Contract and Claim Management Flashcards
Successful Claim - Basis (4)
1) Event
2) Legal Basis
3) Evidence
4) Enforcement
Sales, General Contract Management Steps (4)
1) Analysis of contract and spec
2) Commenting
3) Contract Negotiation
4) Finalization
Claim Strategy- 3
Set at the beginning of a project.
1) Active
2) Defensive
3) Preventive
Claim Handling - 5 steps
1) Identification - notification
2) Analysis
3) Decision
4) Announcement
5) Enforcement
Treatment of Claim - Textbook (costs/rev)
Costs: Costs attributable to claim before contractual agreement have been made - treated as progress relevant cost
Rev: Only when agreement reached
Treatment of supplier claim
Additional costs = increase plancost
Agreement reached = Receivable of costs / reduction of progress relevant costs + reduction in plan cost