Baccara's Practice I Flashcards
Under the AIA A20I, who has the authority to stop the work, if nonconforming work fails to be corrected?
A. A/E.
B. Owner.
C. Contractor.
D. Varies As stated in Division 01 General Requirements.
E. None of the above
Under the AIA A20I, who has the authority to stop the work, if nonconforming work fails to be corrected?
A. A/E
B. Owner
C. Contractor
D. Varies as stated in Division 01 General Requirements
E. None of the above
B. Owner
AIA A20I, 2.4
2.4 Owner’s Right to Stop the Work
If the Contractor fails to correct Work that is not in accordance with the requirements of the Contract Documents as required by Section 12.2 or repeatedly fails to carry out Work in accordance with the Contract Documents, the Owner may issue a written order to the Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, the right of the Owner to stop the Work shall not give rise to a duty on the part of the Owner to exercise this right for the benefit of the Contractor or any other person or entity, except to the extent required by Section 6.1.3.
A Punch List is generated by which of the following?
A. A/E just prior to Substantial Completion.
B. The subcontractors after Substantial Completion.
C. The Owner before Substantial Completion.
D. The Contractor before Substantial Completion.
A Punch List is generated by which of the following?
A. A/E just prior to Substantial Completion.
B. The subcontractors after Substantial Completion.
C. The Owner before Substantial Completion.
D. The Contractor before Substantial Completion.
D. The Contractor before Substantial Completion.
Which of the following is a stage of the Facility Life Cycle? A. Preliminary Project Description. B. Facility Maintenance. C. Project permitting. D. Project Conception.
Which of the following is a stage of the Facility Life Cycle? A. Preliminary Project Description. B. Facility Maintenance. C. Project permitting. D. Project Conception.
B. Facility Maintenance.
D. Project Conception.
Facility Life Cycle • Project conception • Project delivery methods • Design • Construction documents • Bidding/negotiating/purchasing (procurement) • Construction • Facility management
Which of the following is not an example of zoning regulations? A. Construction type. B. Facility function. C. Parking requirement. D. Height limitations.
Which of the following is not an example of zoning regulations? A. Construction type. B. Facility function. C. Parking requirement. D. Height limitations.
A. Construction type.
Zoning
Defines the permitted and conditional uses of land by regulating the type and size of a facility, its use, its function, and the density of improvements.
Prior to BIM, the following drawings required specialized skills to produce and were used rarely in construction drawings: A. Non scaled views and plans. B. Plans and Reflected Ceiling Plans. C. Perspectives and Isometrics. D. Sections and Perspectives.
Prior to BIM, the following drawings required specialized skills to produce and were used rarely in construction drawings: A. Non scaled views and plans. B. Plans and Reflected Ceiling Plans. C. Perspectives and Isometrics. D. Sections and Perspectives.
C. Perspectives and Isometrics.
Isometric drawings - Type of drawing that shows horizontal and vertical surfaces not in perspective but equally foreshortened in all three dimensions
Perspective: Type of drawing that illustrates objects as they appear to the eye, with reference to relative distance and depth.
The written formats can each be employed for a variety of applications: The chief advantage of using standard format is:
A. A standardized numbering system
B. A standardized location within the Drawings for subject matter
C. A standardized means of organizing, storing, retrieving, and communicating an enormous body of data
D. A standardized set of contracts between owner and contractor
The written formats can each be employed for a variety of applications: The chief advantage of using standard format is:
A. A standardized numbering system
B. A standardized location within the Drawings for subject matter
C. A standardized means of organizing, storing, retrieving, and communicating an enormous body of data
D. A standardized set of contracts between owner and contractor
C. A standardized means of organizing, storing, retrieving, and communicating an enormous body of data
Limitations of the Design-Bid-Build Project Delivery Method includes which of the following:
A. Linear Sequence shortens project schedule
B. Bids may exceed budget
C. Partnering is a natural result
D. Low bids may encourage Owner changes
Limitations of the Design-Bid-Build Project Delivery Method includes which of the following:
A. Linear Sequence shortens project schedule
B. Bids may exceed budget
C. Partnering is a natural result
D. Low bids may encourage Owner changes
B. Bids may exceed budget
What written forms are used to document project decisions during schematic design and design development?
A. MasterFormat, PageFormat
B. UniFormat, PageFormat
C. Preliminary Project Descriptions, Outline specifications
D. SectionFormat, PageFormat
What written forms are used to document project decisions during schematic design and design development?
A. MasterFormat, PageFormat
B. UniFormat, PageFormat
C. Preliminary Project Descriptions, Outline specifications
D. SectionFormat, PageFormat
C. Preliminary Project Descriptions, Outline specifications
Under AIA A201, who provides property insurance covering the work: A. Contractor's Surety B. Owner C. Contractor D. Financing Agency
Under AIA A201, who provides property insurance covering the work: A. Contractor's Surety B. Owner C. Contractor D. Financing Agency
B. Owner
11.2.2 Failure to Purchase Required Property Insurance. If the Owner fails to purchase and maintain the required property insurance, with all of the coverages and in the amounts described in the Agreement or elsewhere in the Contract Documents, the Owner shall inform the Contractor in writing prior to commencement of the Work. Upon receipt of notice from the Owner, the Contractor may delay commencement of the Work and may obtain insurance that will protect the interests of the Contractor, Subcontractors, and Sub-Subcontractors in the Work. When the failure to provide coverage has been cured or resolved, the Contract Sum and Contract Time shall be equitably adjusted. In the event the Owner fails to procure coverage, the Owner waives all rights against the Contractor, Subcontractors, and Subsubcontractors to the extent the loss to the Owner would have been covered by the insurance to have been procured by the Owner. The cost of the insurance shall be charged to the Owner by a Change Order. If the Owner does not provide written notice, and the Contractor is damaged by the failure or neglect of the Owner to purchase or maintain the required insurance, the Owner shall reimburse the Contractor for all reasonable costs and damages attributable thereto.
These documents become Contract Documents when the Owner-Contractor Agreement is signed: A. Specifications B. Bid Solicitation C. Contracting Forms D. Instructions to Bidders
These documents become Contract Documents when the Owner-Contractor Agreement is signed: A. Specifications B. Bid Solicitation C. Contracting Forms D. Instructions to Bidders
A. Specifications
The special procedures used to ensure cost compliance include which of the following?:
A. Cash allowances, material allowances, quantity allowances
B. Alternates, unit prices, stipulated sums
C. Alternates, unit prices, allowances
D. Guaranteed maximum price, unit prices, design allowances
The special procedures used to ensure cost compliance include which of the following?:
A. Cash allowances, material allowances, quantity allowances
B. Alternates, unit prices, stipulated sums
C. Alternates, unit prices, allowances
D. Guaranteed maximum price, unit prices, design allowances
C. Alternates, unit prices, allowances
Types of variables may include Allowances (Cash allowance or quantity allowance), Alternate, or Unit Prices.
There are occasions when it will be necessary for the A/E to consider special procedures for certain variables in a project, including:
- Indeterminate Items, unknowns and contingencies;
- Postponement of decisions until adequate information is available;
- Flexibility and adjustment for variables;
- Identification and control of construction costs.
These procedures are used to control costs for administration of unknown of hidden conditions. Note that too many alternates, allowances, and unit prices complicated procurement and awarding activities. If undue burdens are placed on the prospective contractors, higher costs may result for the owner. Therefore these special procedures should not become a substitute for accurate and complete documents.
Guaranteed maximum prices and stipulated sums are not special procedures.
Alternates: A defined portion of work that is priced separately and thus provides an option for the owner in determining the final scope of the project. Provides the owner with a choice between different products or can define the addition or deletion of a portion of the work
Unit Price: Payment is made at a stipulated sum multiplied by the quantity completed. Used in cases where the exact extent or quantity of work cannot be calculated accurately or otherwise determined in advance of actually performing the work. Commonly used for civil engineering projects where the types of work, such as unstable soil or rock excavation, can be identified during the design of the project but the actual quantities of such work items can be only be estimated.
Stipulated sums: An agreed amount for a defined extent of work based upon complete or partially complete construction documents. This is the simplest method of stating the basis of payment wherein a single amount is agreed upon for completion of entire contract.
From PDPG:
13.10.1 Stipulated Sum
A stipulated sum is the simplest method of stating the basis of payment. Sometimes called
a lump-sum price or fixed price, a stipulated sum is a single fixed amount for a described
extent of work, based on complete or partially complete construction documents. The stipulated sum includes all costs to construct the project, including labor, materials, products,
equipment, services, and other related costs. The principal advantage to the parties to the
agreement is that the amount is clearly established in advance.
A stipulated sum contract is usually closed book contracting and the owner is not provided with any information that was developed by the contractor to arrive at the final construction price. The owner is at risk for increases in the contract sum without any understanding of what was included in the original stipulated sum that became the contract sum.
While a stipulated sum contract is common for the design-bid-build project delivery method, it is rarely used with any of the other project delivery methods. A stipulated sum contract is a common contract form for projects that were procured by the low bid or best value: total cost procurement options. Also, stipulated sum contracts are the most common form of contract between contractors and subcontractors and suppliers in all project delivery methods.
Which of the following is the principal type (business arrangement) of the Design-Build Project Delivery method?:
A. An architect and an engineer may form a joint venture and contract with an owner to provide D-B services
B. An A/E and a contractor may form a joint venture and contract with subcontractors to provide D-B services
C. An owner may contract with a contractor and then subcontract with an A/E for architectural and engineering services
D. A construction manager may contract with an A/E for D-B services, and the A/E then subcontracts with a contractor for
construction services
Which of the following is the principal type (business arrangement) of the Design-Build Project Delivery method?:
A. An architect and an engineer may form a joint venture and contract with an owner to provide D-B services
B. An A/E and a contractor may form a joint venture and contract with subcontractors to provide D-B services
C. An owner may contract with a contractor and then subcontract with an A/E for architectural and engineering services
D. A construction manager may contract with an A/E for D-B services, and the A/E then subcontracts with a contractor for
construction services
B. An A/E and a contractor may form a joint venture and contract with subcontractors to provide D-B services
The NCS is comprised of which of the following standards?: A. OmniClass B. CSI CAD Layer Guidelines C. MasterFormat D. CSI Uniform Drawing System
The NCS is comprised of which of the following standards?: A. OmniClass B. CSI CAD Layer Guidelines C. MasterFormat D. CSI Uniform Drawing System
D. CSI Uniform Drawing System
A punch list is generated by the:
A. A/E just prior to Substantial Completion
B. The Subcontractors after Substantial Completion
C. The Owner prior to Substantial Completion
D. The Contractor prior to Substantial Completion
A punch list is generated by the:
A. A/E just prior to Substantial Completion
B. The Subcontractors after Substantial Completion
C. The Owner prior to Substantial Completion
D. The Contractor prior to Substantial Completion
D. The Contractor prior to Substantial Completion
When interpreting Contract Documents, the A/E should:
A. Show no partiality to Owner or Contractor
B. Protect the client‘s best interests
C. Protect the A/E from possible liabilities
D. Achieve the original design intent of the A/E
When interpreting Contract Documents, the A/E should:
A. Show no partiality to Owner or Contractor
B. Protect the client‘s best interests
C. Protect the A/E from possible liabilities
D. Achieve the original design intent of the A/E
Show no partiality to Owner or Contractor
AIA A201, 12.1.1