Contract Administration Flashcards
What is a contract?
An agreement between two or more parties by which they confer personal rights and impose personal obligations on one another.
What is the difference between Assignment and Novation?
An assignment transfers the benefit of a contract from one party to another, but only the benefit, not the burden. In contrast, a novation will transfer both the benefit and the burden of a contract from one party to another.
What elements form a contract?
Offer, Acceptance, Intent, Consideration.
What is a Latent Defect?
Latent defects are defects that are not apparent at the time of completion but which subsequently become apparent months or years later.
What is a Patent Defect?
What is the role of a Contract Administrator?
To impartially administer the contract terms between the Employer and the Contractor.
How does the role of Contract Administrator differ to that of an Employer’s Agent?
Contract admin - impartial admin of the contract
Employer’s agent - act exclusively in the interests of the employer
What are some of the key tasks undertaken by the Contract Administrator?
- 1) Chairing meetings, specifically the pre-start meeting
- 2) Periodically inspecting the works
- 3) Giving instruction regarding variations or changes
- 4) Authorising interim payments to the contractor
- 5) Certifying the date of completion
- 6) Settling the adjusted contract sum (final account)
- 7) Determining any applications for extensions of time by the Contractor
Does the role of Contract Administrator include design responsibilities?
No, however the appointed contract administrator can undertake design responsibilities by separate arrangement.
What is a Relevant Event?
What is a Relevant Matter?
What is a Letter of Intent?
This is a document often used as an ‘interim’ contract to allow the contractor to proceed before the full contract is signed. These can be used to provide an early start but to prevent future issues you should ensure they contain all relevant information linked to the form of contract to be used.
What are the three key documents which cover contract administration?
RICS Appropriate Contract Selection Guidance Note
JCT Guide on deciding on the appropriate JCT contract 2016
RICS contract administration Guidance Note
How are disputes handled between contractual parties?
All recognised forms of contract contain a specific ‘Dispute resolution’ method in the event of a dispute between the client and the principal contractor which both parties agree to by signing the contract.
When does the role of a Contract Administrator technically commence?
The Contract administrator’s role does not technically commence until the ‘post contract’ delivery phase of the project, i.e RIBA stages 5,6 and 7.
What are some issues with verbal agreements between parties?
Verbal agreements are unprofessional and risky as there is no evidence of what has been agreed. These should be avoided at all costs.
What are the two most common payment types within a contract?
Lump Sum
Cost Reimbursement
What is a lump sum payment?
Where a figure is agreed between parties typically after tendering the works to multiple contractors. This sum can change though.
What is a cost reimbursement payment?
This is where the contractor is paid for the actual cost of work carried out plus an agreed percentage of profit.
Can you name some suites of contract?
JCT
FIDIC
NEC
What does JCT stand for?
The Joint Contracts Tribunal.