Contract Dates Flashcards
Contractor to give Owner notice of cancellation or expiration of required insurance.
3 days
Owner to give Contractor notice of cancellation or expiration of required insurance.
3 days
Successful Bidder to deliver required bonds to Owner, after execution of Contract.
3 days
Architect to issue addenda, before bid date.
4 days
Contractor/Architect’s notice to Owner before disclosing confidential information.
7 days
Architect to respond to Application for Payment.
7 days
Contractor to pay subcontractor, after receiving payment from Owner.
7 days
Contractor to provide proof of payment of subcontractors, at Owner’s request.
7 days
Owner to pay Contractor, after date established in Contract Documents, if any.
7 days
Contractor’s notice to Owner and Architect of stopping Work, after failure to receive payment.
7 days
Contractor/Architect’s notice to Owner before terminating Contract for cause.
7 days
Owner’s notice to Contractor before terminating for cause.
7 days
Bidder’s deadline to submit RFIs, before bid date.
7 days
Owner to furnish reasonable evidence of financial arrangements to Bidders, upon request.
7 days
Architect to request lien rights from Owner, at Consultant’s request.
7 days
Contractor to send Application for Payment to Architect, prior to scheduled progress payment date
10 days
Bidder’s deadline to return Bid Documents to issuing office for refund of deposit, after bid date.
10 days
Bidder’s deadline to propose substitutions, before bid date.
10 days
Owner to furnish reasonable evidence of financial arrangements to Contractor, at Contractor’s request.
14 days
Contractor to report concealed or unknown conditions, after discovery.
14 days
Architect to report objections, whether by Architect or Owner, to proposed superintendent or subcontractors, or request additional time to consider.
14 days
Owner to evaluate, give notice of, or enforce mechanic’s lien rights.
15 days
Owner to furnish information necessary for Architect to evaluate, give notice of, or enforce lien rights, upon request.
15 days
Injured party to give notice of injury or damage to other party, after discovery.
21 days
Of stopped Work, at no fault of the Contractor, before Contractor may terminate the Contract.
30 days
Days of stopped Work, due to Owner non conformance, before Contractor may terminate the Contract.
60 days
Days after Substantial Completion, Construction Phase services to be compensated as Additional Services.
60 days
Cumulative days of suspended Work before Architect can terminate.
90 days