World Project Controller Flashcards

1
Q

A WPC must be implemented when… at least one criteria of (3) is fulfilled

A

1) Complexity - at least two entities
2) A or B Project
3) Risks - technical and/or financial

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Project is within NCM scope when the following criteria are fulfilled cumulatively (4)

A

1) A, B, C Project
2) project has on+off parts
3) executed in country of RU
4) BU is substantial contributor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

WPC, Major topics PACT Workshop

A

1) OEC
2) Risk and Opp analysis
3) Consortium agreement
4) Root cause approach
5) Applicable controlling and accounting procedure
6) Information has to be provided by RU to WPC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

THOP Costs - who pays extra?
1) Hourly Rate increase
2) Duration Extension

A

Depending on Responsibility Split / Root Cause default:
1) RU
2) BU

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Internal Dispute Settlement - Who takes additional costs into account near closing when no resolution could be found yet?

A

BU as the entity providing the WPC - then Root Cause Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What if the RU profit becomes negative but the overall profit is still positive? Provision for onerous contracts?

A

Not per IFRS, RU needs to check if it has to create one per local GAAP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

True or False - if the customer claims the delay the WPC needs to follow up claim settlement payments

A

True. Each entity needs to follow up, however - the WPC has to monitor the claim situation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly