forms, Contract Conditions, and Specifications is called the:

A. Procurement Documents

B. Contract Documents

C. Specifications Book

D. Project Manual

A
  • The element of the construction documents that contains the Procurement Requirements, Contract, Forms, Contract Conditions, and Specifications is called the:*
  • A. Procurement Documents*
  • B. Contract Documents*
  • C. Specifications Book*
  • D. Project Manual*

D. - PDPG 11.3.5.1, (253)

11.3.5.1 Project Manual Concept

The documents commonly referred to as the specifications normally contains much more than that name implies. The procurement requirements, contracting forms, and conditions of the contract are usually included, but they are not specifications. In most cases, these are prepared by, or in coordination with, the owner and the owner’s legal counsel and insurance adviser. This information, along with the specifications, is, in fact, a collection of certain written construction documents and project requirements whose contents and functions are best implied by the title Project Manual. With different methods of construction procurement, some documents become unnecessary. For example, in the owner-build delivery method and with negotiated contracts, bidding requirements are not applicable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which of the following is a purpose of GreenFormat:

A. Provide a uniform presentation of sustainability information.

B. Verify manufacturer’s sustainability claims.

C. Substantiate and verify sustainable content of materials.

D. “Green-wash” product information.

A
  • Which of the following is a purpose of GreenFormat:*
  • A. Provide a uniform presentation of sustainability information.*
  • B. Verify manufacturer’s sustainability claims.*
  • C. Substantiate and verify sustainable content of materials.*
  • D. “Green-wash” product information.*

A. - GreenFormat web page

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

In a standard single-prime construction contract project, the Owner has contractual relationships with the:

A. Contractor.

B. Contractor and subcontractors.

C. Contractor and Architect/Engineer.

D. Contractor, subcontractors, and suppliers.

A
  • In a standard single-prime construction contract project, the Owner has contractual relationships with the:*
  • A. Contractor.*
  • B. Contractor and subcontractors.*
  • C. Contractor and Architect/Engineer.*
  • D. Contractor, subcontractors, and suppliers.*

C. - PDPG 4.4.1, (39)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which of the following would be found in a GreenFormat entry:

A. VOC content

B. Recycled material content

C. Product lifecycle assessment information

D. All of the above.

A
  • Which of the following would be found in a GreenFormat entry:*
  • A. VOC (Volatile Organic Compound) content*
  • B. Recycled material content*
  • C. Product lifecycle assessment information*
  • D. All of the above.*

D. - GreenFormat web page

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The contract method in which the Owner hires an agent to oversee design, evaluate bids, award contracts, and coordinate the work is called:

A. Construction Management as Contractor

B. Construction Manager as Advisor.

C. Design-Build.

D. Multiple-Contracting

A
  • The contract method in which the Owner hires an agent to oversee design, evaluate bids, award contracts, and coordinate the work is called:*
  • A. Construction Management as Contractor*
  • B. Construction Manager as Advisor.*
  • C. Design-Build.*
  • D. Multiple-Contracting*

B. - PDPG 4.9.1 &4.9.2, (68 - 69)

4.9.1 Construction Manager as Agent

Construction Manager as Agent is management method, known as Construction Manager as Agent, abbreviated as CM-Agent, has the construction manager acting as the owner’s agent. An agency relationship is established by agreement and is when one party, in this case the owner, delegates the authority to act in the best interests of the owner to another party, the CM-Agent. This means that the CM-Agent can make and render binding decisions on behalf of the owner. The level of authority delegated to the CM-Agent is defined by the agreement with the owner.

In addition to acting as the owner’s agent, other characteristics of CM-Agent include, but are not limited, to the following:

  • Does not enter into agreements with contractor, subcontractors, or suppliers; only with the owner
  • Does not guarantee, and is not directly responsible for construction risks such as the following:
    • Schedule delays
    • Cost overruns
    • Construction defects
  • Is not at risk for the performance of the contractor
  • Sufficient authority should be delegated so that the CM-Agent can make timely decisions and hold team members accountable for those decisions
  • Provides project coordination, administration, and management
  • Provides leadership
  • Provides constructability reviews
  • Coordinates, receives, and possibly negotiates trade bids and prepare them for review and execution by the owner
  • Takes an active role in scheduling and project coordination meetings
  • Provides financial oversight during construction, including monitoring payment requests and the overall construction budget
  • Assists the owner with the review, evaluation, and documentation of claims

4.9.2 Construction Manager as Advisor

This management method, known as Construction Manager as Advisor, abbreviated as CM-Advisor, has the construction manager acting as the owner’s advisor. The CM-Advisor may not participate in the day-to-day project activities as the CM-Agent does, but may only advise the owner about project activities. While the CM-Advisor may offer the many of the same services offered by the CM-Agent, the CM-Advisor does not have the authority to act or make binding decisions on behalf of the owner. The CM-Advisor does not enter into any agreements except with the owner.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The Contract Documents usually include the:

A. Instructions to Bidders, Bid Form, Agreement, General & Supplementary Conditions, Specifications, Drawings.

B. Bid Form, Agreement, General & Supplementary Conditions, Specifications, Drawings.

C. Agreement, General & Supplementary Conditions, Specifications, Drawings, Addenda.

D. Agreement, General & Supplementary Conditions, Specifications, Drawings.

A
  • The Contract Documents usually include the:*
  • A. Instructions to Bidders, Bid Form, Agreement, General & Supplementary Conditions, Specifications, Drawings.*
  • B. Bid Form, Agreement, General & Supplementary Conditions, Specifications, Drawings.*
  • C. Agreement, General & Supplementary Conditions, Specifications, Drawings, Addenda.*
  • D. Agreement, General & Supplementary Conditions, Specifications, Drawings.*

C. - PDPG 14.3, (363)

14.3 Contract Documents

The owner-contractor agreement establishes the documents that are considered contract documents which are typically used in the construction of a project. Contract documents generally include the following:

  • Owner-contractor agreement.
  • General and supplementary .conditions.
  • Specifications.
  • Drawings.
  • Bid form or proposal, when attached as an exhibit to the agreement (EJCDC; engineering projects generally have many unit prices).
  • Precontract revisions, including post-bid addenda (AIA) with items relating to contract documents.
  • Notice to proceed (as required by most EJCDC agreements, and as required by some public- and private-sector projects utilizing standard or modified AIA agreements).
  • Contract modifications, including addenda before execution of the agreement change orders after execution of the agreement.

These documents are interrelated, and it is necessary that those responsible for construction contract administration and contractor project management have a working knowledge of each of the documents. While the agreements are not usually shared among the project participants, the rights, roles, and responsibilities of the participants are covered in the general conditions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The contract type most often associated with the term “turnkey” is called:

A. Construction Management.

B. Project Management.

C. Design-Build.

D. Owner-Builder.

A
  • The contract type most often associated with the term “turnkey” is called:*
  • A. Construction Management.*
  • B. Project Management.*
  • C. Design-Build.*
  • D. Owner-Builder.*

C. - PDPG 4.6.2, (55)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The simplest method of stating a project’s cost is by a:

A. Stipulated or Lump Sum.

B. Unit Price.

C. Cost-Plus-Fee.

D. Any of the above.

A
  • The simplest method of stating a project’s cost is by a:*
  • A. Stipulated or Lump Sum.*
  • B. Unit Price.*
  • C. Cost-Plus-Fee.*
  • D. Any of the above.*

A. - PDPG 4.4.4.1, (43)

Lump Sum

The most common and simplest method of determining and stating the contract sum is the lump sum method, in which a single amount is quoted for all of the work. The contractor is paid the contract sum in one or more installments. With the lump sum method, the initial contract sum is determined during bidding, and may be required for budgetary reasons. Using this method, if the amount bid is within the budget, the project proceeds; if the amount bid is over budget, rebidding or other steps must be taken to either augment the budget or bring the bid amount within the budget. In competitive bidding and informal bidding, lump sums are quoted by the bidders; in negotiated contracting, a lump sum is negotiated between the owner and the contractor.

Cost-Plus-Fee

When the cost-plus-fee method is used to determine the contract sum, the contractor is reimbursed for the actual cost of labor and materials and is paid a fee for overhead and profit (the fee may be a percentage of the labor and materials costs or a fixed amount). With this method, the contract sum is not fully determined until the work is completed (the initial contract sum is the amount of the fixed fee or the percentage due to contractor which will be converted to a dollar amount after completion of the work). In some cases, the owner stipulates a guaranteed maximum sum that cannot be exceeded.

Unit Price

With some projects, the extent of work cannot be fully determined, or the actual quantities of required items cannot be accurately calculated in advance. In these cases, bidders are requested to submit bids based on unit prices.

Unit-price contracts subdivide the work or parts of the work into like items and state approximate quantities for each item. The bidders use these quantities in preparing their bids. A price per unit of measurement (unit price) is quoted for each item. Sums for the extended unit prices are not included in the initial contract sum. As the work is completed, actual quantities are measured, and the contractor is paid according to the contractor’s quoted unit prices. The owner pays only for the actual quantities of materials used.

Unit prices may or may not be used as a basis of award. Sometimes, unit prices are requested at bid time to add work to a project but are not used as a basis of award.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Which is usually NOT a factor in determining the length of the bidding period?

A. Time reasonably necessary for bidders to complete bids.

B. Time for settlement of questions and discrepancies.

C. Urgency dictated by the Owner’s requirements.

D. Time required for bidders to visit and examine the jobsite.

A
  • Which is usually NOT a factor in determining the length of the bidding period?*
  • A. Time reasonably necessary for bidders to complete bids.*
  • B. Time for settlement of questions and discrepancies.*
  • C. Urgency dictated by the Owner’s requirements.*
  • D. Time required for bidders to visit and examine the jobsite.*

C. - PDPG 13.4.2.4, (332)

13.4.2.4 Establishing a Competitive Bidding Period

The extent (scope) of the project influences the length of time that is allowed for the preparation of bids or proposals. Although the length of the bidding period varies from project to project, all projects should allow sufficient time for bidders to:

  • Study the procurement documents including available information.
  • Attend a prebid meeting for an introduction to the project and existing conditions.
  • Visit the site to verify existing conditions and correlate the information in the procurement documents with observations.
  • Make inquiries regarding existing conditions and the procurement documents.
  • Propose substitutions when permitted by the procurement documents.
  • Receive addenda resulting from bidder inquiries and substitution proposals.
  • Solicit, evaluate, and compile prices from subcontractors and suppliers.
  • Obtain bid security when required by the procurement requirements.
  • Prepare qualification statements when required by the procurement requirements.

The competitive bidding period should allow a reasonable amount of time to perform these procedures and activities. Bidding periods for public projects must be structured according to prescribed time periods to ensure the activities are performed according to prevailing laws. Although private projects are not subject to the same restrictions as public projects, the length of the competitive bidding stage might affect the accuracy and number of bids or proposals submitted. The architect/engineer should advise the owner about the activities of a well-structured bidding period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

All of the following are usually part of the Invitation or Advertisement for Bidders EXCEPT:

A. Time of Completion

B. Provisions for liquidated damages

C. Bid security reference

D. Types of bids required

A
  • All of the following are usually part of the Invitation or Advertisement for Bidders EXCEPT:*
  • A. Time of Completion*
  • B. Provisions for liquidated damages*
  • C. Bid security reference*
  • D. Types of bids required*

B. - PDPG 12.2.1 & Fig. 12.1, (297 - 300)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The main purpose of the Supplementary Conditions is:

A. As the replacement document for the outmoded “Special Conditions.”

B. For inclusion of transitional clauses between the General Conditions and the General Requirements of the Specifications.

C. To modify and expand on the General Conditions as needed to accommodate the unique requirements of a specific project.

D. To define the insurance requirements and Liquidated Damages provisions for the project.

A
  • The main purpose of the Supplementary Conditions is:*
  • A. As the replacement document for the outmoded “Special Conditions.”*
  • B. For inclusion of transitional clauses between the General Conditions and the General Requirements of the Specifications.*
  • C. To modify and expand on the General Conditions as needed to accommodate the unique requirements of a specific project.*
  • D. To define the insurance requirements and Liquidated Damages provisions for the project.*

C. - PDPG 12.3.3.3, (318)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Project insurance requirements are located in the:

A. Agreement.

B. General Conditions.

C. General and Supplementary Conditions.

D. General Requirements.

A
  • Project insurance requirements are located in the:*
  • A. Agreement.*
  • B. General Conditions.*
  • C. General and Supplementary Conditions.*
  • D. General Requirements.*

C. - PDPG 12.3.3.3, (319) & AIA A201

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

The extent of Work to be performed by any Subcontractor or trade is established by the:

A. Specifications

B. Drawings

C. Contractor/Subcontractor agreement

D. General Conditions

A
  • The extent of Work to be performed by any Subcontractor or trade is established by the:*
  • A. Specifications*
  • B. Drawings*
  • C. Contractor/Subcontractor agreement*
  • D. General Conditions*

C. - A201/1.2.2;EJCDC 6.06 G

AIA 201 1.2.2 Organization of the Specifications into divisions, sections and articles, and arrangement of Drawings shall not control the Contractor in dividing the Work among Subcontractors or in establishing the extent of Work to be performed by any trade.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

The entity responsible for furnishing surveys describing physical characteristics, legal limits, a legal description, and utility locations for the site is the:

A. Owner.

B. Contractor.

C. Architect/Engineer.

D. County Recorder’s office where the project is located.

A
  • The entity responsible for furnishing surveys describing physical characteristics, legal limits, a legal description, and utility locations for the site is the:*
  • A. Owner.*
  • B. Contractor.*
  • C. Architect/Engineer.*
  • D. County Recorder’s office where the project is located.*

A. - A201/2.2.3; EJCDC 8.05, PDPG 5.2.3, (77)

2.2.4! The Owner shall furnish surveys describing physical characteristics, legal limitations and utility locations for the site of the Project, and a legal description of the site. The Contractor shall be entitled to rely on the accuracy of information furnished by the Owner but shall exercise proper precautions relating to the safe performance of the Work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

The right and responsibility to stop the work when the Contractor’s performance is defective lies with the:

A. Owner

B. Architect/Engineer

C. Both the Architect/Engineer and Owner

D. Neither

A
  • The right and responsibility to stop the work when the Contractor’s performance is defective lies with the:*
  • A. Owner*
  • B. Architect/Engineer*
  • C. Both the Architect/Engineer and Owner*
  • D. Neither*

A. - A201/2.3.1; EJCDC 13.05, 15.02

2.4 Owner’s Right to Stop the Work!!!! Not 2.3.1

If the Contractor fails to correct Work that is not in accordance with the requirements of the Contract Documents as required by Section 12.2 or repeatedly fails to carry out Work in accordance with the Contract Documents, the Owner may issue a written order to the Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, the right of the Owner to stop the Work shall not give rise to a duty on the part of the Owner to exercise this right for the benefit of the Contractor or any other person or entity, except to the extent required by Section 6.1.3.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

The responsibility for inspecting portions of the Work already completed to determine that they are acceptable to receive subsequent work lies with the:

A. Architect/Engineer

B. Contractor

C. Subcontractor who is performing the subsequent work.

D. Building Inspector

A
  • The responsibility for inspecting portions of the Work already completed to determine that they are acceptable to receive subsequent work lies with the:*
  • A. Architect/Engineer*
  • B. Contractor*
  • C. Subcontractor who is performing the subsequent work.*
  • D. Building Inspector*

B. - A201/3.3.3; EJCDC 6.06 D

3.3.3 The Contractor shall be responsible for inspection of portions of Work already performed to determine that such portions are in proper condition to receive subsequent Work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

The primary responsibility to ascertain that the Contract Documents are in accordance with applicable laws, statutes, ordinances, building codes, and rules and regulations lies with the:

A. Architect/Engineer.

B. Contractor.

C. Owner.

D. Building official.

A
  • The primary responsibility to ascertain that the Contract Documents are in accordance with applicable laws, statutes, ordinances, building codes, and rules and regulations lies with the:*
  • A. Architect/Engineer.*
  • B. Contractor.*
  • C. Owner.*
  • D. Building official.*

A. - A201/3.7.3; EJCDC 6.09 B

3.7.2 The Contractor shall comply with and give notices required by applicable laws, statutes, ordinances, codes, rules and regulations, and lawful orders of public authorities applicable to performance of the Work.

3.7.3 If the Contractor performs Work knowing it to be contrary to applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities, the Contractor shall assume appropriate responsibility for such Work and shall bear the costs attributable to correction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Unless otherwise stipulated, allowances cover:

A. Materials and equipment delivered.

B. Materials and equipment delivered, plus unloading and handling at the site.

C. Materials and equipment delivered, plus Contractor’s overhead and profit.

D. Materials and equipment delivered and installed

A
  • Unless otherwise stipulated, allowances cover:*
  • A. Materials and equipment delivered.*
  • B. Materials and equipment delivered, plus unloading and handling at the site.*
  • C. Materials and equipment delivered, plus Contractor’s overhead and profit.*
  • D. Materials and equipment delivered and installed*

A. - A201/3.8.2; EJCDC 11.02 A, PDPG 13.8.1, (350-351)

§ 3.8.2 Unless otherwise provided in the Contract Documents, .1allowances shall cover the cost to the Contractor of materials and equipment delivered at the site and all required taxes, less applicable trade discounts; .2 Contractor’s costs for unloading and handling at the site, labor, installation costs, overhead, profit, and other expenses contemplated for stated allowance amounts shall be included in the Contract Sum but not in the allowances; and .3 whenever costs are more than or less than allowances, the Contract Sum shall be adjusted accordingly by Change Order. The amount of the Change Order shall reflect (1) the difference between actual costs and the allowances under Section 3.8.2.1 and (2) changes in Contractor’s costs under Section 3.8.2.2.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

The purpose of shop drawings, product data, and samples is to:

A. Verify that the Contractor has read the Drawings and Specifications.

B. Provide an opportunity to propose more cost-efficient means of construction.

C. Demonstrate the way the Contractor proposes to conform to the information expressed in the Contract Documents.

D. All of the above.

A
  • The purpose of shop drawings, product data, and samples is to:*
  • A. Verify that the Contractor has read the Drawings and Specifications.*
  • B. Provide an opportunity to propose more cost-efficient means of construction.*
  • C. Demonstrate the way the Contractor proposes to conform to the information expressed in the Contract Documents.*
  • D. All of the above.*

C. - A201/3.12.4; EJCDC 6.17 E.1, PDPG 15.8, (388)

3.12.4 Shop Drawings, Product Data, Samples, and similar submittals are not Contract Documents. Their purpose is to demonstrate how the Contractor proposes to conform to the information given and the design concept expressed in the Contract Documents for those portions of the Work for which the Contract Documents require submittals. Review by the Architect is subject to the limitations of Section 4.2.7. Informational submittals upon which the Architect is not expected to take responsive action may be so identified in the Contract Documents. Submittals that are not required by the Contract Documents may be returned by the Architect without action.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

The responsibility to review and approve submittals lies with the:

A. Architect/Engineer.

B. Owner’s Representative.

C. Contractor.

D. Architect/Engineer and Contractor.

A
  • The responsibility to review and approve submittals lies with the:*
  • A. Architect/Engineer.*
  • B. Owner’s Representative.*
  • C. Contractor.*
  • D. Architect/Engineer and Contractor.*

D. - A201/3.12.5, 4.2.7; EJCDC 6.17 D

3.12.5 The Contractor shall review for compliance with the Contract Documents, approve, and submit to the Architect, Shop Drawings, Product Data, Samples, and similar submittals required by the Contract Documents, in accordance with the submittal schedule approved by the Architect or, in the absence of an approved submittal schedule, with reasonable promptness and in such sequence as to cause no delay in the Work or in the activities of the Owner or of Separate Contractors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

If a shop drawing is submitted by the Contractor and stamped “approved” by the Architect, who is responsible for any deviations from the Contract Documents shown on the shop drawing?

A. Architect/Engineer.

B. Owner.

C. Contractor.

D. Architect/Engineer and Contractor

A
  • If a shop drawing is submitted by the Contractor and stamped “approved” by the Architect, who is responsible for any deviations from the Contract Documents shown on the shop drawing?*
  • A. Architect/Engineer.*
  • B. Owner.*
  • C. Contractor.*
  • D. Architect/Engineer and Contractor*

C. - A201/3.12.8; EJCDC 6.17 E.3

A201 3.12.8 The Work shall be in accordance with approved submittals except that the Contractor shall not be relieved of responsibility for deviations from the requirements of the Contract Documents by the Architect’s approval of Shop Drawings, Product Data, Samples, or similar submittals, unless the Contractor has specifically notified the Architect of such deviation at the time of submittal and (1) the Architect has given written approval to the specific deviation as a minor change in the Work, or (2) a Change Order or Construction Change Directive has been issued authorizing the deviation. The Contractor shall not be relieved of responsibility for errors or omissions in Shop Drawings, Product Data, Samples, or similar submittals, by the Architect’s approval thereof.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

The Contractor is entitled to an extension of time for:

A. Rainy days.

B. Abnormal weather conditions.

C. Rainy days which have an adverse effect on the schedule.

D. Abnormal weather conditions that could not have been anticipated and that affected the schedule.

A
  • The Contractor is entitled to an extension of time for:*
  • A. Rainy days.*
  • B. Abnormal weather conditions.*
  • C. Rainy days which have an adverse effect on the schedule.*
  • D. Abnormal weather conditions that could not have been anticipated and that affected the schedule.*

D. - A201/4.3.7.2; EJCDC 12.03

  1. 3.1!!!!!
  2. 3.1 If the Contractor is delayed at any time in the commencement or progress of the Work by (1) an act or neglect of the Owner or Architect, of an employee of either, or of a Separate Contractor; (2) by changes ordered in the Work; (3) by labor disputes, fire, unusual delay in deliveries, unavoidable casualties, adverse weather conditions documented in accordance with Section 15.1.6.2, or other causes beyond the Contractor’s control; (4) by delay authorized by the Owner pending mediation and binding dispute resolution; or (5) by other causes that the Contractor asserts, and the Architect determines, justify delay, then the Contract Time shall be extended for such reasonable time as the Architect may determine.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Claims arising out of or related to the Contract are subject to:

A. Mediation

B. Arbitration

C. Mediation followed by arbitration

D. Arbitration followed by litigation if the parties cannot agree.

A
  • Claims arising out of or related to the Contract are subject to:*
  • A. Mediation*
  • B. Arbitration*
  • C. Mediation followed by arbitration*
  • D. Arbitration followed by litigation if the parties cannot agree.*

C. - A201/4.5.1;EJCDC 16.01

§ 15.4.1 If the parties have selected arbitration as the method for binding dispute resolution in the Agreement, any Claim subject to, but not resolved by, mediation shall be subject to arbitration which, unless the parties mutually agree otherwise, shall be administered by the American Arbitration Association in accordance with its Construction Industry Arbitration Rules in effect on the date of the Agreement. The Arbitration shall be conducted in the place where the Project is located, unless another location is mutually agreed upon. A demand for arbitration shall be made in writing, delivered to the other party to the Contract, and filed with the person or entity administering the arbitration. The party filing a notice of demand for arbitration must assert in the demand all Claims then known to that party on which arbitration is permitted to be demanded.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

All of the following are true of Change Orders EXCEPT:

A. May be initiated by either the Owner, Architect/Engineer, or Contractor.

B. Must be signed by all 3 parties to be valid.

C. May be ignored by the Contractor under legitimate objection to its terms.

D. Requires agreement on costs between the Owner and Contractor.

A
  • All of the following are true of Change Orders EXCEPT:*
  • A. May be initiated by either the Owner, Architect/Engineer, or Contractor.*
  • B. Must be signed by all 3 parties to be valid.*
  • C. May be ignored by the Contractor under legitimate objection to its terms.*
  • D. Requires agreement on costs between the Owner and Contractor.*

C. - A201/7.2.1; EJCDC 12.01, PDPG 15.11.2.3, (406)

7.1.2 A Change Order shall be based upon agreement among the Owner, Contractor, and Architect. A Construction Change Directive requires agreement by the Owner and Architect and may or may not be agreed to by the Contractor. An order for a minor change in the Work may be issued by the Architect alone.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

A Construction Change Directive (EJCDC = Work Change Directive) is best defined as:

A. A written order directing a change in the Work.

B. A directive for a change in the Work and an agreed upon change to the Contract Sum or Contract Time, or both.

C. A directive which requires Work to be performed by “Force Account”.

D. A directive to change the Work prior to agreement on the adjustment to the contract sum or time, if any.

A
  • A Construction Change Directive (EJCDC = Work Change Directive) is best defined as:*
  • A. A written order directing a change in the Work.*
  • B. A directive for a change in the Work and an agreed upon change to the Contract Sum or Contract Time, or both.*
  • C. A directive which requires Work to be performed by “Force Account”.*
  • D. A directive to change the Work prior to agreement on the adjustment to the contract sum or time, if any.*

D. - A201/7.3.1; EJCDC 1.0149, PDPG 15.11.2.2, (405)

7.3.1 A Construction Change Directive is a written order prepared by the Architect and signed by the Owner and Architect, directing a change in the Work prior to agreement on adjustment, if any, in the Contract Sum or Contract Time, or both. The Owner may by Construction Change Directive, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions, or other revisions, the Contract Sum and Contract Time being adjusted accordingly.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

A Construction Change Directive must be signed by:

A. Owner.

B. Owner and Architect/Engineer.

C. Owner and Contractor.

D. Owner, Architect/Engineer and Contractor.

A
  • A Construction Change Directive must be signed by:*
  • A. Owner.*
  • B. Owner and Architect/Engineer.*
  • C. Owner and Contractor.*
  • D. Owner, Architect/Engineer and Contractor.*

B. - A201/7.3.1; EJCDC 1.0149, PDPG 15.11.2.2, (405)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

A Change Order is best defined as: A.

A written instrument prepared by the Architect/Engineer directing a change in the Work.

B. A document prepared by the Architect/Engineer to change the Work and an agreed upon change to the Contract Sum or Contract Time, or both.

C. A directive which requires Work to be performed by “Force Account”.

D. A directive to change the Work and a proposed basis for change to the Contract sum or time, if any.

A
  • A Change Order is best defined as: A.*
  • A written instrument prepared by the Architect/Engineer directing a change in the Work.*
  • B. A document prepared by the Architect/Engineer to change the Work and an agreed upon change to the Contract Sum or Contract Time, or both.*
  • C. A directive which requires Work to be performed by “Force Account”.*
  • D. A directive to change the Work and a proposed basis for change to the Contract sum or time, if any.*

B. - A201/7.2.1; EJCDC 1.019, PDPG 15.11.2.3, (406)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

A Change Order must be signed by:

A. Architect/Engineer.

B. Owner and Architect/Engineer.

C. Owner and Contractor.

D. Owner, Architect/Engineer and Contractor.

A
  • A Change Order must be signed by:*
  • A. Architect/Engineer.*
  • B. Owner and Architect/Engineer.*
  • C. Owner and Contractor.*
  • D. Owner, Architect/Engineer and Contractor.*

D. - A201/7.2.1; EJCDC 1.019, PDPG 15.11.2.3, (406)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Minor changes in the Work for items not involving a change in cost or time to the Contract and consistent with the intent of the Contract Documents:

A. Require the consent of the Owner.

B. Can be ordered by the Architect/Engineer, and are binding on the Owner and Contractor.

C. Require the consent of the Owner and Contractor.

D. Require the Architect/Engineer to issue a Construction Change Directive.

A
  • Minor changes in the Work for items not involving a change in cost or time to the Contract and consistent with the intent of the Contract Documents:*
  • A. Require the consent of the Owner.*
  • B. Can be ordered by the Architect/Engineer, and are binding on the Owner and Contractor.*
  • C. Require the consent of the Owner and Contractor.*
  • D. Require the Architect/Engineer to issue a Construction Change Directive.*

B. - A201/7.4.1; EJCDC 1.0149, PDPG 15.11.2.1, (405)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Contract time is the time allotted from date of commencement of Work until date of:

A. Final completion.

B. Substantial completion.

C. Certification of final payment by the A/E.

D. County issuance of an occupancy permit.

A
  • Contract time is the time allotted from date of commencement of Work until date of:*
  • A. Final completion.*
  • B. Substantial completion.*
  • C. Certification of final payment by the A/E.*
  • D. County issuance of an occupancy permit.*

B. - A201/8.1.1; EJCDC 1.0143, PDPG 16.8, (434)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

The term “day” is defined as a (an):

A. Working day.

B. Calendar day.

C. 8-hour day.

D. 24-hour day.

A
  • The term “day” is defined as a (an):*
  • A. Working day.*
  • B. Calendar day.*
  • C. 8-hour day.*
  • D. 24-hour day.*

B. - A201/8.1.4; EJCDC 1.02 B, PDPG 15.6, (382)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

The document prepared by the Contractor which allocates a dollar value to various portions of the Work is called the:

A. Progress and Completion List.

B. Schedule of Values.

C. Payment Schedule.

D. Cost Breakdown.

A
  • The document prepared by the Contractor which allocates a dollar value to various portions of the Work is called the:*
  • A. Progress and Completion List.*
  • B. Schedule of Values.*
  • C. Payment Schedule.*
  • D. Cost Breakdown.*

B. - A201/9.2.1; EJCDC 2.05 B.3, PDPG 15.13.5, (417)

Where the Contract is based on a stipulated sum or Guaranteed Maximum Price, the Contractor shall submit a schedule of values to the Architect before the first Application for Payment, allocating the entire Contract Sum to the various portions of the Work. The schedule of values shall be prepared in the form, and supported by the data to substantiate its accuracy, required by the Architect. This schedule, unless objected to by the Architect, shall be used as a basis for reviewing the Contractor’s Applications for Payment. Any changes to the schedule of values shall be submitted to the Architect and supported by such data to substantiate its accuracy as the Architect may require, and unless objected to by the Architect, shall be used as a basis for reviewing the Contractor’s subsequent Applications for Payment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Unless otherwise provided by the Contract Documents, the Contractor is entitled to payment by the Owner for all of the following EXCEPT:

A. Materials furnished and installed.

B. Materials stored at the site, even though the materials are not yet installed.

C. Materials stored off the site, at a location agreed upon in writing.

D. Materials for which the Contractor has pre-paid in order to lock-in a lower price.

A
  • Unless otherwise provided by the Contract Documents, the Contractor is entitled to payment by the Owner for all of the following EXCEPT:*
  • A. Materials furnished and installed.*
  • B. Materials stored at the site, even though the materials are not yet installed.*
  • C. Materials stored off the site, at a location agreed upon in writing.*
  • D. Materials for which the Contractor has pre-paid in order to lock-in a lower price.*

D. - A201/9.3.2; EJCDC 14.02 A.1, PDPG 15.13.7, (418)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

When may the Work be occupied and utilized for its intended use?

A. Date of Substantial Completion.

B. Date of Final Completion.

C. When the building official issues an occupancy permit.

D. When the owner’s insurance company issues a certificate of insurance.

A
  • When may the Work be occupied and utilized for its intended use?*
  • A. Date of Substantial Completion.*
  • B. Date of Final Completion.*
  • C. When the building official issues an occupancy permit.*
  • D. When the owner’s insurance company issues a certificate of insurance.*

A. - A201/9.8.1; EJCDC 1.0143, PDPG 16.8, (434)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

The “Punch List” is first prepared by the:

A. Owner.

B. Architect/Engineer.

C. Contractor.

D. Owner’s jobsite inspector

A
  • The “Punch List” is first prepared by the:*
  • A. Owner.*
  • B. Architect/Engineer.*
  • C. Contractor.*
  • D. Owner’s jobsite inspector*

C. - A201/9.8.2;EJCDC 14.04 A, PDPG 16.8.1, (435)

41
Q

Contract closeout procedures:

A. Are fully covered in the General Conditions.

B. Require Architect/Engineer to prepare a punchlist of items of work to be completed or corrected, which the Contractor must perform.

C. Require Owner’s inspection for acceptance of the Work.

D. Require the Architect to inspect the Work.

A
  • Contract closeout procedures:*
  • A. Are fully covered in the General Conditions.*
  • B. Require Architect/Engineer to prepare a punchlist of items of work to be completed or corrected, which the Contractor must perform.*
  • C. Require Owner’s inspection for acceptance of the Work.*
  • D. Require the Architect to inspect the Work.*

D. - A201/9.8.3; EJCDC 14.06 A, PDPG 16.5.2, (431)

42
Q

The Architect, suspecting non-conformance, requests the Contractor to uncover an embedded column base plate connection, an inspection that was not specified. Upon inspection, the base is found to comply with the Contract Documents. Who pays the costs of uncovering, inspection, and reinstallation?

A. Architect/Engineer.

B. Owner.

C. The Architect/Engineer and Owner split the cost.

D. Contractor.

A
  • The Architect, suspecting non-conformance, requests the Contractor to uncover an embedded column base plate connection, an inspection that was not specified. Upon inspection, the base is found to comply with the Contract Documents. Who pays the costs of uncovering, inspection, and reinstallation?*
  • A. Architect/Engineer.*
  • B. Owner.*
  • C. The Architect/Engineer and Owner split the cost.*
  • D. Contractor.*

B. - A201/12.1.2; EJCDC 13.04 B

43
Q

The General Conditions requires the Contractor to correct defective work:

A. Within one year of date of Substantial Completion.

B. Within one year of date of Final Completion.

C. Within the time limits set by law.

D. Only within the time limits of any special extended warranties.

A
  • The General Conditions requires the Contractor to correct defective work:*
  • A. Within one year of date of Substantial Completion.*
  • B. Within one year of date of Final Completion.*
  • C. Within the time limits set by law.*
  • D. Only within the time limits of any special extended warranties.*

A. - A201/12.2.1; EJCDC 13.07 A, PDPG 16.9, (438)

44
Q

Tests and inspections required by laws, ordinances, or regulations:

A. Are the responsibility of the Owner’s testing laboratory.

B. Are the Contractor’s responsibility to schedule and pay for.

C. Require the approval of the Architect/Engineer.

D. May not be a requirement of the Contract Documents.

A
  • Tests and inspections required by laws, ordinances, or regulations:*
  • A. Are the responsibility of the Owner’s testing laboratory.*
  • B. Are the Contractor’s responsibility to schedule and pay for.*
  • C. Require the approval of the Architect/Engineer.*
  • D. May not be a requirement of the Contract Documents.*

B. - A201/13.5.1; EJCDC 13.03 C

45
Q

The decision on the amount of information to include in a section, (i.e., a level two, a level three, or a level four specification section), is based on all of the following reasons, EXCEPT:

A. Complexity of the project.

B. The scope of work included in the section.

C. Local trade jurisdiction.

D. Length and complexity of a section.

A
  • The decision on the amount of information to include in a section, (i.e., a level two, a level three, or a level four specification section), is based on all of the following reasons, EXCEPT:*
  • A. Complexity of the project.*
  • B. The scope of work included in the section.*
  • C. Local trade jurisdiction.*
  • D. Length and complexity of a section.*

C. - PDPG 11.3.8.4, (269)

46
Q

Specifications address the:

A. Owner and Contractor.

B. Owner, Architect/Engineer, and Contractor.

C. Contractor, subcontractors, and suppliers.

D. Contractor.

A
  • Specifications address the:*
  • A. Owner and Contractor.*
  • B. Owner, Architect/Engineer, and Contractor.*
  • C. Contractor, subcontractors, and suppliers.*
  • D. Contractor.*

D. - PDPG 11.3.8.4, (269)

47
Q

The individual specification section is responsible for defining:

A. All the work of a trade.

B. The work results for a material, product, assembly, or piece of equipment .

C. The work of one subcontractor.

D. None of the above.

A
  • The individual specification section is responsible for defining:*
  • A. All the work of a trade.*
  • B. The work results for a material, product, assembly, or piece of equipment .*
  • C. The work of one subcontractor.*
  • D. None of the above.*

B. - PDPG 11.3.8.5, (270)

48
Q

Which of the following are best designated on the drawings?

A. Locations, dimensions, sizes, specific requirements.

B. Locations, dimensions, sizes, shapes and forms.

C. Locations, dimensions, sizes, quality of materials.

D. Locations, dimensions, sizes, manufacturers and model numbers.

A
  • Which of the following are best designated on the drawings?*
  • A. Locations, dimensions, sizes, specific requirements.*
  • B. Locations, dimensions, sizes, shapes and forms.*
  • C. Locations, dimensions, sizes, quality of materials.*
  • D. Locations, dimensions, sizes, manufacturers and model numbers.*

B. - PDPG 11.2.2,(230)

49
Q

Marked-up or corrected Contract Documents that indicate changes incorporated into the work during construction are called:

A. As-built drawings.

B. Record drawings.

C. Shop drawings.

D. Contractor certified drawings.

A
  • Marked-up or corrected Contract Documents that indicate changes incorporated into the work during construction are called:*
  • A. As-built drawings.*
  • B. Record drawings.*
  • C. Shop drawings.*
  • D. Contractor certified drawings.*

B. - PDPG 11.2.4.4, (231)

50
Q

The pictorial representations of the Project such as elevations, sections, details, and diagrams are collectively referred to as:

A. Plans.

B. Contract Documents.

C. Drawings.

D. As-built drawings.

A
  • The pictorial representations of the Project such as elevations, sections, details, and diagrams are collectively referred to as:*
  • A. Plans.*
  • B. Contract Documents.*
  • C. Drawings.*
  • D. As-built drawings.*

C. - PDPG 9.4, (187), 9.13.1, (200), 9.14.1, (201), & 11.2.2, (230)

51
Q

The goal of the national EPA green building strategy is:

A. Facilitate the mainstream adoption of effective green building practices.

B. Make green building available to everyone within a generation.

C. Insure green design excellence in our nation’s business and communities.

D. Categorize information from manufacturers according to sustainable categories

A
  • The goal of the national EPA green building strategy is:*
  • A. Facilitate the mainstream adoption of effective green building practices.*
  • B. Make green building available to everyone within a generation.*
  • C. Insure green design excellence in our nation’s business and communities.*
  • D. Categorize information from manufacturers according to sustainable categories*

A. - EPA website,Green Building Basic Information

52
Q

A statement that establishes the precedence of the various documents to consider when a conflict occurs is located:

A. In the General Conditions.

B. In the Specifications.

C. In the Supplementary Conditions.

D. None of the above.

A
  • A statement that establishes the precedence of the various documents to consider when a conflict occurs is located:*
  • A. In the General Conditions.*
  • B. In the Specifications.*
  • C. In the Supplementary Conditions.*
  • D. None of the above.*

D. - AlA A201/1.2.1; EJCDC3.01

53
Q

The most important reason why proprietary product information should not be called out on the Drawings is that:

A. It requires a closed specification to limit options to a single product.

B. Acceptance of a substitute may require revision of each reference by addendum or contract modification.

C. It prevents the Owner from changing his mind.

D. The Drawings should tell the Contractor to “refer to Specifications”.

A
  • The most important reason why proprietary product information should not be called out on the Drawings is that:*
  • A. It requires a closed specification to limit options to a single product.*
  • B. Acceptance of a substitute may require revision of each reference by addendum or contract modification.*
  • C. It prevents the Owner from changing his mind.*
  • D. The Drawings should tell the Contractor to “refer to Specifications”.*

B. - PDPG 11.2.10.1, (248)

54
Q

Administrative provisions of the construction Contract are:

A. Fully specified in the Conditions of the Contract.

B. The Contractor’s responsibility and should not be specified.

C. Written in Division 01 to expand on provisions in the Conditions of the Contract.

D. Written in a manner to avoid Owner responsibilities.

A
  • Administrative provisions of the construction Contract are:*
  • A. Fully specified in the Conditions of the Contract.*
  • B. The Contractor’s responsibility and should not be specified.*
  • C. Written in Division 01 to expand on provisions in the Conditions of the Contract.*
  • D. Written in a manner to avoid Owner responsibilities.*

C. - PDPG Division 1- General Requirements, 11.3.16, (288)

55
Q

The Division 01, General Requirements are comprised mainly of:

A. Administrative requirements.

B. Project procedures.

C. Issues common to many or all sections in other Divisions.

D. All of the above.

A
  • The Division 01, General Requirements are comprised mainly of:*
  • A. Administrative requirements.*
  • B. Project procedures.*
  • C. Issues common to many or all sections in other Divisions.*
  • D. All of the above.*

D. - PDPG 11.3.16, (288)

56
Q

All of the following are part of the role of Division 01 EXCEPT:

A. Expands on the principles stated in the General Conditions.

B. Expands on the responsibilities stated in the Agreement.

C. Pertains only to the requirements stated in Part 1 - General in the individual specifications sections in other Divsions.

D. Applies to the specifications sections in other Divisions.

A
  • All of the following are part of the role of Division 01 EXCEPT:*
  • A. Expands on the principles stated in the General Conditions.*
  • B. Expands on the responsibilities stated in the Agreement.*
  • C. Pertains only to the requirements stated in Part 1 - General in the individual specifications sections in other Divsions.*
  • D. Applies to the specifications sections in other Divisions.*

C. - PDPG 11.3.16, (288)

57
Q

A listing of Owner-furnished Contractor-installed items is located in Section:

A. Part 1, General, Summary of Work.

B. Project Management and Coordination.

C. Part 2, Products, Product Requirements.

D. Part 3, Execution, Execution Requirements.

A
  • A listing of Owner-furnished Contractor-installed items is located in Section:*
  • A. Part 1, General, Summary of Work.*
  • B. Project Management and Coordination.*
  • C. Part 2, Products, Product Requirements.*
  • D. Part 3, Execution, Execution Requirements.*

C. - PDPG 11.3.8.5, (270 &271)

58
Q

Administrative procedures and descriptions for allowances and unit price work is located in:

A. Part 1 - General, Summary.

B. Division 01, Price and Payment Procedures.

C. Administrative Requirements.

D. Part 3, Execution, Execution Requirements.

A
  • Administrative procedures and descriptions for allowances and unit price work is located in:*
  • A. Part 1 - General, Summary.*
  • B. Division 01, Price and Payment Procedures.*
  • C. Administrative Requirements.*
  • D. Part 3, Execution, Execution Requirements.*

B. – PDPG 11.3.16.3, (291) [A. is also correct.]

59
Q

To be effective in communicating, it is most important that specifications be:

A. written around a specific manufacturer’s products.

B. Clear in the products required and their method of installation.

C. Clear, correct, complete, and concise.

D. Complete enough to clearly bid and build.

A
  • To be effective in communicating, it is most important that specifications be:*
  • A. written around a specific manufacturer’s products.*
  • B. Clear in the products required and their method of installation.*
  • C. Clear, correct, complete, and concise.*
  • D. Complete enough to clearly bid and build.*

C. - PDPG11.3.6, (259)

60
Q

Standard terms and abbreviations for use in construction drawings are found in:

A. GreenFormat.

B. MasterFormat.

C. CSI Uniform Drawings Standards.

D. GSA BIM Guide.

A
  • Standard terms and abbreviations for use in construction drawings are found in:*
  • A. GreenFormat.*
  • B. MasterFormat.*
  • C. CSI Uniform Drawings Standards.*
  • D. GSA BIM Guide.*

C. - PDPG 11.2.6.8, (245)

61
Q

The methods of specifying are:

A. Descriptive, proprietary, reference standard, nonrestrictive.

B. Descriptive, performance, reference standard, proprietary.

C. Descriptive, performance, nonrestrictive, proprietary.

D. Descriptive, performance, reference standard, proprietary, procurement.

A
  • The methods of specifying are:*
  • A. Descriptive, proprietary, reference standard, nonrestrictive.*
  • B. Descriptive, performance, reference standard, proprietary.*
  • C. Descriptive, performance, nonrestrictive, proprietary.*
  • D. Descriptive, performance, reference standard, proprietary, procurement.*

B. - PDPG 11.3.7, (262)

62
Q

Proprietary specifications:

A. Do not allow other manufacturers to bid the project.

B. Are a restriction of free trade, and are against the law on public bid jobs.

C. Make use of manufacturers’ trade names and model numbers.

D. Cost the Owner more for any given item.

A
  • Proprietary specifications:*
  • A. Do not allow other manufacturers to bid the project.*
  • B. Are a restriction of free trade, and are against the law on public bid jobs.*
  • C. Make use of manufacturers’ trade names and model numbers.*
  • D. Cost the Owner more for any given item.*

C. - PDPG 11.3.7.4, (263) & 11.3.14.3, (286)

63
Q

When a product is specified by referring to a reference standard:

A. Any product meeting the standard is acceptable.

B. It can create contradictions in the contract documents.

C. It generally refers to a minimum standard.

D. All of the above.

A
  • When a product is specified by referring to a reference standard:*
  • A. Any product meeting the standard is acceptable.*
  • B. It can create contradictions in the contract documents.*
  • C. It generally refers to a minimum standard.*
  • D. All of the above.*

D. - PDPG 11.3.7.3, (262)

64
Q

Which of the 4-methods of specifying plaster provides the exact materials and mix proportions?

A. Nonrestrictive.

B. Descriptive.

C. Reference Standard.

D. Performance.

A
  • Which of the 4-methods of specifying plaster provides the exact materials and mix proportions?*
  • A. Nonrestrictive.*
  • B. Descriptive.*
  • C. Reference Standard.*
  • D. Performance.*

B. - PDPG 11.3.7.1, (262)

65
Q

Performance specifications:

A. Specify the means to achieve the end result.

B. Limit an innovative manufacturer from providing an improved product.

C. Should include criteria for verifying compliance with results desired.

D. Put limitations on the methods used to achieve the required results.

A
  • Performance specifications:*
  • A. Specify the means to achieve the end result.*
  • B. Limit an innovative manufacturer from providing an improved product.*
  • C. Should include criteria for verifying compliance with results desired.*
  • D. Put limitations on the methods used to achieve the required results.*

C. - PDPG 11.3.7.2, (262)

66
Q

Major aspects to be considered in the evaluation of a product substitution are:

A. Product characteristics, installation, and maintenance.

B. Product characteristics, manufacturer, installer, and maintenance.

C. Initial and operating costs, product characteristics, and maintenance.

D. All of the above.

A
  • Major aspects to be considered in the evaluation of a product substitution are:*
  • A. Product characteristics, installation, and maintenance.*
  • B. Product characteristics, manufacturer, installer, and maintenance.*
  • C. Initial and operating costs, product characteristics, and maintenance.*
  • D. All of the above.*

D. - PDPG 15.11.3, (406)

67
Q

At the time the documents are issued for bid, what means are available to include items for which complete information is not included in the bid documents?

A. Allowances.

B. Unit prices.

C. Allowances and unit prices.

D. Allowances, alternates, and unit prices.

A
  • At the time the documents are issued for bid, what means are available to include items for which complete information is not included in the bid documents?*
  • A. Allowances.*
  • B. Unit prices.*
  • C. Allowances and unit prices.*
  • D. Allowances, alternates, and unit prices.*

C. - PDPG 13.8.1 & 13.8.3, (350 & 351)

68
Q

An Allowance:

A. Is a dollar amount that the bidder includes in the bid to cover the cost of items to be determined at a later time.

B. Is a specified quantity of a product that the bidder includes in the scope of work, even though the location is not indicated on the Drawings.

C. Must be accompanied by a unit price quote in order to equitably adjust the contract price later.

D. Can be either a dollar amount that the bidder includes in the bid, or a quantity of a product that the bidder includes in the scope of work.

A
  • An Allowance:*
  • A. Is a dollar amount that the bidder includes in the bid to cover the cost of items to be determined at a later time.*
  • B. Is a specified quantity of a product that the bidder includes in the scope of work, even though the location is not indicated on the Drawings.*
  • C. Must be accompanied by a unit price quote in order to equitably adjust the contract price later.*
  • D. Can be either a dollar amount that the bidder includes in the bid, or a quantity of a product that the bidder includes in the scope of work.*

D. - PDPG 13.8.1, (350)

69
Q

Which of the following is NOT an allowance?

A. Allow $30,000 for the furnishing of door hardware.

B. Allow for furnishing and installing of 35 each Type “L” lighting fixtures where indicated on Drawings.

C. Allow for material cost of 2,000 square feet of stone tile pavers.

D. Allow for 250 lineal feet of 8’-0” high demountable partitions.

A
  • Which of the following is NOT an allowance?*
  • A. Allow $30,000 for the furnishing of door hardware.*
  • B. Allow for furnishing and installing of 35 each Type “L” lighting fixtures where indicated on Drawings.*
  • C. Allow for material cost of 2,000 square feet of stone tile pavers.*
  • D. Allow for 250 lineal feet of 8’-0” high demountable partitions.*

B. - PDPG 13.8.1, (350)

70
Q

Unit prices are addressed in which part of the Project Manual?

A. Bid Form

B. Division 01, General Requirements

C. Technical specifications

D. All of the above

A
  • Unit prices are addressed in which part of the Project Manual?*
  • A. Bid Form*
  • B. Division 01, General Requirements*
  • C. Technical specifications*
  • D. All of the above*

D. - PDPG 13.8.3, (353)

71
Q

All of the following are true regarding unit prices EXCEPT:

A. Unit prices should not be used when lump-sum bids are requested.

B. Unit prices are useful when the nature of the work is defined, but the extent is not known.

C. Unit prices can be different for an “add” cost than for a “deduct” cost.

D. The Bid Form should include a schedule for unit prices with the A/E’s estimate of quantity.

A
  • All of the following are true regarding unit prices EXCEPT:*
  • A. Unit prices should not be used when lump-sum bids are requested.*
  • B. Unit prices are useful when the nature of the work is defined, but the extent is not known.*
  • C. Unit prices can be different for an “add” cost than for a “deduct” cost.*
  • D. The Bid Form should include a schedule for unit prices with the A/E’s estimate of quantity.*

A. - PDPG 13.8.3, (353)

72
Q

All of the following are reasons for having an Alternate Bid EXCEPT:

A. To provide latitude in project scope and cost.

B. To assure an owner that a project can be constructed within available funds.

C. To save the Architect/Engineer time while preparing construction documents.

D. To cover uncertainties in variable market conditions.

A
  • All of the following are reasons for having an Alternate Bid EXCEPT:*
  • A. To provide latitude in project scope and cost.*
  • B. To assure an owner that a project can be constructed within available funds.*
  • C. To save the Architect/Engineer time while preparing construction documents.*
  • D. To cover uncertainties in variable market conditions.*

C. - PDPG 13.8.2, (352)

73
Q

Substitutions proposed during the bidding phase of a project:

A. Allows bidders to propose products they prefer.

B. Requires additional time to evaluate the bids.

C. Allows for the introduction of a possible superior or more cost effective product than the one specified.

D. All of the above.

A
  • Substitutions proposed during the bidding phase of a project:*
  • A. Allows bidders to propose products they prefer.*
  • B. Requires additional time to evaluate the bids.*
  • C. Allows for the introduction of a possible superior or more cost effective product than the one specified.*
  • D. All of the above.*

D. - PDPG 13.4.2.7, (333) & 15.11.3, (406)

74
Q

The A/E may consider a request for a substitution during the construction phase of a project for the following reasons EXCEPT:

A. When the substituted item has been accompanied by insufficient information for the A/E to evaluate its impact on other materials.

B. If the specified item is not available when needed.

C. If substitutions are not allowed during the bidding phase.

D. In order to save the Owner money.

A
  • The A/E may consider a request for a substitution during the construction phase of a project for the following reasons EXCEPT:*
  • A. When the substituted item has been accompanied by insufficient information for the A/E to evaluate its impact on other materials.*
  • B. If the specified item is not available when needed.*
  • C. If substitutions are not allowed during the bidding phase.*
  • D. In order to save the Owner money.*

A. - PDPG 15.11.3, (406)

75
Q

All of the following statements are true regarding approved substitutions EXCEPT:

A. The General Conditions state that the A/E is the sole judge of what is acceptable as a substitute for specified items.

B. Approving a substitution has the same effect on the A/E’s liability as specifying the substituted product.

C. The Contractor is responsible for the success or failure of a substituted product

D. Modification to the Contract in the form of a Change Order will be required.

A
  • All of the following statements are true regarding approved substitutions EXCEPT:*
  • A. The General Conditions state that the A/E is the sole judge of what is acceptable as a substitute for specified items.*
  • B. Approving a substitution has the same effect on the A/E’s liability as specifying the substituted product.*
  • C. The Contractor is responsible for the success or failure of a substituted product*
  • D. Modification to the Contract in the form of a Change Order will be required.*

C. - PDPG 15.11.3.2, (406)

76
Q

The use of the terms “or equal” or “or approved equal” in project specifications is used in which method of specifying?

A. Descriptive.

B. Reference standard.

C. Performance.

D. Proprietary.

A
  • The use of the terms “or equal” or “or approved equal” in project specifications is used in which method of specifying?*
  • A. Descriptive.*
  • B. Reference standard.*
  • C. Performance.*
  • D. Proprietary.*

D. - PDPG 11.3.7.4, (263)

77
Q

A promise arising by operation of law, that something sold shall be merchantable and fit for the purpose for which the seller has reason to know that it is required is called a (an)

A. Warranty.

B. Express warranty.

C. Implied warranty.

D. Warranty of Title.

A
  • A promise arising by operation of law, that something sold shall be merchantable and fit for the purpose for which the seller has reason to know that it is required is called a (an)*
  • A. Warranty.*
  • B. Express warranty.*
  • C. Implied warranty.*
  • D. Warranty of Title.*

C. - PDPG 11.3.13.3, (284) & 16.10, (442)

78
Q

A limited warranty:

A. Can provide increased protection against product defects over a full warranty.

B. Limits the Contractor’s responsibility to repair defective work.

C. Limits a seller’s liability to less than that required under the Uniform Commercial Code.

D. Both B. & C. above.

A
  • A limited warranty:*
  • A. Can provide increased protection against product defects over a full warranty.*
  • B. Limits the Contractor’s responsibility to repair defective work.*
  • C. Limits a seller’s liability to less than that required under the Uniform Commercial Code.*
  • D. Both B. & C. above.*

The UCC governs contracts dealing with the sale of goods and, with minor variations, is the law in every state except Louisiana. The purpose of the UCC is to facilitate commerce by providing certainty and consistency in commercial transactions.

D. - PDPG 16.10.1, (442)

79
Q

All of the following are reasons for requiring a construction warranty EXCEPT:

A. To protect the Owner against faults, defects, or failures in spite of technical compliance with the terms of the contract.

B. To enforce the one-year warranty period in the general conditions.

C. To give the Owner recourse against additional parties who are not in a direct contractual relationship with the Owner.

D. To extend the manufacturer’s responsibility beyond the end of the correction period.

A
  • All of the following are reasons for requiring a construction warranty EXCEPT:*
  • A. To protect the Owner against faults, defects, or failures in spite of technical compliance with the terms of the contract.*
  • B. To enforce the one-year warranty period in the general conditions.*
  • C. To give the Owner recourse against additional parties who are not in a direct contractual relationship with the Owner.*
  • D. To extend the manufacturer’s responsibility beyond the end of the correction period.*

B. - PDPG 16.9, (440)

80
Q

All of the following are benefits to be gained from an equitable extended warranty EXCEPT:

A. Assurance that the Architect has selected the right product for its application.

B. The manufacturer’s involvement in selection of the installer.

C. The manufacturer’s involvement in the construction process.

D. Recourse when a failure occurs.

A
  • All of the following are benefits to be gained from an equitable extended warranty EXCEPT:*
  • A. Assurance that the Architect has selected the right product for its application.*
  • B. The manufacturer’s involvement in selection of the installer.*
  • C. The manufacturer’s involvement in the construction process.*
  • D. Recourse when a failure occurs.*

A. - PDPG 16.10.3.3, (443)

81
Q

Which sentence uses the preferred specification writing language?

A. Contractor shall spread adhesive with a notched trowel.

B. Spread adhesive with a notched trowel.

C. Installer should spread the adhesive with a notched trowel.

D. Adhesive shall be spread with a notched trowel.

A
  • Which sentence uses the preferred specification writing language?*
  • A. Contractor shall spread adhesive with a notched trowel.*
  • B. Spread adhesive with a notched trowel.*
  • C. Installer should spread the adhesive with a notched trowel.*
  • D. Adhesive shall be spread with a notched trowel.*

B. - PDPG 11.3.6.2, (259-261)

82
Q

Which of the following words should be capitalized in a specification?

A. Owner, Contractor, and Subcontractor.

B. Article, Paragraph, and Subparagraph.

C. General Conditions, Supplementary Conditions, and Drawings.

D. Project, Work, and Site Survey.

A
  • Which of the following words should be capitalized in a specification?*
  • A. Owner, Contractor, and Subcontractor.*
  • B. Article, Paragraph, and Subparagraph.*
  • C. General Conditions, Supplementary Conditions, and Drawings.*
  • D. Project, Work, and Site Survey.*

C. - PDPG 11.3.6.6, (260), & CSPG 2.9, (39-40)

83
Q

In order to change the bid date, it is necessary to issue a (an):

A. Addendum.

B. Change Order.

C. Construction Change Directive.

D. Memo to Bidders.

A
  • In order to change the bid date, it is necessary to issue a (an):*
  • A. Addendum.*
  • B. Change Order.*
  • C. Construction Change Directive.*
  • D. Memo to Bidders.*

A. - PDPG 13.4.2.8, (333)

84
Q

When the A/E wants to make a change in the contract documents during construction that does not involve time or money, the simplest way would be to issue a (an) :

A. Addendum.

B. Change Order.

C. Construction Change Directive.

D. Architect’s Supplemental Instruction

A
  • When the A/E wants to make a change in the contract documents during construction that does not involve time or money, the simplest way would be to issue a (an) :*
  • A. Addendum.*
  • B. Change Order.*
  • C. Construction Change Directive.*
  • D. Architect’s Supplemental Instruction*

D. - PDPG 15.11.2.1, (404)

85
Q

In the PDPG, IPD stands for:

A. Intern Development Program.

B. Integrated Project Delivery.

C. Integrated Project Document.

D. Internally Prepared Document.

A
  • In the PDPG, IPD stands for:*
  • A. Intern Development Program.*
  • B. Integrated Project Delivery.*
  • C. Integrated Project Document.*
  • D. Internally Prepared Document.*

B. PDPG 4.8, (63)

86
Q

Suggested applications for UniFormat include:

A. Preliminary Project Descriptions and Outline Specifications.

B. Preliminary cost estimates and Outline Specifications.

C. Preliminary Project Descriptions and cost estimates.

D. Preliminary Project Descriptions, preliminary cost estimates, and drawing detail filing.

A
  • Suggested applications for UniFormat include:*
  • A. Preliminary Project Descriptions and Outline Specifications.*
  • B. Preliminary cost estimates and Outline Specifications.*
  • C. Preliminary Project Descriptions and cost estimates.*
  • D. Preliminary Project Descriptions, preliminary cost estimates, and drawing detail filing.*

D. PDPG 11.3.8.3, (266)

87
Q

UniFormat is based on:

A. A four-digit numbering system.

B. A five-digit numbering system.

C. An alpha-numeric system with five levels.

D. An alpha-numeric five-digit numbering system.

A
  • UniFormat is based on:*
  • A. A four-digit numbering system.*
  • B. A five-digit numbering system.*
  • C. An alpha-numeric system with five levels.*
  • D. An alpha-numeric five-digit numbering system.*

C. PDPG 11.3.8.3, (266)

88
Q

The benefits of Integrated Project Delivery include:

A. Strategic alliances and mutual respect between owners, contractors, construction managers, architects and engineers.

B. Early involvement of trade contractors and suppliers.

C. Increasing project value and decreasing owner costs through shared information.

D. All of the above.

A
  • The benefits of Integrated Project Delivery include:*
  • A. Strategic alliances and mutual respect between owners, contractors, construction managers, architects and engineers.*
  • B. Early involvement of trade contractors and suppliers.*
  • C. Increasing project value and decreasing owner costs through shared information.*
  • D. All of the above.*

D. PDPG 4.8.4, (67)

89
Q

Applications of MasterFormat include:

A. Specification writing and product data filing.

B. Specification writing, product data filing, and construction cost classification.

C. Specification writing, product data filing, and construction market data.

D. Specification writing, product data filing, construction cost classification, and improvement in construction communication.

A
  • Applications of MasterFormat include:*
  • A. Specification writing and product data filing.*
  • B. Specification writing, product data filing, and construction cost classification.*
  • C. Specification writing, product data filing, and construction market data.*
  • D. Specification writing, product data filing, construction cost classification, and improvement in construction communication.*

D. PDPG 13.3.8.4, (266)

90
Q

Administrative requirements for project meetings are located in which MasterFormat Division 01, Section:

A. Summary

B. Project Management and Coordination

C. Quality Assurance

D. Execution Requirements

A
  • Administrative requirements for project meetings are located in which MasterFormat Division 01, Section:*
  • A. Summary*
  • B. Project Management and Coordination*
  • C. Quality Assurance*
  • D. Execution Requirements*

B. PDPG 11.3.16, (291)

91
Q

In a project with multiple prime contracts, in which section of Division 01 would you find a definition of the scope of each prime contract?

A. Summary

B. Project Management and Coordination

C. Special Procedures

D. Execution Requirements

A
  • In a project with multiple prime contracts, in which section of Division 01 would you find a definition of the scope of each prime contract?*
  • A. Summary*
  • B. Project Management and Coordination*
  • C. Special Procedures*
  • D. Execution Requirements*

A. PDPG 11.3.16, (291)

92
Q

In the MasterFormat numbering structure, Section 07 81 23 – Intumescent Mastic Fireproofing would be considered:

A. a category 3 material.

B. the last product category for which CSI assigns numbers.

C. a Level 3 section.

D. a Level 4 section.

A
  • In the MasterFormat numbering structure, Section 07 81 23 – Intumescent Mastic Fireproofing would be considered:*
  • A. a category 3 material.*
  • B. the last product category for which CSI assigns numbers.*
  • C. a Level 3 section.*
  • D. a Level 4 section.*

C. CSPG 4.2.3.3, (68-69)

93
Q

The following sentence best describes which of the following: “Integrated object based model that describes the parameters or attributes of building objects and the relationships of those objects to each other.”

A. GSA.

B. IPD.

C. GreenFormat.

D. BIM.

A
  • The following sentence best describes which of the following: “Integrated object based model that describes the parameters or attributes of building objects and the relationships of those objects to each other.”*
  • A. GSA.*
  • B. IPD.*
  • C. GreenFormat.*
  • D. BIM.*

D. PDPG 11.2.9, (247)

94
Q

Typical articles that appear in PART 1 of the SectionFormat are:

A. Summary, Submittals, Quality Control, Demonstration, Protection.

B. System Description, Project Conditions, Manufacturer’s Field Services.

C. Summary, Submittals, Quality Assurance, Field or Site Conditions.

D. Submittals, Quality Assurance, Maintenance, Schedules.

A
  • Typical articles that appear in PART 1 of the SectionFormat are:*
  • A. Summary, Submittals, Quality Control, Demonstration, Protection.*
  • B. System Description, Project Conditions, Manufacturer’s Field Services.*
  • C. Summary, Submittals, Quality Assurance, Field or Site Conditions.*
  • D. Submittals, Quality Assurance, Maintenance, Schedules.*

C. PDPG 11.3.8.5, (271) & Fig. 11.13

95
Q

The three parts of a specification section are:

A. Summary, Materials, Installation

B. General, Materials, Execution

C. General, Products, Installation

D. General, Products, Execution

A
  • The three parts of a specification section are:*
  • A. Summary, Materials, Installation*
  • B. General, Materials, Execution*
  • C. General, Products, Installation*
  • D. General, Products, Execution*

D. PDPG 11.3.8.5, (271) & Fig. 11.13

96
Q

Typical articles that appear in PART 3 of the SectionFormat are:

A. Mockups, Preparation, Installation, Warranty.

B. Examination, Application, Cleaning, Schedules.

C. Site Conditions, Preparation, Installation, System Startup.

D. Examination, Preparation, Application, Warranty.

A
  • Typical articles that appear in PART 3 of the SectionFormat are:*
  • A. Mockups, Preparation, Installation, Warranty.*
  • B. Examination, Application, Cleaning, Schedules.*
  • C. Site Conditions, Preparation, Installation, System Startup.*
  • D. Examination, Preparation, Application, Warranty.*

B. PDPG 11.3.8.5, (271) & Fig. 11.13

97
Q

Requirements for elevator field testing procedures can be found in the elevator specification section:

A. In Part 1, under Quality Assurance.

B. In Part 1, under System Startup.

C. In Part 2, under Verification of Performance.

D. In Part 3, under Field Quality Control.

A
  • Requirements for elevator field testing procedures can be found in the elevator specification section:*
  • A. In Part 1, under Quality Assurance.*
  • B. In Part 1, under System Startup.*
  • C. In Part 2, under Verification of Performance.*
  • D. In Part 3, under Field Quality Control.*

D. PDPG 11.3.8.5, (271) & Fig. 11.13

98
Q

When products are furnished or supplied by others, they should be described in the specifications as:

A. By Others.

B. By Owner.

C. Not in Contract (NIC).

D. Under other contracts.

A
  • When products are furnished or supplied by others, they should be described in the specifications as:*
  • A. By Others.*
  • B. By Owner.*
  • C. Not in Contract (NIC).*
  • D. Under other contracts.*

B. PDPG 11.3.8.5, (271) & Fig. 11.13

99
Q

The phase of the project when the documents first fix the size and character of the entire project, including architectural, structural, mechanical, and electrical systems during:

A. Planning/Pre-design

B. Schematic design

C. Design development

D. Construction documents

A

The phase of the project when the documents first fix the size and character of the entire project, including architectural, structural, mechanical, and electrical systems during:

A. Planning/Pre-design

B. Schematic design

C. Design development

D. Construction documents

Answer: C. Design development

Reference: 9.14.1 Drawings page 201

The drawings at this phase are more detailed than the schematic design drawings, but are not suitable as construction drawings. Artist’s renderings are not typically used because at this point the stakeholders and participants are familiar with the aesthetic aspects of the project design. The emphasis during this time is shifting from aesthetics to the technical aspects of the project design in anticipation of producing construction drawings.

The objective of the design development drawings is to fix and describe the size and character of the project design and will typically include drawings for the following project aspects:

  • Civil and site development
  • Architectural
  • Structural system
  • Mechanical, electrical, plumbing, and fire protection systems
  • Landscaping
  • Other aspects necessary to communicate design development information, such as access security, food service equipment, or food any of the many specialty consultants.

See also:

Special article:

“6 Phases of the Design Process” with PRINTABLE QUICK REFERENCE CARD by Laura Schneider, Schooley Caldwell’s Marketing Director and Business Development Manager. Her phases of design are different from our textbook, but the article is still helpful.