Works Progress & Quality Management Flashcards

1
Q

What is the role of a Clerk of Works?

A

To inspect the workmanship, quality and safety of work on site and report back to the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How would you assess project progress?

A

I would conduct a site visit and compare the status of works on site with the contractors construction programme.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How would you assess project quality?

A

I would compare the finished works with the products detailed with the specification and the manufacturers installation requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What would you do if an alternative product was suggested by a Contractor?

A

I would review the manufacturers information regarding both products and assess the time cost or quality implication of using the alternative product. I would also ensure that the alternative product achieves the same performance or safety standard as a minimum.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When producing a Progress Report, what information would you include?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Why is it important to monitor works progress & quality?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How regularly should site visits be undertaken?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How would you undertake a progress inspection on site?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What action can the Client take if the Contractor does not achieve Practical Completion on time?

A

They can make a claim for liquidated damages, as outlined within the construction contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What might be used to demonstrate a construction programme?

A

A Gantt chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What would typically be discussed during a Pre-Start Meeting?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the three main deliverables you would consider when inspecting a site?

A

1) Cost
2) Time
3) Quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What options are available if the project is falling significantly behind programme?

A

Acceleration, as outlined within the construction contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

To what standard should construction works be conducted?

A

Building works must comply with Building Regulations and should comply with relevant British Standards.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What’s required to carry out a site inspection, and the importance
of recording progress of works

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The requirements of recording progress, and comparing to project
phase

A
17
Q

The requirements for quality descriptors as set out in the contract
documentation

A

terms such as “good standard” are subjective.

18
Q

The differences between the duties of a CA and those of a person
appointed solely to report on progress and quality issues.

A
19
Q

Carry out inspections of works being completed on site, and
prepare the necessary reports showing progress and quality
issues that have arisen

A

give example of when

20
Q

Prepare reports for clients detailing the effects of additional
instructions, amendments to specifications, and the likely effect
on progress

A

give example of when

21
Q

Record for in-house and external purposes reports on quality of
works on site, including any works rejected, and the reasons for
doing so

A

give example of when

22
Q

Compare progress of construction works at any stage of the
works against the contract programme, or status of current
gross financial valuation to original projections/cash flow.

A

give example of when