Week 9 (Project Schedule Management) Flashcards

1
Q

Project Time Management (Scheduling)

A

The process used to determine the overall project duration and when activities and events are planned to happen.
This includes identification of activities and their logical dependencies, and estimating of activity durations, taking into account requirements and availability of resources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Activity List

A

shows how the WBS work packages can be subdivided into a list of activities. these are an input into the network diagram, gantt chart and CPM.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Activity Box

A

diagramming method which uses boxes to denote schedule activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Calendar

A
  • Work Days
  • Rest days
  • Holidays
  • Training
  • Number of Calendars
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Milestones

A
  • Unique Number
  • Description
  • Zero Duration= a point in time
  • Start or Finish= an activity, a work package, a project phase or the project itself.
  • Checkpoint
  • Interface= between trades or contractors as one hands over to the other.
  • Data Capture
  • Stage Payment
  • Project Handover
  • Decision-Making
  • Procurement = placement of an order and the receiving of goods
  • Risk
  • Quality
  • Documents= business case, project charter, build-method, execution strategy, closeout report
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Event Gantt Chart

A

shows events at the start and finish of all the activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Trade Off between certain elements

A
  • Scope Management
  • Time Management
  • Cost Management
  • Quality Management
  • Execution Management
  • Procurement Management
  • Resource Management
  • Communication Management
  • Risk Management
  • Project Control
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Activity

A

An activity has a unique activity code or number.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Description

A

An activity has a description. The description should be as informative and clear as possible to distinguish the activity from any other activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Objectives

A

An activity should have an objective, which usually expressed as a deliverable that relates to the scope of work and the project charter.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Responsibility

A

The responsibility for the completion of an activity should be assigned. The responsibility hierarchy starts with the project sponsor assigning responsibility to the completion of the project to the project manager.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Project Plan

A

An activity will be a small part of the project plan. It is important to appreciate how all the individual activities roll up to form a number of deliverables and eventually the complete project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Assumptions

A

An activity is carried out within defined boundaries which are defined as assumptions and constraints.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Constraints

A

Might be imposed by the client
(project sponsor)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Stakeholders

A

An activity will have a number of stakeholders and interested parties who might be impacted upon by the activity and could, in turn, have an impact on the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Logic Relationships

A

An activity has a logical relationship with other activities. This is usually expressed as activities in series or activities in parallel.

17
Q

Lag

A

An activity could have a lead or lag to represent the relative start of finish between one activity state and the next.

18
Q

Duration

A

An activity has a time duration for completing the task, which is from the start to finish of the activity. This is often on a sliding scale depending on the number of available resources.

19
Q

Milestones

A

An activity with zero duration is called a milestone.

20
Q

Calendar

A

An activity has a calendar or work pattern to indicate when the work can be scheduled.

21
Q

Target Date

A

An activity can have a target date. This could be a target start date or a target finish date.

22
Q

Procurement

A

An activity might need to procure materials and services. The resource requirement can be linked to the activity’s schedule to produce a procurement schedule and identify long lead items.

23
Q

Resource Requirements

A

As activity might need resources to perform the work. The resource requirement can be linked to the activity’s schedule to produce a procurement schedule and identify resource overloads.

24
Q

Budget

A

An activity has a budget to fund the work. This can be linked to the schedule to produce a cashflow.

25
Q

S Curve

A

Any parameter can be linked to the activities schedule to produce the S-curve. This helps to model and profile the project and is used in the Earned Value presentation.

26
Q

Quality

A

An activity usually has to be produced to a specific quality.

27
Q

Risk

A

An activity will be subjected to risks that will prevent the activity from the achieving its objectives. These need to be identified and managed.

28
Q

Estimating Data Base

A

A company’s estimating database of tariffs or rates outlines how much the company charges and the man-hours allocated for its list of goods and services.

28
Q

Control

A

An activity need to be expedited, monitored and controlled to guide the activity to achieve its objectives as outlined in the project plan.

29
Q

Activity List

A

Outlines the jobs to be performed to complete the project’s scope of work and achieve the project’s objectives.

30
Q

Scope of Work

A

A measure of the amount of work each activity has to perform to complete the activity.

31
Q

Level of Effort

A

Once an activity’s scope of work has been quantified, this can now be converted into a level of effort (man hours).

32
Q

Level of Resources

A

The level of resources quantifies the number of resources available to perform the work.