Week 7 (Feasibility Study) Flashcards
Feasibility Study
An analysis to determine if a course of action is possible within the terms of reference of the project. Work carried out on a project or alternatives to provide a basis for deciding whether or not to proceed.
Realise Benefits
Will the company be able to realise benefits from the project? It can be expressed a financial and non-financial.
Financial Objectives
Will the company make a profit from the operation of the project and achieve minimum acceptable return on its investment?
Positive Cash Flow
The company might be experiencing cash flow problems and would therefore, prefer to only authorise projects with a positive cash flow.
Project Finance
The company’s share price and credit rating will have an impact on the company’s ability to borrow and the cost of borrowing.
Company Resources
The company might want to use only company resources to make the project. If there is insufficient resources available this might have an impact on the project’s build schedule.
Life Cycle Costing
The company might impose certain life cycle costing requirements that look at the long-term cash flow of the project.
Diversify Products
The company might wish to diversify its products range and enter new markets. The project itself might be implement the technology transfer for the company to produce the new products.
Buying Work
During the downturn in the economy, the company’s main priority might be to keep the workforce intact. The strategy of lowering the profit margin and writing off direct costs is often referred to as buying work.
Exports
The company might influence the quotation (usually lower) in an effort to acquire exports to enter new markets or take advantage of export incentives.
Partner
To reduce the level of risk the company might consider taking on a partner who has previous experience in the field of the project.
Industry Relations
Industrial unrest is often caused by conflict over pay and working conditions.
Training
The project might become the training ground for new recruits.
Corporate Schedule
The project’s schedule might be influenced by other company projects or be part of a larger programme.
Approved Suppliers
The project’s procurement suppliers might be limited to the company’s approved suppliers list.
Upgrade
The executive might require the project to be designed in such a way that they have the option to easily upgrade the project as new technology becomes available.
Benefits and Risks
The benefits vs risks should be clearly identified. This is usually quantified in the cost-benefit analysis and should align with the acceptable level of risk outlined in the corporate values statement.
Specifications and Standards
The project must meet certain design specifications, national and international standards.
Build-Method
Can the company physically make the project? The only way to answer this question is by developing a detailed project build-method.
Level of Technology Available
Is the level of technology available sufficient to design, implement and operate the project?
Design Freeze
At what point in the design development should the project manager impose a design freeze?