Price Escalation in Project Business Flashcards

1
Q

Aims of Price escalation clauses?

A

Avoid negative influences from cost fluctuations + share risks with customer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Indexation - Timing

A

Base timeline should be time of bid submission

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Price escalation - basic principle seller buyer

A

Seller: As variable as possible
Buyer: As fixed as possible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Price escalation - threshold / ceiling

A

Threshold: Price increase below cannot be considered / Ceiling: Price increases above not considered

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which Consumer Price index have to be used (country)

A

The ones from the producing country

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Price Formula from customer contract impact…

A

planned revenue

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Price formula from supplier contracts impact…

A

Total planned costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Checklist for the consideration of price increase in total planned revenue (4)

A

1) Only use current and valid indices issued by public authorities
2) Do not consider potential future trends
3) Do not consider price increases until threshold is achieved or exceeded
4) Consider price increase if the outcome of price formula can be calculated based on contractually defined points

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Compensation Rate - calculation

A

Expected price increase on the rev side / expected price increase on cost side

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Order Entry Price Calculation - Preconditions (2)

A

1) Price increase based on contractually defined point in time
2) It is highly probable that the calculated price factor will be at least sustainable till final payment - apply current price factor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When do price increases on the cost side have to be taken into account?

A

Immediately if there is no enforceable price escalation clause on the revenue side

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Parallel approach - definition

A

In case of an enforceable price escalation clause on the revenue side, the consideration of the planned costs takes place in period of price increases on the revenue and not immediately - requires documentation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

True or False - If specific conditions are fulfilled, the total planned revenue can be adjusted even though contractually defined points in time for the price escalation have not been reached yet.

A

True, it may be appropriate to increase total planned revenue to a certain amount even though contractually agreed point in time have not been reached. This is only admissible when: 1) Application of price escalation clause has to be contractually agreed 2) Indices used in the formula had an increasing trend in the past and based on the trend it’s highly probable that a negative turn will not occur

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

True or False - It is allowed to provide evidence that price increases on the cost side will be compensated by price increases on the revenue side within the Limits of Authority (LoA) process.

A

True, Consideration of price increases on the cost side requires documentation that price increases on the cost side will be at least largely compensated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Important clause index re-evaluation

A

To anticipate future rebasing by the publishing authorities, clause for re-evaluation has to be included in future bids and orders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly