Baccara's Practice II for 10/7 Flashcards
Great Lake Region CDT Certification Quiz Part 2
All of the following are Articles in Part 3 Execution EXCEPT:
A. Examination
B. Application
C. Fabrication
D. System Startup
All of the following are Articles in Part 3 Execution EXCEPT:
A. Examination
B. Application
C. Fabrication
D. System Startup
C. Fabrication
Fabrication is a process that takes place in the manufacturing plant or fabrication shop, prior to delivery to the site. Execution takes place on the job site.
An alternate becomes part of the contract documents:
a. When the bids are opened
b. When owner makes his or her decision to accept
c. On A/E’s recommendation
d. When stipulated in the Owner/Contractor Agreement.
- An alternate becomes part of the contract documents:*
- a. When the bids are opened*
- b. When owner makes his or her decision to accept*
- c. On A/E’s recommendation*
- d. When stipulated in the Owner/Contractor Agreement.*
d. When stipulated in the Owner/Contractor Agreement
The Agreement indicates alternate(s) that are accepted. The contract sum given in the Agreement reflects the base bid plus the selected alternate(s). On certain occasions, alternates may be accepted after award and the contract sum (and possibly contract time) modified by change order.
The contractual relationship governed by the Conditions of the Contract is between:
A. Owner and contractor
B. Architect/engineer and contractor
C. Owner and Subcontractors
D. Owner, contractor, and architect/engineer
- The contractual relationship governed by the Conditions of the Contract is between:*
- A. Owner and contractor*
- B. Architect/engineer and contractor*
- C. Owner and Subcontractors*
- D. Owner, contractor, and architect/engineer*
A. Owner and contractor
The owner and the contractor are the parties to the construction contract, hence they are subject to the Conditions of the Contract. Yes, the duties of the architect are described in the Conditions of the Contract, but they are governed by the separate Owner/Architect or Owner/Engineer Agreement.
Contractual clauses in the Conditions of the Contract:
A. Have priority over Division 01
B. Are superseded by Division 01
C. Are expanded upon by the provisions of Division 01
D. Are independent, and Division 01 provisions have no effect
- Contractual clauses in the Conditions of the Contract:*
- A. Have priority over Division 01*
- B. Are superseded by Division 01*
- C. Are expanded upon by the provisions of Division 01*
- D. Are independent, and Division 01 provisions have no effect*
C. Are expanded upon by the provisions of Division 01
The key word is “expanded.” Division 01 General Requirements are detailed. They address administrative and procedural level issues. The Conditions of the Contract say: “Do this.” The General Requirements say: “Do it like this.” And don’t forget the concept of “complementary documents.” No provisions have priority over, are superseded by, or are independent of, other provisions in the contract documents - they are “complementary.”
It is important to establish the site conditions prior to:
A. Notice to Proceed
B. Mobilization
C. Negotiating Procurement
D. Signing the contract
It is important to establish the site conditions prior to:
A. Notice to Proceed
B. Mobilization
C. Negotiating Procurement
D. Signing the contract
B. Mobilization
The dollar amounts of cash allowances are:
A. In the Instructions to Bidders
B. On the Bid Form
C. In Division 01
D. In the specification sections of Division 02 through 49 that specify the product installation
- The dollar amounts of cash allowances are:*
- A. In the Instructions to Bidders*
- B. On the Bid Form*
- C. In Division 01*
- D. In the specification sections of Division 02 through 49 that specify the product installation*
C. In Division 01
To avoid duplication and possible contradiction, the single place the actual dollar amounts are given are in Division 01 Section “Allowances.” All other documents, including the bid form, refer to that location. Some AEs prefer to have allowance amounts incorporated in the bid form; great care must be taken to ensure that this does not introduce a conflict within the documents.
The following are advantages gained by using standard agreement forms except:
A. Parties’ familiarity with the forms
B. Uniformity of terminology
C. Legal precedents interpreting the documents
D. Accommodate choice from a wide variety of standard contract conditions
E. Recognized customs resulting from longtime use
- The following are advantages gained by using standard agreement forms except:*
- A. Parties’ familiarity with the forms*
- B. Uniformity of terminology*
- C. Legal precedents interpreting the documents*
- D. Accommodate choice from a wide variety of standard contract conditions*
- E. Recognized customs resulting from longtime use*
D. Accommodate choice from a wide variety of standard contract conditions
Standardized agreements forms are composed assuming the use of the related conditions of the contract document published by the same source association. In order to achieve the benefits of using standard contract forms, they must be consistently used across the body of the project’s contract forms.
The contractor should begin preparation and delivery of the preconstruction submittals after which event?
A. Bid opening
B. Notice to proceed
C. Execution of agreement
D. Preconstruction meeting
- The contractor should begin preparation and delivery of the preconstruction submittals after which event?*
- A. Bid opening*
- B. Notice to proceed*
- C. Execution of agreement*
- D. Preconstruction meeting*
B. Notice to proceed
The document named “Available Information” is part of the:
A. Instructions to Bidders
B. Contract Documents
C. Specifications
D. Procurement Requirements
E. All of the above
The document named “Available Information” is part of the:
A. Instructions to Bidders
B. Contract Documents
C. Specifications
D. Procurement Requirements
E. All of the above
D. Procurement Requirements
The “Available Information” document is a convenient location for data that is not part of the contract but may be useful to assist Bidders in understanding the project. These documents are not incorporated in the construction contract under the A201; however, some owner general conditions or supplementary conditions do incorporate bidding requirements in the construction documents, a practice that CSI strongly advises against.
Available Information (Types)
- Preliminary schedule
- Budget information
- Existing conditions
- Property survey
- Environmental assessment
- Existing material information
- Existing hazardous material information
- Geophysical data
- Geotechnical data
- Permit application requirements
What information is found within Division 02 in MasterFormat?:
A. Site Work
B. Existing Conditions
C. Equipment
D. Special Construction
- What information is found within Division 02 in MasterFormat?:*
- A. Site Work*
- B. Existing Conditions*
- C. Equipment*
- D. Special Construction*
B. Existing Conditions
If the construction budget of a 50,000 square foot project is $5 million based on $100 per square foot, it is an example of which method of preparing the budget?
A. Unit price
B. Cost per measured unit
C. Systems
D. Component cost
- If the construction budget of a 50,000 square foot project is $5 million based on $100 per square foot, it is an example of which method of preparing the budget?*
- A. Unit price*
- B. Cost per measured unit*
- C. Systems*
- D. Component cost*
B. Cost per measured unit
It is not uncommon for a Public Owner to dictate the design and construction process for the different delivery methods. Which of the following are examples of this?:
A. Which financial institutions will provide bonding for the Contractor financing
B. AHJ submittal requirements
C. How the A/Es Construction Administration and the Contractor’s Project Management will be conducted
D. How safety will be controlled on the Project site
- It is not uncommon for a Public Owner to dictate the design and construction process for the different delivery methods. Which of the following are examples of this?:*
- A. Which financial institutions will provide bonding for the Contractor financing*
- B. AHJ submittal requirements*
- C. How the A/Es Construction Administration and the Contractor’s Project Management will be conducted*
- D. How safety will be controlled on the Project site*
C. How the A/Es Construction Administration and the Contractor’s Project Management will be conducted
The Facility Manager should not be involved in project closeout because the Facility Manager is not a party to the Construction Contract:
A. True
B. False
The Facility Manager should not be involved in project closeout because the Facility Manager is not a party to the Construction Contract:
B. False
The Contractor’s Superintendent:
A. Cannot be changed without Owner’s consent
B. Communication is as binding as if given by the Contractor
C. All of the Above
D. None of the Above
- The Contractor’s Superintendent:*
- A. Cannot be changed without Owner’s consent*
- B. Communication is as binding as if given by the Contractor*
- C. All of the Above*
- D. None of the Above*
C. All of the Above
AIA A201
3.9 Superintendent
The Contractor shall employ a competent superintendent and necessary assistants who shall be in attendance at the Project site during performance of the Work. The superintendent shall represent the Contractor, and communications given to the superintendent shall be as binding as if given to the Contractor.
- 9.2 The Contractor, as soon as practicable after award of the Contract, shall notify the Owner and Architect of the name and qualifications of a proposed superintendent. Within 14 days of receipt of the information, the Architect may notify the Contractor, stating whether the Owner or the Architect (1) has reasonable objection to the proposed superintendent or (2) requires additional time for review. Failure of the Architect to provide notice within the 14-day period shall constitute notice of no reasonable objection.
- 9.3 The Contractor shall not employ a proposed superintendent to whom the Owner or Architect has made reasonable and timely objection. The Contractor shall not change the superintendent without the Owner’s consent, which shall not unreasonably be withheld or delayed.
Which of the following is not a Mobilization and startup cost?
A. Transportation
B. Installation of temporary facilities
C. Protection between stages of work
D. Royalties, licenses, and fees
- Which of the following is not a Mobilization and startup cost?*
- A. Transportation*
- B. Installation of temporary facilities*
- C. Protection between stages of work*
- D. Royalties, licenses, and fees*
D. Royalties, licenses, and fees
The responsibility of inspecting work already performed for proper condition to receive subsequent work lies with the:
A. Owner
B. A/E
C. Contractor
D. Subcontractor
The responsibility of inspecting work already performed for proper condition to receive subsequent work lies with the:
A. Owner
B. A/E
C. Contractor
D. Subcontractor
C. Contractor
AIA A201
3.3.3 The Contractor shall be responsible for inspection of portions of Work already performed to determine that such portions are in proper condition to receive subsequent Work.
Preconstruction activities begin when the contractor has received:
A. a letter of intent to award.
B. the contracting forms.
C. the project specifications.
D. a signed copy of the addenda.
- Preconstruction activities begin when the contractor has received:*
- A. a letter of intent to award.*
- B. the contracting forms.*
- C. the project specifications.*
- D. a signed copy of the addenda.*
A. a letter of intent to award.
The Design Negotiate Build (DNB) Process is more conducive to:
A. Value analysis and repricing
B. Complex negotiations
C. Protracted counter offers
D. Multiple contracts
- The Design Negotiate Build (DNB) Process is more conducive to:*
- A. Value analysis and repricing*
- B. Complex negotiations*
- C. Protracted counter offers*
- D. Multiple contracts*
A. Value analysis and repricing
Which of the following is not a document for negotiating a contract?
A. Invitation to Bid
B. Request for Proposal (RFP)
C. Drawings and Specifications
D. Other Forms and Supplements
- Which of the following is not a document for negotiating a contract?*
- A. Invitation to Bid*
- B. Request for Proposal (RFP)*
- C . Drawings and Specifications*
- D. Other Forms and Supplements*
A. Invitation to Bid
Which of the following is not a Construction Schedule Milestones?
A. Submittal approval
B. Project Delivery and Team Selection Processes
C. Procurement (Bidding/Negotiating Purchase) activities
D. Contract Completion
- Which of the following is not a Construction Schedule Milestones?*
- A. Submittal approval*
- B. Project Delivery and Team Selection Processes*
- C. Procurement (Bidding/Negotiating Purchase) activities*
- D. Contract Completion*
B. Project Delivery and Team Selection Processes
All of the following activities are associated with the Project Conception Stage except:
A. Predesign
B. Planning
C. Commissioning
D. Programming
- All of the following activities are associated with the Project Conception Stage except:*
- A. Predesign*
- B. Planning*
- C. Commissioning*
- D. Programming*
C. Commissioning
Which of the following is a Stage of the Facility Life Cycle:
A. Preliminary Project Description
B. Facility Maintenance
C. Project Permitting
D. Project Conception
Which of the following is a Stage of the Facility Life Cycle:
A. Preliminary Project Description
B. Facility Maintenance
C. Project Permitting
D. Project Conception
Under AIA A 201 and EJCDC C-700, who provides Property Insurance covering the Work?
A. Contractor’s Surety
B. Owner
C. Contractor
D. Financing Agency
E. None of the above
- Under AIA A 201 and EJCDC C-700, who provides Property Insurance covering the Work?*
- A. Contractor’s Surety*
- B. Owner*
- C. Contractor*
- D. Financing Agency*
- E. None of the above*
C. Contractor
Insurance requirements are defined in AIA Document A201, Section 11, Insurance and Bonds, and the Insurance and Bonds Exhibit.
The owner is required to carry all-risk type property insurance per Exhibit A, Section A.2.3.1. Property insurance deductibles are paid by the owner as the policy holder, not by the contractor.
Section 11.2.2 of AIA Document A201 states that if the owner fails to purchase property insurance, the contractor may delay the start of work and purchase insurance to protect their interests. In this case, the contract time and sum may be adjusted by change order. If the owner does not purchase required insurance and does not notify the contractor of this decision, the owner becomes responsible for all losses that the property insurance would have covered.
An affirmation of fact or promise made by the seller to the buyer that relates to the goods and becomes a part of the basis of the bargain creates:
A. An implied warranty
B. A full warranty
C. An express warranty
D. A guarantee
- An affirmation of fact or promise made by the seller to the buyer that relates to the goods and becomes a part of the basis of the bargain creates:*
- A. An implied warranty*
- B. A full warranty*
- C. An express warranty*
- D. A guarantee*
C. An express warranty
Which of the following is not included in typical Site Studies?
a. Environmental Issues
b. Hazardous Materials
c. Similar facilities
d. Archeological Studies
- Which of the following is not included in typical Site Studies?*
- a. Environmental Issues*
- b. Hazardous Materials*
- c. Similar facilities*
- d. Archeological Studies*
c. Similar facilities
All of Ihe following should be included in “Project/Site Conditions EXCEPT:
A. Existing conditions that alTect the application of other materials
B. Protection of materials delivered to the site
C. Limitations such as temperature or weather that affect proper installation
D. References to documents about existing structures or utilities
- All of Ihe following should be included in “Project/Site Conditions” EXCEPT:*
- A. Existing conditions that alTect the application of other materials*
- B. Protection of materials delivered to the site*
- C. Limitations such as temperature or weather that affect proper installation*
- D. References to documents about existing structures or utilities*
B. Protection of materials delivered to the site.