Clay Tiger / Paper Rabbit Quiz (Mock Exam) Flashcards
The Owner contracts with a single entity to build the project and to design it.
A. Single prime contract
B. Multiple prime contract
C. Construction management contract
D. Project management contract
E. Design-Build contract
F. Owner-Builder contract
G. Procurement contract
H. Performance contract
I. Lump Sum Contract
J. Unit Price Contract
The Owner contracts with a single entity to build the project and to design it.
E. Design-Build contract
The Owner hires an entity to oversee and administer the contract, including acting as the owner’s agent in evaluating bids and awarding contracts for all, or various parts of a project.
A. Single prime contract
B. Multiple prime contract
C. Construction management contract
D. Project management contract
E. Design-Build contract
F. Owner-Builder contract
G. Procurement contract
H. Performance contract
I. Lump Sum Contract
J. Unit Price Contract
The Owner hires an entity to oversee and administer the contract, including acting as the owner’s agent in evaluating bids and awarding contracts for all, or various parts of a project.
C. Construction management contract
Construction Management Project delivery method - Construction management services are often provided in one of two basic forms: construction manager as Contractor (CMc) sometimes known as construction manager at risk, and construction manager as adviser (CMa). CMc is effectively the Contractor and provides Contractor project management services; guarantees the cost of construction, and signs subcontracts for most or all of the construction work. CMa usually divides the project into multiple contracts for procurement and award of contracts. CMa provides management services to the Owner and usually includes consolidating applications for payment and coordination among contracts. A construction manager may also provide construction expertise, cost estimating experience, and scheduling services to the A/E during the design stage of a project. (PDPG 7.4 CCAPG 1.4.2)
The Owner serves as his own contractor to build the project, hiring various subcontractors to do portions of the work.
A. Single prime contract
B. Multiple prime contract
C. Construction management contract
D. Project management contract
E. Design-Build contract
F. Owner-Builder contract
G. Procurement contract
H. Performance contract
I. Lump Sum Contract
J. Unit Price Contract
The Owner serves as his own contractor to build the project, hiring various subcontractors to do portions of the work.
F. Owner-Builder contract
Owner-Build Project delivery method - Owners involved in aspects of contracting for every portion of a construction project. Because the Owner can act similar to a Contractor, the construction contracts are between the Owner and the specialty Contractors (subcontractors). (PDPG 7.6, CPRPG Fig. 2.1f, CPRPG 5.4.5, CPRPG Fig. 5.11)
The Owner hires an entity to coordinate the design and planning stages as well as the construction, including acting as the owner’s agent in evaluating bids and awarding contracts for all, or various parts of a project.
A. Single prime contract
B. Multiple prime contract
C. Construction management contract
D. Project management contract
E. Design-Build contract
F. Owner-Builder contract
G. Procurement contract
H. Performance contract
I. Lump Sum Contract
J. Unit Price Contract
The Owner hires an entity to coordinate the design and planning stages as well as the construction, including acting as the owner’s agent in evaluating bids and awarding contracts for all, or various parts of a project.
D. Project management contract
The Owner divides the work among several contractors and enters into a separate contract with each.
A. Single prime contract
B. Multiple prime contract
C. Construction management contract
D. Project management contract
E. Design-Build contract
F. Owner-Builder contract
G. Procurement contract
H. Performance contract
I. Lump Sum Contract
J. Unit Price Contract
The Owner divides the work among several contractors and enters into a separate contract with each.
The Owner contracts with a single entity to build the project.
A. Single prime contract
B. Multiple prime contract
C. Construction management contract
D. Project management contract
E. Design-Build contract
F. Owner-Builder contract
G. Procurement contract
H. Performance contract
I. Lump Sum Contract
J. Unit Price Contract
The Owner contracts with a single entity to build the project.
The Owner and the A/E define the Owner’s requirements for the desired results to be achieved, and the project is bid.
A. Single prime contract
B. Multiple prime contract
C. Construction management contract
D. Project management contract
E. Design-Build contract
F. Owner-Builder contract
G. Procurement contract
H. Performance contract
I. Lump Sum Contract
J. Unit Price Contract
The Owner and the A/E define the Owner’s requirements for the desired results to be achieved, and the project is bid.
H. Performance contract
____________ Has the advantage of identifying an exact construction price prior to signing the Agreement.
A. Single prime contract
B. Multiple prime contract
C. Construction management contract
D. Project management contract
E. Design-Build contract
F. Owner-Builder contract
G. Procurement contract
H. Performance contract
I. Lump Sum Contract
J. Unit Price Contract
____________ Has the advantage of identifying an exact construction price prior to signing the Agreement.
I. Lump Sum Contract
____________ Deals with the direct acquisition of materials and equipment by an Owner for the Owner’s use or for the installation in the Owner’s project.
A. Single prime contract
B. Multiple prime contract
C. Construction management contract
D. Project management contract
E. Design-Build contract
F. Owner-Builder contract
G. Procurement contract
H. Performance contract
I. Lump Sum Contract
J. Unit Price Contract
____________ Deals with the direct acquisition of materials and equipment by an Owner for the Owner’s use or for the installation in the Owner’s project.
G. Procurement contract
____________ Because the extent of work cannot be fully determined, the Work is subdivided into like items and appropriate quantities shown or stated for each item.
A. Single prime contract
B. Multiple prime contract
C. Construction management contract
D. Project management contract
E. Design-Build contract
F. Owner-Builder contract
G. Procurement contract
H. Performance contract
I. Lump Sum Contract
J. Unit Price Contract
____________ Because the extent of work cannot be fully determined, the Work is subdivided into like items and appropriate quantities shown or stated for each item.
J. Unit Price Contract
Which of the following elements should be contained within the Agreement Form?
- Identification of the Parties
- Warranty and guarantee of the Work
- Enumeration of Contract Documents
- Description of Work
A) 1,2,3
B) 2,3,4
C) 1,3,4
D) 1,2,4
Which of the following elements should be contained within the Agreement Form?
- Identification of the Parties
- Warranty and guarantee of the Work
- Enumeration of Contract Documents
- Description of Work
C) 1,3,4
Construction Contracts 101: Choosing & Completing Owner/Contractor Agreements (Youtube video)
A101-2017 free sample PDF
A101-2017 Exhibit A free sample PDF
Instructions for A101 use
For which of the following is it desirable to use standardized documents?
- Agreement
- General Conditions
- Supplementary Conditions
A) 2,3
B) 1,2,3
C) 1,3
D) 1,2
For which of the following is it desirable to use standardized documents?
- Agreement
- General Conditions
- Supplementary Conditions
D) 1,2
Supplementary conditions should be arranged…
- in the same order as related articles occur in the general conditions.
- in numerical order as established by Division 01.
- in accordance with CSI Section Format.
A) 1
B) 2
C) 3
D) 2 & 3
Supplementary conditions should be arranged…
- in the same order as related articles occur in the general conditions.
- in numerical order as established by Division 01.
- in accordance with CSI Section Format.
A) 1
You are informed that no Conditions of the Contract have been drafted for the project which you are currently specifying. You are requested to add these documents. In response you should…
A. begin drafting a set of General Conditions tailored to the specific project.
B. insert the General Conditions that were used and reviewed by the Owner’s legal counsel on the Owner’s last project.
C. explain that these are legal documents which must be written by attorneys.
D. not begin drafting of the General Conditions without the Owner’s explicit approval and guidance from Owner’s legal counsel.
You are informed that no Conditions of the Contract have been drafted for the project which you are currently specifying. You are requested to add these documents. In response you should…
D. not begin drafting of the General Conditions without the Owner’s explicit approval and guidance from Owner’s legal counsel.
During your review of the project manual you discover that some differences in terminology exist between the General Conditions and the General Requirements of the Specifications. In response you should…
A. revise the terminology in Division 01 to match that contained in the General Conditions.
B. revise the terminology in the General Conditions to match that contained in Division 01.
C. make no changes, since adjusting terminology has legal consequences which are the Owner’s responsibility and are beyond the purview of the A/E.
D. revise the terminology consistently in either Division 1 or the General Conditions.
During your review of the project manual you discover that some differences in terminology exist between the General Conditions and the General Requirements of the Specifications. In response you should…
A. revise the terminology in Division 01 to match that contained in the General Conditions.
General Conditions published by professional societies and used on a particular project should be…
A. inserted into the original Project Manual for ease of reproduction.
B. purchased in quanity and bound into each Project Manual.
C. included into the Project Manual by reference only.
D. bound separately from the Project Manual.
General Conditions published by professional societies and used on a particular project should be…
B. purchased in quanity and bound into each Project Manual.
Printing and inserting standard Supplementary Conditions is…
A. permitted only after review by the Owner’s insurance advisor.
B. recommended since standardization facilitates constructability.
C. not recommended.
D. recommended only if Owner, A/E, Contractor and building type remain unchanged from previous projects.
Printing and inserting standard Supplementary Conditions is…
C. not recommended.
Which of the following provisions are included within the general conditions in common use?
1) The Contractor shall keep the premises and surrounding area free from accumulation of waste materials caused by construction operations.
2) The Contractor shall be responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the Work.
3) Prior to commencement of Work, a preconstruction meeting will be held to discuss pro-cedures to be followed in performance of the Work.
4) The Contractor shall arrange for inspection for all Work before work is covered.
5) Division 1 (one) General Requirements of the Specifications shall govern the Work as described in all other sections of the specifications.
A) 1,2
B) 2,4
C) 2,4,5
D) 1,3,5
E) 1,4
Which of the following provisions are included within the general conditions in common use?
1) The Contractor shall keep the premises and surrounding area free from accumulation of waste materials caused by construction operations.
2) The Contractor shall be responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the Work.
3) Prior to commencement of Work, a preconstruction meeting will be held to discuss pro-cedures to be followed in performance of the Work.
4) The Contractor shall arrange for inspection for all Work before work is covered.
5) Division 1 (one) General Requirements of the Specifications shall govern the Work as described in all other sections of the specifications.
A) 1,2
AIA A201, 3.15.1: EJCDC 1910-8, 6.17
- *3.15 Cleaning Up**
- *3.15.1** The Contractor shall keep the premises and surrounding area free from accumulation of waste materials and rubbish caused by operations under the Contract. At completion of the Work, the Contractor shall remove waste materials, rubbish, the Contractor’s tools, construction equipment, machinery, and surplus materials from and about the Project.
AIA A201, 10.1.1; EJCDC 1910-8, 6.20
ARTICLE 10 PROTECTION OF PERSONS AND PROPERTY
10.1 Safety Precautions and Programs
The Contractor shall be responsible for initiating, maintaining, and supervising all safety precautions and programs connection with the performance of the Contract.
Which of the following provisions are included within the general conditions in common use?
- The Contractor shall submit a schedule indicating when during the progress of the Work submittals requiring approval, will be submitted.
- Each change order item shall be computed based upon the aggregate deductive or additive nature of the work covered by the initiating document.
- Where a conflict may occur within the Contract Documents the Specifications shall govern performance of the Work.
- Where a conflict may occur within the Contract Documents the Drawings shall govern performance of the Work.
A) 2,3
B) 1,3
C) 2,4
D) 1
E) 2
Which of the following provisions are included within the general conditions in common use?
- The Contractor shall submit a schedule indicating when during the progress of the Work submittals requiring approval, will be submitted.
- Each change order item shall be computed based upon the aggregate deductive or additive nature of the work covered by the initiating document.
- Where a conflict may occur within the Contract Documents the Specifications shall govern performance of the Work.
- Where a conflict may occur within the Contract Documents the Drawings shall govern performance of the Work.
D) 1
AIA A201, 3.10.2; EJCDC 1910-8, 2.6.2
3.10.2 The Contractor, promptly after being awarded the Contract and thereafter as necessary to maintain a current submittal schedule, shall submit a submittal schedule for the Architect’s approval. The Architect’s approval shall not be unreasonably delayed or withheld. The submittal schedule shall ( 1 ) be coordinated with the Contractor’s construction schedule, and (2) allow the Architect reasonable time to review submittals. If the Contractor fails to submit a submittal schedule, or fails to provide submittals in accordance with the approved submittal schedule, the Contractor shall not be entitled to any increase in Contract Sum or extension of Contract Time based on the time required for review of submittals.
Secure and pay for the building permit.
A = Architect/Engineer. B = Owner. C = Contractor. D = Architect/Engineer and Owner.
Secure and pay for the building permit.
C = Contractor.
AIA A201, 3.7.1; EJCDC 6.13
3.7.1 Unless otherwise provided in the Contract Documents, the Contractor shall secure and pay for the building permit as well as for other permits, fees, licenses, and inspections by government agencies necessary for proper execution and completion of the Work that are customarily secured after execution of the Contract and legally required at the time bids are received or negotiations concluded.
Purchase and maintain property insurance.
A = Architect/Engineer. B = Owner. C = Contractor. D = Architect/Engineer and Owner.
Purchase and maintain property insurance.
B = Owner.
AIA A201, 11.2; EJCDC 5.6
11.2.2 Failure to Purchase Required Property Insurance. If the Owner fails to purchase and maintain the required property insurance, with all of the coverages and in the amounts described in the Agreement or elsewhere in the Contract Documents, the Owner shall inform the Contractor in writing prior to commencement of the Work. Upon receipt of notice from the Owner, the Contractor may delay commencement of the Work and may obtain insurance that will protect the interests of the Contractor, Subcontractors, and Sub-Subcontractors in the Work. When the failure to provide coverage has been cured or resolved, the Contract Sum and Contract Time shall be equitably adjusted. In the event the Owner fails to procure coverage, the Owner waives all rights against the Contractor, Subcontractors, and Sub- subcontractors to the extent the loss to the Owner would have been covered by the insurance to have been procured by the Owner. The cost of the insurance shall be charged to the Owner by a Change Order. If the Owner does not provide written notice, and the Contractor is damaged by the failure or neglect of the Owner to purchase or maintain the required insurance, the Owner shall reimburse the Contractor for all reasonable costs and damages attributable thereto.
Determine dates of substantial completion and final completion.
A = Architect/Engineer. B = Owner. C = Contractor. D = Architect/Engineer and Owner.
Determine dates of substantial completion and final completion.
A = Architect/Engineer.
AIA A201, 4.2.9; EJCDC 14.8, 14.11
4.2.9 The Architect will conduct inspections to determine the date or dates of Substantial Completion and the date of final completion; issue Certificates of Substantial Completion pursuant to Section 9.8; receive and forward to the Owner, for the Owner’s review and records, written warranties and related documents required by the Contract and assembled by the Contractor pursuant to Section 9.10; and issue a final Certificate for Payment pursuant to Section 9.10.
Use the following information to answer the next 2 questions: The following items need to be incorporated into the addendum:
- Drawing A-2, which was previously issued as part of Addendum No.1, must be revised and reissued to reflect the removal of additional ceramic tile in some areas.
- The following note must be added to electrical Drawing Sheet E-4:
“On partial 2nd Floor Plan, connect exhaust fan EF-3 to existing panel #12AA, circuit #10.” - Add the following to Section 01 11 00 - Summary of Work, page 4, Article 1.07:
“J. Removal of debris shall be done daily, 2:00pm to 4:00pm. Transport material in tightly sealed clean containers to protect occupied areas.”
- Change the date bids are to be opened to March 28th.
- Add the following sentence to the General Conditions, Article 8.2 Progress and Completion: “8.2.4 Upon completion of Work, Contractor shall deliver to Architect all required Certificates of Inspection.”
- Section 22 42 00, page 6, paragraph 2.03B.1.a.: revise sink size from 16” x 16” x 12” deep to 16” x 18” x 12” deep.
The items to be incorporated into the body of the addendum should be organized into the following order:
A. 1, 4, 5, 3, 6, 2.
B. 4, 5, 3, 6, 1, 2.
C. 1, 4, 5, 2, 3, 6.
D. 4, 5, 1, 2, 3, 6.
Use the following information to answer the next 2 questions: The following items need to be incorporated into the addendum:
- Drawing A-2, which was previously issued as part of Addendum No.1, must be revised and reissued to reflect the removal of additional ceramic tile in some areas.
- The following note must be added to electrical Drawing Sheet E-4:
“On partial 2nd Floor Plan, connect exhaust fan EF-3 to existing panel #12AA, circuit #10.” - Add the following to Section 01 11 00 - Summary of Work, page 4, Article 1.07:
“J. Removal of debris shall be done daily, 2:00pm to 4:00pm. Transport material in tightly sealed clean containers to protect occupied areas.”
- Change the date bids are to be opened to March 28th.
- Add the following sentence to the General Conditions, Article 8.2 Progress and Completion: “8.2.4 Upon completion of Work, Contractor shall deliver to Architect all required Certificates of Inspection.”
- Section 22 42 00, page 6, paragraph 2.03B.1.a.: revise sink size from 16” x 16” x 12” deep to 16” x 18” x 12” deep.
The items to be incorporated into the body of the addendum should be organized into the following order:
A. 1, 4, 5, 3, 6, 2.
- Section 22 42 00, page 6, paragraph 2.03B.1.a.: revise sink size from 16” x 16” x 12” deep to 16” x 18” x 12” deep.
A. is acceptable as written.
B. should be rewritten to read as follows:
Section 22 42 00, Paragraph 2.03B.1.a.: “Revise sink size from 16 x 16 x 12 inches deep to 16 x 18 x 12 inches deep.”
C. should be rewritten to read as follows:
Section 15400, Subparagraph 2.03B.1.a.: Revise to read as follows: “…16 by 18 by 12-inches deep.”
D. should be deleted from the specifications and the Contractor should be referred to the drawings for sizes.
E. should not be included in the Addendum. This can be picked up as a clarification after the project is bid.
- Section 22 42 00, page 6, paragraph 2.03B.1.a.: revise sink size from 16” x 16” x 12” deep to 16” x 18” x 12” deep.
C. should be rewritten to read as follows:
Section 15400, Subparagraph 2.03B.1.a.: Revise to read as follows: “…16 by 18 by 12-inches deep.”
Which of the following is not a reason for issuing addenda:
A. Clarify questions raised by bidders.
B. Make changes to the Work when cost of change cannot be agreed upon.
C. Issue new requirements, including changes to the scope of Work.
D. Correct errors or omissions in the bidding documents
Which of the following is not a reason for issuing addenda:
B. Make changes to the Work when cost of change cannot be agreed upon.
All of the following are reasons for an A/E to consider requests for substitutions during the bidding phase of a project EXCEPT:
A. To encourage a more open and competitive bidding process.
B. To allow bidders to propose products they prefer.
C. To allow for the introduction of a possible superior or more cost effective product than the one specified.
D. To allow the owner additional product options.
All of the following are reasons for an A/E to consider requests for substitutions during the bidding phase of a project EXCEPT:
D. To allow the owner additional product options.
The use of the terms “or equal” or “or approved equal” in project specifications is usually used with which method of specifying?
A. Nonrestrictive.
B. Descriptive.
C. Performance.
D. Proprietary.
E. Prescriptive.
The use of the terms “or equal” or “or approved equal” in project specifications is usually used with which method of specifying?
D. Proprietary.
Proprietary. Specifies actual brand names, model numbers, and other proprietary information. A proprietary specification describes products and materials by manufacturer’s name, brand name, model number, or unique characteristic. Closed proprietary specifications do not allow for substitutions, but open proprietary specifications allow for alternative products.
Which of the following documents should be used to advise bidders whether or not the Owner is prepared to consider additional products that fulfill the same functions as the specified item?
A. Agreement
B. General Conditions
C. Invitation to Bid
D. Instructions to Bidders
E. Section 01 63 00 - Product Options and Substitutions
Which of the following documents should be used to advise bidders whether or not the Owner is prepared to consider additional products that fulfill the same functions as the specified item?
The Contractor submits only shop drawings, substituting an elevator for an elevator specified by the open-proprietary method. No product literature was submitted as required by the Specifications. The Contractor is still within the 35 day time period allowed for substitutions. The A/E should:
A. evaluate the submittal and return it to the contractor.
B. reject the submittal with no comment.
C. reject the submittal with a comment to resubmit the specified product.
D. return the submittal with a comment to resubmit the item with complete data.
E. None of the above.
The Contractor submits only shop drawings, substituting an elevator for an elevator specified by the open-proprietary method. No product literature was submitted as required by the Specifications. The Contractor is still within the 35 day time period allowed for substitutions. The A/E should:
D. return the submittal with a comment to resubmit the item with complete data.
A Work Change Directive/Construction Change Directive is ….
A. used to direct the Contractor to perform Work when the Owner and Architect assert that the Work is included in the Contract but the Contractor disagrees.
B. used by the Architect/Engineer to order changes in the Work which do not effect the Contract Amount/Price.
C. signed by the Owner, Architect and Contractor; stipulating a change in the Work but agreeing to detemine the adjustment to Contract Time and Amount/Price at some later date.
D. used only to change the Work and Contract Time but never the Contract Amount/Price.
E. Evidence that the Owner and Architect/Engineer expect the change in Work, to be incorporated in a subsequently issued change order.
A Work Change Directive/Construction Change Directive is ….
E. Evidence that the Owner and Architect/Engineer expect the change in Work, to be incorporated in a subsequently issued change order.
AIA A201, 7.3.2; EJCDC 1910-8; 1.44
An AIA order for “Minor Change in the Work” or an EJCDC “Field Order”:
A. Must be agreed to by the Contractor.
B. Must be agreed to by the Owner.
C. are binding on the Owner and Contractor.
D. must be followed up by a change order.
An AIA order for “Minor Change in the Work” or an EJCDC “Field Order”:
C. are binding on the Owner and Contractor.
EJCDC 1.19
For a Project documented by both Drawings and Specifications, having 2 types of pavement, but only 1 type of unit paver and this paver is fabricated from brick, the recommended description on the Drawings for the unit paver is:
A. Pavement
B. Unit Pavers
C. Brick Pavers
D. Red Brick Pavers
E. Red Brick Pavers as manufactured by U.S. Paver, Inc.
For a Project documented by both Drawings and Specifications, having 2 types of pavement, but only 1 type of unit paver and this paver is fabricated from brick, the recommended description on the Drawings for the unit paver is:
B. Unit Pavers
_______________ Establishes conditions under which Owner’s right to stop the Work may be exercised.
A. General Conditions
B. Supplementary Conditions
C. Division One
D. The Agreement
_______________ Establishes conditions under which Owner’s right to stop the Work may be exercised.
A. General Conditions
AIA 201, 14.3; EJCDC 15.1
14.3 Suspension by the Owner for Convenience
- 3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work, in whole or in part for such period of time as the Owner may determine.
- 3.2 The Contract Sum and Contract Time shall be adjusted for increases in the cost and time caused by suspension, delay, or interruption under Section 14.3.1. Adjustment of the Contract Sum shall include profit. No adjustment shall be made to the extent
.1 that performance is, was, or would have been, so suspended, delayed, or interrupted, by another cause for which the Contractor is responsible; or
.2 that an equitable adjustment is made or denied under another provision of the Contract.
_______________ Describes subcontractural relationships.
A. General Conditions
B. Supplementary Conditions
C. Division One
D. The Agreement
_______________ Describes subcontractural relationships.
A. General Conditions
AIA 201 5.3; EJCDC 1.37
5.3 Subcontractual Relations
By appropriate written agreement, the Contractor shall require each Subcontractor, to the extent of the Work to be performed by the Subcontractor, to be bound to the Contractor by terms of the Contract Documents, and to assume toward the Contractor all the obligations and responsibilities, including the responsibility for safety of the Subcontractor’s Work that the Contractor, by these Contract Documents, assumes toward the Owner and Architect. Each subcontract agreement shall preserve and protect the rights of the Owner and Architect under the Contract Documents with respect to the Work to be performed by the Subcontractor so that subcontracting thereof will not prejudice such rights, and shall allow to the Subcontractor, unless specifically provided otherwise in the subcontract agreement, the benefit of all rights, remedies, and redress against the Contractor that the Contractor, by the Contract Documents, has against the Owner. Where appropriate, the Contractor shall require each Subcontractor to enter into similar agreements with Sub-subcontractors. The Contractor shall make available to each proposed Subcontractor, prior to the execution of the subcontract agreement, copies of the Contract Documents to which the Subcontractor will be bound, and, upon written request of the Subcontractor, identify to the Subcontractor terms and conditions of the proposed subcontract agreement that may be at variance with the Contract Documents. Subcontractors will similarly make copies of applicable portions of such documents available to their respective proposed Sub-subcontractors.
_______________ Establishes the monthly due date for progress payments
A. General Conditions
B. Supplementary Conditions
C. Division One
D. The Agreement
_______________ Establishes the monthly due date for progress payments
D. The Agreement
_______________ Administratively governs the specification sections.
A. General Conditions
B. Supplementary Conditions
C. Division One
D. The Agreement
_______________ Administratively governs the specification sections.
C. Division One
_______________ Specifies amounts of insurance coverage.
A. General Conditions
B. Supplementary Conditions
C. Division One
D. The Agreement
_______________ Specifies amounts of insurance coverage.
B. Supplementary Conditions
No longer true.
In A201-2017, the majority of negotiated insurance provisions have been included in an exhibit to the Owner-Contractor and Owner-Construction Manager as Constructor Agreements. This new exhibit provides for required and optional insurance coverages that the Project participants may tailor to the specific needs of the Project.
_______________ Specifies time of performance.
A. General Conditions
B. Supplementary Conditions
C. Division One
D. The Agreement
_______________ Specifies time of performance.
D. The Agreement
Period of Performance means the period between the project start and end dates as specified in the executed grant agreement.
_______________ States liquidated damage amounts.
A. General Conditions
B. Supplementary Conditions
C. Division One
D. The Agreement
_______________ States liquidated damage amounts.
D. The Agreement
_______________ States Contract Sum.
A. General Conditions
B. Supplementary Conditions
C. Division One
D. The Agreement
_______________ States Contract Sum.
D. The Agreement
_______________ Establishes procedures for resolution of claims.
A. General Conditions
B. Supplementary Conditions
C. Division One
D. The Agreement
_______________ Establishes procedures for resolution of claims.
A. General Conditions
AIA 201 15; EJCDC 16
_______________ Specifies grounds for termination of the Contract.
A. General Conditions
B. Supplementary Conditions
C. Division One
D. The Agreement
_______________ Specifies grounds for termination of the Contract.
A. General Conditions
AIA 201 14.1 & .2; EJCDC 15.2, 15.4-.5
Match the following items with the appropriate construction document where that item would be located.
The cost of an alternate.
A. Bid Form
B. Agreement
C. Supplementary Conditions
D. Division 01 - General Requirements
E. Divisions 02 - 49 specifications
F. Drawings
Match the following items with the appropriate construction document where that item would be located.
The cost of an alternate.
A. Bid Form
Match the following items with the appropriate construction document where that item would be located.
Brief description of an alternate.
A. Bid Form
B. Agreement
C. Supplementary Conditions
D. Division 01 - General Requirements
E. Divisions 02 - 49 specifications
F. Drawings
Match the following items with the appropriate construction document where that item would be located.
Brief description of an alternate.
Match the following items with the appropriate construction document where that item would be located.
The location of an alternate.
A. Bid Form
B. Agreement
C. Supplementary Conditions
D. Division 01 - General Requirements
E. Divisions 02 - 49 specifications
F. Drawings
Match the following items with the appropriate construction document where that item would be located.
The location of an alternate.
F. Drawings
Match the following items with the appropriate construction document where that item would be located.
Time for completion of alternate work.
A. Bid Form
B. Agreement
C. Supplementary Conditions
D. Division 01 - General Requirements
E. Divisions 02 - 49 specifications
F. Drawings
Match the following items with the appropriate construction document where that item would be located.
Time for completion of alternate work.
B. Agreement
Match the following items with the appropriate construction document where that item would be located.
Product description of an alternate.
A. Bid Form
B. Agreement
C. Supplementary Conditions
D. Division 01 - General Requirements
E. Divisions 02 - 49 specifications
F. Drawings
Match the following items with the appropriate construction document where that item would be located.
Product description of an alternate.
E. Divisions 02 - 49 specifications
Match the following items with the appropriate construction document where that item would be located.
Routing of underground piping.
A. Bid Form
B. Agreement
C. Supplementary Conditions
D. Division 01 - General Requirements
E. Divisions 02 - 49 specifications
F. Drawings
Match the following items with the appropriate construction document where that item would be located.
Routing of underground piping.
F. Drawings
Match the following items with the appropriate construction document where that item would be located.
Requirement for separation construction debris.
A. Bid Form
B. Agreement
C. Supplementary Conditions
D. Division 01 - General Requirements
E. Divisions 02 - 49 specifications
F. Drawings
Match the following items with the appropriate construction document where that item would be located.
Requirement for separation construction debris.
D. Division 01 - General Requirements
Match the following items with the appropriate construction document where that item would be located.
Acknowledgment that existing site conditions have been verified.
A. Bid Form
B. Agreement
C. Supplementary Conditions
D. Division 01 - General Requirements
E. Divisions 02 - 49 specifications
F. Drawings
Match the following items with the appropriate construction document where that item would be located.
Acknowledgment that existing site conditions have been verified.
A. Bid Form
Match the following items with the appropriate construction document where that item would be located.
Nailing pattern for shear walls.
A. Bid Form
B. Agreement
C. Supplementary Conditions
D. Division 01 - General Requirements
E. Divisions 02 - 49 specifications
F. Drawings
Match the following items with the appropriate construction document where that item would be located.
Nailing pattern for shear walls.
F. Drawings
Match the following items with the appropriate construction document where that item would be located.
Number of roofing plies.
A. Bid Form
B. Agreement
C. Supplementary Conditions
D. Division 01 - General Requirements
E. Divisions 02 - 49 specifications
F. Drawings
Match the following items with the appropriate construction document where that item would be located.
Number of roofing plies.
E. Divisions 02 - 49 specifications
All of the following are true of UniFormat EXCEPT:
A. It is a classification system for construction information based on elements and systems.
B. It is intended for use before particular materials and installation methods are selected.
C. It classifies data associated with performance and life cycle costs of completed projects.
D. It is applicable to all types of construction projects.
All of the following are true of UniFormat EXCEPT:
C. It classifies data associated with performance and life cycle costs of completed projects.
UniFormat, p. 8
All of the following are appropriate applications for UniFormat EXCEPT:
A. Preliminary project descriptions.
B. Preliminary cost classifications.
C. Preliminary materials and methods descriptions.
D. Detail filing.
All of the following are appropriate applications for UniFormat EXCEPT:
C. Preliminary materials and methods descriptions.
UniFormat, p. 13