Week 9 (Project Schedule Management) Flashcards
Project Time Management (Scheduling)
The process used to determine the overall project duration and when activities and events are planned to happen.
This includes identification of activities and their logical dependencies, and estimating of activity durations, taking into account requirements and availability of resources.
Activity List
shows how the WBS work packages can be subdivided into a list of activities. these are an input into the network diagram, gantt chart and CPM.
Activity Box
diagramming method which uses boxes to denote schedule activities
Calendar
- Work Days
- Rest days
- Holidays
- Training
- Number of Calendars
Milestones
- Unique Number
- Description
- Zero Duration= a point in time
- Start or Finish= an activity, a work package, a project phase or the project itself.
- Checkpoint
- Interface= between trades or contractors as one hands over to the other.
- Data Capture
- Stage Payment
- Project Handover
- Decision-Making
- Procurement = placement of an order and the receiving of goods
- Risk
- Quality
- Documents= business case, project charter, build-method, execution strategy, closeout report
Event Gantt Chart
shows events at the start and finish of all the activities
Trade Off between certain elements
- Scope Management
- Time Management
- Cost Management
- Quality Management
- Execution Management
- Procurement Management
- Resource Management
- Communication Management
- Risk Management
- Project Control
Activity
An activity has a unique activity code or number.
Description
An activity has a description. The description should be as informative and clear as possible to distinguish the activity from any other activity.
Objectives
An activity should have an objective, which usually expressed as a deliverable that relates to the scope of work and the project charter.
Responsibility
The responsibility for the completion of an activity should be assigned. The responsibility hierarchy starts with the project sponsor assigning responsibility to the completion of the project to the project manager.
Project Plan
An activity will be a small part of the project plan. It is important to appreciate how all the individual activities roll up to form a number of deliverables and eventually the complete project.
Assumptions
An activity is carried out within defined boundaries which are defined as assumptions and constraints.
Constraints
Might be imposed by the client
(project sponsor)
Stakeholders
An activity will have a number of stakeholders and interested parties who might be impacted upon by the activity and could, in turn, have an impact on the project.